  1. Compressed Air System Retrofitting Project Improves Productivity at a Foundry (Cast Masters, Bowling Green, OH)

    SciTech Connect (OSTI)

    2002-06-01

    This case study highlights International Truck and Engine Corporation's optimization project on the compressed air system that serves its foundry, Indianapolis Casting Corporation. Due to the project's implementation, the system's efficiency was greatly improved, allowing the foundry to operate with less compressor capacity, which resulted in reduced energy consumption, significant maintenance savings, and more reliable production.

  2. Compressed Air Project Improves Efficiency and Production at Harland Publishing Facility

    SciTech Connect (OSTI)

    2002-05-01

    Case study describing a project which configured a printing machine so that it consumes less compressed air and required lower pressure to operate effectively. Project replicated throughout the company, leading to energy cost savings of $200,000 per year, or 2.9 million kilowatt-hours.

  3. Compressed Air System Project Improves Production at a Candy Making Facility

    SciTech Connect (OSTI)

    2002-03-01

    The H.B. Reese Company successfully completed an upgrade of this compressed air system at its facility in Hershey, PA. The plant took two compressors offline while increasing throughput and quality.

  4. Project PETROL RAM: improving the management of Air Force fuels operations and inventories. Master's thesis

    SciTech Connect (OSTI)

    Frederick, P.R.

    1988-09-01

    The purpose of this research was to provide a handbook on Project PETROL RAM and its ideas for enhancing the base-level fuels operations. This handbook is to serve as an introduction and reference guide to the components, characteristics, and capabilities of the proposed initiative. In preparing this handbook, available information on the structure, operations, and procedures of a typical base Fuels Management Branch was gathered, then condensed and simplified. For added depth and understanding, personal interviews with personnel involved in the design and development of this project were conducted. The research resulted in a handbook that describes, in simplified terminology, the different systems which are being developed under the Project PETROL RAM initiative.

  5. Improving Project Management

    Office of Energy Efficiency and Renewable Energy (EERE)

    On December 19, 2014, the Energy Department released its "Improving Project Management" report, a roadmap to transformation in funding, culture, project ownership, independent oversight and front-end planning from experienced project management leaders.

  6. Interstate Electrification Improvement Project

    SciTech Connect (OSTI)

    Puckette, Margaret; Kim, Jeff

    2015-07-01

    The Interstate Electrification Improvement Project, publicly known as the Shorepower Truck Electrification Project (STEP), started in May 2011 and ended in March 2015. The project grant was awarded by the Department of Energy’s Vehicles Technology Office in the amount of $22.2 million. It had three overarching missions: 1. Reduce the idling of Class 8 tractors when parked at truck stops, to reduce diesel fuel consumption and thus U.S. dependence on foreign petroleum; 2. Stimulate job creation and economic activity as part of the American Reinvestment and Recovery Act of 2009; 3. Reduce greenhouse gas emissions (GHG) from diesel combustion and the carbon footprint of the truck transportation industry. The project design was straightforward. First, build fifty Truck Stop Electrification (TSE) facilities in truck stop parking lots across the country so trucks could plug-in to 110V, 220V, or 480VAC, and shut down the engine instead of idling. These facilities were strategically located at fifty truck stops along major U.S. Interstates with heavy truck traffic. Approximately 1,350 connection points were installed, including 150 high-voltage electric standby Transport Refrigeration Unit (eTRU) plugs--eTRUs are capable of plugging in to shore power1 to cool the refrigerated trailer for loads such as produce, meats and ice cream. Second, the project provided financial incentives on idle reduction equipment to 5,000 trucks in the form of rebates, to install equipment compatible with shore power. This equipment enables drivers to shut down the main engine when parked, to heat or cool their cab, charge batteries, or use other household appliances without idling—a common practice that uses approximately 1 gallon of diesel per hour. The rebate recipients were intended to be the first fleets to plug into Shorepower to save diesel fuel and ensure there is significant population of shore power capable trucks. This two part project was designed to complement each other by

  7. Seneca Compressed Air Energy Storage (CAES) Project

    SciTech Connect (OSTI)

    2012-11-30

    This document provides specifications for the process air compressor for a compressed air storage project, requests a budgetary quote, and provides supporting information, including compressor data, site specific data, water analysis, and Seneca CAES value drivers.

  8. Project Management Improvements Drive Progress

    Energy.gov [DOE]

    WASHINGTON, D.C. – Improving project management has been a top priority of EM’s senior leadership.

  9. Acquisition and Project Management Continuous Improvement Presentation...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    and Project Management Continuous Improvement Presentation Acquisition and Project Management Continuous Improvement Presentation Presentation on Acquisition and Project Management ...

  10. Energy Savings with Acceptable Indoor Air Quality Through Improved...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Savings with Acceptable Indoor Air Quality Through Improved Air Flow Control in Residential Retrofit Energy Savings with Acceptable Indoor Air Quality Through Improved Air Flow ...

  11. Seneca Compressed Air Energy Storage (CAES) Project

    SciTech Connect (OSTI)

    None, None

    2012-11-30

    Compressed Air Energy Storage (CAES) is a hybrid energy storage and generation concept that has many potential benefits especially in a location with increasing percentages of intermittent wind energy generation. The objectives of the NYSEG Seneca CAES Project included: for Phase 1, development of a Front End Engineering Design for a 130MW to 210 MW utility-owned facility including capital costs; project financials based on the engineering design and forecasts of energy market revenues; design of the salt cavern to be used for air storage; draft environmental permit filings; and draft NYISO interconnection filing; for Phase 2, objectives included plant construction with a target in-service date of mid-2016; and for Phase 3, objectives included commercial demonstration, testing, and two-years of performance reporting. This Final Report is presented now at the end of Phase 1 because NYSEG has concluded that the economics of the project are not favorable for development in the current economic environment in New York State. The proposed site is located in NYSEG’s service territory in the Town of Reading, New York, at the southern end of Seneca Lake, in New York State’s Finger Lakes region. The landowner of the proposed site is Inergy, a company that owns the salt solution mining facility at this property. Inergy would have developed a new air storage cavern facility to be designed for NYSEG specifically for the Seneca CAES project. A large volume, natural gas storage facility owned and operated by Inergy is also located near this site and would have provided a source of high pressure pipeline quality natural gas for use in the CAES plant. The site has an electrical take-away capability of 210 MW via two NYSEG 115 kV circuits located approximately one half mile from the plant site. Cooling tower make-up water would have been supplied from Seneca Lake. NYSEG’s engineering consultant WorleyParsons Group thoroughly evaluated three CAES designs and concluded that any

  12. Improving Compressed Air System Performance Third Edition | Department...

    Energy Savers

    Compressed Air System Performance Third Edition Improving Compressed Air System Performance Third Edition PDF icon Improving Compressed Air Sourcebook version 3.pdf More Documents ...

  13. Hopi Tribe Clean Air Partnership Project

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    HOPI TRIBE CLEAN AIR PARTNERSHIP PROJECT Roger Tungovia, Project Manager Ken Lomayestewa, Energy/Utility Specialist HOPI TRIBE Located in Northeast Arizona elevation from 3,900 to 7,500 feet. Land Base: 1.6 million acres - District 6: main residential area; Hopi Partitioned Lands (HPL); and Fee Simple Lands(aboriginal lands) Population: 12,500 plus with 7,500 living on the reservation 12 separate villages (each independent and autonomous from the Tribal Government) and two communities. Tribal

  14. Compressed Air System Optimization Improves Production and saves energy at a Satellite Manufacturer

    SciTech Connect (OSTI)

    2002-05-01

    In 2001, a compressed air improvement project was implemented following an audit on the compressed air system at Boeing Satellite Systems (formerly Hughes Space & Communications Company) in Los Angeles, California.

  15. Acquisition and Project Management Continuous Improvement Presentation |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy and Project Management Continuous Improvement Presentation Acquisition and Project Management Continuous Improvement Presentation Presentation on Acquisition and Project Management Continuous Improvement. Acquisition and Project Management Continuous Improvement presentation (1.43 MB) More Documents & Publications Occupational Safety Performance Voluntary Protection Program Onsite Review, Safeguards and Security - August 2012 Report on Acquisition and Project

  16. Industrial Energy Efficiency Projects Improve Competitiveness...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Energy Efficiency Projects Improve Competitiveness and Protect Jobs Industrial Energy Efficiency Projects Improve Competitiveness and Protect Jobs U.S. Department of Energy (DOE) ...

  17. Chicago Clean Air, Clean Water Project: Environmental Monitoring...

    Office of Scientific and Technical Information (OSTI)

    Chicago Clean Air, Clean Water Project: Environmental Monitoring for a Healthy, Sustainable Urban Future Citation Details In-Document Search Title: Chicago Clean Air, Clean Water ...

  18. Improving Compressed Air System Performance: A Sourcebook for...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Industry, Third Edition Improving Compressed Air System Performance: A Sourcebook for Industry, Third Edition AMO's "Improving Compressed Air System Performance: A Sourcebook for ...

  19. Project Profile: CSP Tower Air Brayton Combustor | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Concentrating Solar Power Project Profile: CSP Tower Air Brayton Combustor Project ... research that are in progress. SunShot Home About the SunShot Initiative Concentrating ...

  20. Improving DOE's Project Controls Integration with Project Management |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy DOE's Project Controls Integration with Project Management Improving DOE's Project Controls Integration with Project Management Improving DOE's Project Controls Integration with Project Management Stephen Korenkiewicz March 24, 2016 Presentation (547.16 KB) Key Resources Internal DOE Tools PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications PMCDP Certification and Equivalency Guidelines PMCDP Certification Review

  1. Alternative Fuels Data Center: Electric Ice Resurfacers Improve Air Quality

    Alternative Fuels and Advanced Vehicles Data Center

    in Minnesota Electric Ice Resurfacers Improve Air Quality in Minnesota to someone by E-mail Share Alternative Fuels Data Center: Electric Ice Resurfacers Improve Air Quality in Minnesota on Facebook Tweet about Alternative Fuels Data Center: Electric Ice Resurfacers Improve Air Quality in Minnesota on Twitter Bookmark Alternative Fuels Data Center: Electric Ice Resurfacers Improve Air Quality in Minnesota on Google Bookmark Alternative Fuels Data Center: Electric Ice Resurfacers Improve Air

  2. Lehigh Southwest Cement Company: Compressed Air System Improvement Saves Energy

    SciTech Connect (OSTI)

    2003-10-01

    In 2001, Lehigh Southwest Cement Company improved the compressed air system at its cement plant in Tehachapi, California. Consequently, the system was able to operate more efficiently with less compressor capacity and at a lower system pressure. The project yielded total annual savings of 895,000 kWh and $199,000. The initial project cost was $417,000, but Southern California Edison provided a $90,000 incentive payment to reduce the cost to $327,000. Simple payback was about 20 months.

  3. Wind Forecasting Improvement Project | Department of Energy

    Energy Savers

    Forecasting Improvement Project Wind Forecasting Improvement Project October 3, 2011 - 12:12pm Addthis This is an excerpt from the Third Quarter 2011 edition of the Wind Program ...

  4. Distributed Wind Competitiveness Improvement Project (Fact Sheet...

    Energy.gov (indexed) [DOE]

    Distributed Wind Competitiveness Improvement Project The Competitiveness Improvement ... (NREL). Manufacturers of small and medium wind turbines are awarded cost-shared grants ...

  5. Seneca Compressed Air Energy Storage (CAES) Project

    SciTech Connect (OSTI)

    None, None

    2012-11-30

    This report provides a review and an analysis of potential environmental justice areas that could be affected by the New York State Electric & Gas (NYSEG) compress air energy storage (CAES) project and identifies existing environmental burden conditions on the area and evaluates additional burden of any significant adverse environmental impact. The review assesses the socioeconomic and demographic conditions of the area surrounding the proposed CAES facility in Schuyler County, New York. Schuyler County is one of 62 counties in New York. Schuyler County’s 2010 population of 18,343 makes it one of the least populated counties in the State (U.S. Census Bureau, 2010). This report was prepared for WorleyParsons by ERM and describes the study area investigated, methods and criteria used to evaluate this area, and the findings and conclusions from the evaluation.

  6. IMPROVING COMPRESSED AIR SYSTEM PERFORMANCE: A SOURCEBOOK FOR INDUSTRY

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    IMPROVING COMPRESSED AIR SYSTEM PERFORMANCE: A SOURCEBOOK FOR INDUSTRY Improving Compressed Air System Performance A Sourcebook for Industry Third Edition U.S. DEPARTMENT OF ENERGY Energy Efficiency & Renewable Energy ADVANCED MANUFACTURING OFFICE IMPROVING COMPRESSED AIR SYSTEM PERFORMANCE: A SOURCEBOOK FOR INDUSTRY ACKNOWLEDGEMENTS Improving Compressed Air System Performance: A Sourcebook for Industry is a cooperative effort of the U.S. Department of Energy's Office of Energy Efficiency

  7. Improving Compressed Air System Performance: A Sourcebook for Industry |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy Industry Improving Compressed Air System Performance: A Sourcebook for Industry This sourcebook is designed to provide compressed air system users with a reference that outlines opportunities for system performance improvements. It is not intended to be a comprehensive technical text on improving compressed air systems, but rather a document that makes compressed air system users aware of the performance improvement potential, details some of the significant

  8. Connecticut Weatherization Project Improves Lives, Receives National

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Recognition | Department of Energy Connecticut Weatherization Project Improves Lives, Receives National Recognition Connecticut Weatherization Project Improves Lives, Receives National Recognition May 6, 2014 - 12:24pm Addthis Donna Hawkins Technology Transfer Specialist, Weatherization Assistance Program Harris Walker Communications Specialist, Weatherization and Intergovernmental Program MORE WEATHERIZATION STORIES Improving Energy Efficiency and Creating Jobs through Weatherization

  9. Class 8 Truck Freight Efficiency Improvement Project

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Daimler Trucks and Buses 1 Super Truck Program: Vehicle Project Review Recovery Act -Class 8 Truck Freight Efficiency Improvement Project Project ID: ARRAVT080 This presentation does not contain any proprietary, confidential, or otherwise restricted information Derek Rotz (PI & Presenter) Dr. Maik Ziegler Daimler Truck North America LLC June 19 th , 2014 Daimler Trucks and Buses 2 Overview * Project start: April 2010 * Project end: March 2015 * Percent complete: 80% * Resolve thermal &

  10. Improving Project Management | Department of Energy

    Energy.gov (indexed) [DOE]

    Secretary of Energy Ernest Moniz has made improving project management a priority at the Energy Department. In August 2013, the Secretary established a special working group that...

  11. Industrial Energy Efficiency Projects Improve Competitiveness...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Rapids, Wisconsin. Photo courtesy of NewPage Wisconsin Systems Inc. Industrial Energy Efficiency Projects Improve Competitiveness and Protect Jobs Recovery Act Funding Supports ...

  12. DOE Announces Competitive Improvement Project Awards | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Competitiveness Improvement Project (CIP), which was announced in January 2013. Bergey Windpower Company of Oklahoma, an initial CIP recipient, used this funding to identify ...

  13. Wind Forecast Improvement Project Southern Study Area Final Report...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Wind Forecast Improvement Project Southern Study Area Final Report Wind Forecast Improvement Project Southern Study Area Final Report Wind Forecast Improvement Project Southern ...

  14. Heating, Ventilation, and Air Conditioning Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Heating, Ventilation, and Air Conditioning Projects Heating, Ventilation, and Air Conditioning Projects AS-IHP System Concept Sketch. Image credit: Oak Ridge National Laboratory Air-Source Integrated Heat Pump Lead Performer: Oak Ridge National Laboratory - Oak Ridge, TN Partner: Lennox Building-Integrated Heat & Moisture Exchange (SBIR Phase 2B) Lead Performer: Architectural Applications - Portland, Oregon Partner: Oregon State University - Corvallis, Oregon Left: Environmental chamber to

  15. Improving the Department's Management of Projects

    Energy.gov [DOE]

    DOE is managing some of the largest, most complex, and technically challenging projects in the public or private sector. Many are one-of-a-kind projects that involve the risks and challenges of nuclear operations. The Department made significant progress over the past five years in improving overall project management, and in 2013 the GAO narrowed its High-Risk List focus at the Department to NNSA and EM projects valued at more than $750 million. Based on this progress, this secretarial memorandum makes improving project management a continuing priority.

  16. NEUP Project Selections_September212011_IRP and Infrastructure Improvements

    Office of Energy Efficiency and Renewable Energy (EERE)

    Projects selections for NEUP 2011 under Integrated Research Projects and University Research Infrastructure Improvements.

  17. Improving Compressed Air System Performance: A Sourcebook for Industry,

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Third Edition | Department of Energy Industry, Third Edition Improving Compressed Air System Performance: A Sourcebook for Industry, Third Edition AMO's "Improving Compressed Air System Performance: A Sourcebook for Industry, Third Edition" has been recently revised introducing industry to compressed air systems, performance opportunities and where they can find help on optimizing these important industrial systems. Over the years AMO has worked with the Compressed Air Challenge

  18. Improving Air Quality with Solar Energy

    DOE R&D Accomplishments [OSTI]

    2008-04-01

    This fact sheet series highlights how renewable energy and energy efficiency technologies can and are being used to reduce air emissions and meet environmental goals, showcasing case studies and technology-specific topics. This one focus on solar energy technologies.

  19. Recommendations to Improve EVM and Project Management Integration...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Recommendations to Improve EVM and Project Management Integration in the DOE Recommendations to Improve EVM and Project Management Integration in the DOE Significant improvements ...

  20. Savings Project: Insulate and Air Seal Floors Over Unconditioned Garages |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy and Air Seal Floors Over Unconditioned Garages Savings Project: Insulate and Air Seal Floors Over Unconditioned Garages Addthis Project Level Easy Energy Savings Depend on energy cost, R-value increase, and airtightness of newly insulated floor compared to existing. Time to Complete 4-8 hours Overall Cost $0.60 to $1.00 PER SQUARE FOOT FOR R-30 BATTS Careful air sealing and insulation between an unconditioned garage and the conditioned space above can increase comfort,

  1. Project Hanford management contract quality improvement project management plan

    SciTech Connect (OSTI)

    ADAMS, D.E.

    1999-03-25

    On July 13, 1998, the U.S. Department of Energy, Richland Operations Office (DOE-RL) Manager transmitted a letter to Fluor Daniel Hanford, Inc. (FDH) describing several DOE-RL identified failed opportunities for FDH to improve the Quality Assurance (QA) Program and its implementation. In addition, DOE-RL identified specific Quality Program performance deficiencies. FDH was requested to establish a periodic reporting mechanism for the corrective action program. In a July 17, 1998 response to DOE-RL, FDH agreed with the DOE concerns and committed to perform a comprehensive review of the Project Hanford Management Contract (PHMC) QA Program during July and August, 1998. As a result, the Project Hanford Management Contract Quality Improvement Plan (QIP) (FDH-3508) was issued on October 21, 1998. The plan identified corrective actions based upon the results of an in-depth Quality Program Assessment. Immediately following the scheduled October 22, 1998, DOE Office of Enforcement and Investigation (EH-10) Enforcement Conference, FDH initiated efforts to effectively implement the QIP corrective actions. A Quality Improvement Project (QI Project) leadership team was assembled to prepare a Project Management Plan for this project. The management plan was specifically designed to engage a core team and the support of representatives from FDH and the major subcontractors (MSCs) to implement the QIP initiatives; identify, correct, and provide feedback as to the root cause for deficiency; and close out the corrective actions. The QI Project will manage and communicate progress of the process.

  2. Improving Compressed Air System Performance: A Sourcebook for Industry

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Energy Efficiency and Renewable Energy One in a series of industrial energy efficiency sourcebooks a sourcebook for industry Bringing you a prosperous future where energy is clean, abundant, reliable, and affordable Improving Compressed Air System Performance Acknowledgments Improving Compressed Air System Performance: A Sourcebook for Industry is a cooperative effort of the U.S. Department of Energy's Office of Energy Efficiency and Renewable Energy (EERE) BestPractices and the Compressed Air

  3. Lower Rio Grande Valley transboundary air pollution project (TAPP). Project report 1996--1997

    SciTech Connect (OSTI)

    Mukerjee, S.; Shadwick, D.S.; Dean, K.E.; Carmichael, L.Y.; Bowser, J.J.

    1999-04-01

    The Lower Rio Grande Valley Transboundary Air Pollution Project (TAPP) was a US-Mexico Border XXI project to find out if air pollutants were moving across the border from Mexico into the Lower Rio Grande Valley of Texas and to see what levels of air pollutants were present. Ambient measurements and meteorology were collected data for a year (March 1996-March 1997) at three fixed sites in and near Brownsville, Texas very close to the US-Mexico border on a continuous and 24-h internal basis. Overall levels of air pollution were similar to or lower than other areas in Texas and elsewhere. Based on wind sector analyses, transport of air pollution across the border did not appear to adversely impact air quality on the US side of the Valley. Southeasterly winds from the Gulf of Mexico were largely responsible for the clean air conditions.

  4. Safety Improvements, Project Progress at Hanford Site's Plutonium...

    Office of Environmental Management (EM)

    Safety Improvements, Project Progress at Hanford Site's Plutonium Finishing Plant Safety Improvements, Project Progress at Hanford Site's Plutonium Finishing Plant May 16, 2016 - ...

  5. Energy Department Announces Five Research Projects to Improve...

    Energy Savers

    Research Projects to Improve Mining Efficiency Energy Department Announces Five Research Projects to Improve Mining Efficiency May 5, 2005 - 12:42pm Addthis WASHINGTON, DC - As ...

  6. FY 2016 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    6 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2016 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  7. FY 2013 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    3 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2013 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  8. FY 2010 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    0 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2010 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  9. FY 2009 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    9 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2009 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  10. Contract and Project Management Improvement (CPMI) Closure Report...

    Energy Savers

    Contract and Project Management Improvement (CPMI) Closure Report -- April 2012 Contract and Project Management Improvement (CPMI) Closure Report -- April 2012 The Department of ...

  11. FY 2011 Overall Contract and Project Management Improvement Performanc...

    Energy.gov (indexed) [DOE]

    More Documents & Publications FY 2013 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2014 Overall Contract and Project Management Improvement ...

  12. FY 2015 Overall Contract and Project Management Improvement Performanc...

    Energy Savers

    5 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2015 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  13. FY 2008 Overall Contract and Project Management Improvement Performanc...

    Office of Environmental Management (EM)

    8 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2008 Overall Contract and Project Management Improvement Performance Metrics and Targets FY ...

  14. FY 2014 Overall Contract and Project Management Improvement Performanc...

    Office of Environmental Management (EM)

    4 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2014 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  15. FY 2012 Overall Contract and Project Management Improvement Performanc...

    Energy Savers

    2 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2012 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  16. Improving Compressed Air System Performance: A Sourcebook for Industry

    SciTech Connect (OSTI)

    2003-11-01

    NREL will produce this sourcebook for DOE's Industrial Technologies Office as part of a series of documents on industrial energy equipment. The sourcebook is a reference for industrial compressed air system users, outlining opportunities to improve system efficiency.

  17. Improved zinc electrode and rechargeable zinc-air battery

    DOE Patents [OSTI]

    Ross, P.N. Jr.

    1988-06-21

    The invention comprises an improved rechargeable zinc-air cell/battery having recirculating alkaline electrolyte and a zinc electrode comprising a porous foam support material which carries the active zinc electrode material. 5 figs.

  18. Distributed Wind Competitiveness Improvement Project Fact Sheet

    Energy.gov [DOE]

    The Competitiveness Improvement Project (CIP) is a periodic solicitation through the U.S. Department of Energy and its National Renewable Energy Laboratory. Manufacturers of small and medium wind turbines are awarded cost-shared grants via a competitive process to optimize their designs, develop advanced manufacturing processes, and perform turbine testing. The goals of the CIP are to make wind energy cost competitive with other distributed generation technology and increase the number of wind turbine designs certified to national testing standards.

  19. Improving Project Management at the Department of Energy | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Energy Improving Project Management at the Department of Energy Improving Project Management at the Department of Energy December 19, 2014 - 12:15pm Addthis Improving Project Management at the Department of Energy John J. MacWilliams John J. MacWilliams Associate Deputy Secretary Read the Report Learn more by reading the full Improving Project Management report. Secretary Ernest Moniz has made improving project management a priority at the Energy Department. In August 2013, the Secretary

  20. Secretary's 2014 Award for Project Management Improvement | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Energy for Project Management Improvement Secretary's 2014 Award for Project Management Improvement Nuclear Materials Safeguards & Security Upgrades (NMSSUP) Project (The National Nuclear Security Administration) (855.47 KB) More Documents & Publications 2014 Awards for Project Management Secretary's 2014 Achievement Awards Acquisition and Project Management Awards Presentations - Ingrid Kolb, Director, Office of Management

  1. Improving the efficiency of residential air-distribution systems in California, Phase 1

    SciTech Connect (OSTI)

    Modera, M.; Dickerhoff, D.; Jansky, R.; Smith, B.

    1992-06-01

    This report describes the results of the first phase of a multiyear research project. The project`s goal is to investigate ways to improve the efficiency of air-distribution systems in detached, single-family residences in California. First-year efforts included: A survey of heating, ventilating, and air conditioning (HVAC) contractors in California. A 31-house field study of distribution-system performance based on diagnostic measurements. Development of an integrated air-flow and thermal-simulation tool for investigating residential air-distribution system performance. Highlights of the field results include the following: Building envelopes for houses built after 1979 appear to be approximately 30% tighter. Duct-system tightness showed no apparent improvement in post-1979 houses. Distribution-fan operation added an average of 0.45 air changes per hour (ACH) to the average measured rate of 0.24 ACH. The simulation tool developed is based on DOE-2 for the thermal simulations and on MOVECOMP, an air-flow network simulation model, for the duct/house leakage and flow interactions. The first complete set of simulations performed (for a ranch house in Sacramento) indicated that the overall heating-season efficiency of the duct systems was approximately 65% to 70% and that the overall cooling-season efficiency was between 60% and 75%. The wide range in cooling-season efficiency reflects the difference between systems with attic return ducts and those with crawl-space return ducts, the former being less efficient. The simulations also indicated that the building envelope`s UA-value, a measurement of thermoconductivity, did not have a significant impact on the overall efficiency of the air-distribution system.

  2. The Wind Forecast Improvement Project (WFIP): A Public/Private...

    Energy.gov (indexed) [DOE]

    The Wind Forecast Improvement Project (WFIP) is a U. S. Department of Energy (DOE) sponsored research project whose overarching goals are to improve the accuracy of short-term wind ...

  3. J.R. Simplot: Burner Upgrade Project Improves Performance and...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy at a Large Food Processing Plant J.R. Simplot: Burner Upgrade Project Improves Performance and Saves ...

  4. Joint transmission system projects to improve system reliability

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    County PUD, 425-783-8444 Joint transmission system projects to improve system reliability First major regional electric grid improvements in decades prepare the area for the...

  5. Recommendations to Improve EVM and Project Management Integration in the

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    DOE | Department of Energy Recommendations to Improve EVM and Project Management Integration in the DOE Recommendations to Improve EVM and Project Management Integration in the DOE Significant improvements can be made by DOE to improve EVM and project management integration by focusing on two prevailing themes: (1) Trust based project management approach, and (2) Formal knowledge transfer process. Many of the recommendations contained in this report relate in some aspect to one or both of

  6. Interstate Grid Electrification Improvement Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Interstate Grid Electrification Improvement Project Interstate Grid Electrification Improvement Project 2012 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting arravt070_vss_gustafson_2012_o.pdf (3.62 MB) More Documents & Publications Interstate Grid Electrification Improvement Project Interstate Grid Electrification Improvement Project Vehicle Technologies Office: 2011 Vehicle and Systems Simulation and Testing R&D Annual

  7. Contract and Project Management Improvement (CPMI) Closure Report -- April

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    2012 | Department of Energy Contract and Project Management Improvement (CPMI) Closure Report -- April 2012 Contract and Project Management Improvement (CPMI) Closure Report -- April 2012 The Department of Energy (DOE) is committed to making continuous improvements in contract and project management performance. One of the first steps the Department took to improve contract and project management was to hold a Root Cause Analysis (RCA) Workshop in 2007. Following the RCA Workshop, DOE

  8. Greater Green River Basin Production Improvement Project

    SciTech Connect (OSTI)

    DeJarnett, B.B.; Lim, F.H.; Calogero, D.

    1997-10-01

    The Greater Green River Basin (GGRB) of Wyoming has produced abundant oil and gas out of multiple reservoirs for over 60 years, and large quantities of gas remain untapped in tight gas sandstone reservoirs. Even though GGRB production has been established in formations from the Paleozoic to the Tertiary, recent activity has focused on several Cretaceous reservoirs. Two of these formations, the Ahnond and the Frontier Formations, have been classified as tight sands and are prolific producers in the GGRB. The formations typically naturally fractured and have been exploited using conventional well technology. In most cases, hydraulic fracture treatments must be performed when completing these wells to to increase gas production rates to economic levels. The objectives of the GGRB production improvement project were to apply the concept of horizontal and directional drilling to the Second Frontier Formation on the western flank of the Rock Springs Uplift and to compare production improvements by drilling, completing, and testing vertical, horizontal and directionally-drilled wellbores at a common site.

  9. Lehigh Southwest Cement Company: Compressed Air System Improvement Saves Energy at a Lehigh Southwest Cement Plant

    SciTech Connect (OSTI)

    Not Available

    2003-10-01

    In 2001, Lehigh Southwest Cement Company improved the compressed air system at its cement plant in Tehachapi, California. Consequently, the system was able to operate more efficiently with less compressor capacity and at a lower system pressure. The project yielded total annual savings of 895,000 kWh and $199,000. The initial project cost was $417,000, but Southern California Edison provided a $90,000 incentive payment to reduce the cost to $327,000. Simple payback was about 20 months.

  10. A methodology for evaluating air pollution strategies to improve the air quality in Mexico City

    SciTech Connect (OSTI)

    Barrera-Roldan, A.S.; Guzman, F.; Hardie, R.W.; Thayer, G.R.

    1995-05-01

    The Mexico City Air Quality Research Initiative has developed a methodology to assist decision makers in determining optimum pollution control strategies for atmospheric pollutants. The methodology introduces both objective and subjective factors in the comparison of various strategies for improving air quality. Strategies or group of options are first selected using linear programming. These strategies are then compared using Multi-Attribute Decision Analysis. The decision tree for the Multi-Attribute Decision Analysis was generated by a panel of experts representing the organizations in Mexico that are responsible for formulating policy on air quality improvement. Three sample strategies were analyzed using the methodology: one to reduce ozone by 33% using the most cost effective group of options, the second to reduce ozone by 43% using the most cost effective group of options and the third to reduce ozone by 43% emphasizing the reduction of emissions from industrial sources. Of the three strategies, the analysis indicated that strategy 2 would be the preferred strategy for improving air quality in Mexico City.

  11. NNSA continues improvements in best practices for acquisition and project

    National Nuclear Security Administration (NNSA)

    management | National Nuclear Security Administration | (NNSA) continues improvements in best practices for acquisition and project management Monday, September 19, 2016 - 2:27pm Participants in the third annual Federal Project Director and Project Integrator Training Session in Albuquerque, N.M. In July, NNSA's Office of Acquisition and Project Management hosted the third annual Federal Project Director and Project Integrator Training Session in Albuquerque, N.M. This training is one of

  12. 2014 QA Improvement Project Plan (August 2014).pdf

    Office of Environmental Management (EM)

    4 Awards for Project Management 2014 Awards for Project Management Federal Project Director of the Year for 2014: Pepin Carolan (Office of Science) Secretary's Award of Excellence: Numi Off-axis electron neutrino (νe) Appearance (NOνA) Project (Office of Science) Secretary's Achievement Awards: Seismic Life-Safety, Modernization, and Replacement of General Purpose Buildings, Phase 2 Project (Office of Science) Security Improvements Project (The National Nuclear Security Administration) Energy

  13. ENHANCEMENT OF ENVIRONMENTAL SAMPLING THROUGH AN IMPROVED AIR MONITORING TECHNIQUE

    SciTech Connect (OSTI)

    Hanks, D.

    2010-06-07

    Environmental sampling (ES) is a key component of International Atomic Energy Agency (IAEA) safeguarding approaches throughout the world. Performance of ES (e.g. air, water, vegetation, sediments, soil and biota) supports the IAEAs mission of drawing conclusions concerning the absence of undeclared nuclear material or nuclear activities in a State and has been available since the introduction of safeguards strengthening measures approved by the IAEA Board of Governors (1992-1997). A recent step-change improvement in the gathering and analysis of air samples at uranium/plutonium bulk handling facilities is an important addition to the international nuclear safeguards inspector's toolkit. Utilizing commonly used equipment throughout the IAEA network of analytical laboratories for particle analysis, researchers are developing the next generation of ES equipment for air grab and constant samples. Isotopic analysis of collected particles from an Aerosol Contaminant Extractor (ACE) silicon substrate has been performed with excellent results in determining attribute and isotopic composition of chemical elements present in an actual test-bed sample. The new collection equipment will allow IAEA nuclear safeguards inspectors to develop enhanced safeguarding approaches for complicated facilities. This paper will explore the use of air monitoring to establish a baseline environmental signature of a particular facility that could be used for comparison of consistencies in declared operations. The implementation of air monitoring will be contrasted against the use of smear ES when used during unannounced inspections, design information verification, limited frequency unannounced access, and complementary access visits at bulk handling facilities. Technical aspects of the air monitoring device and the analysis of its environmental samples will demonstrate the essential parameters required for successful application of the system.

  14. Report on Acquisition and Project Management Continuous Improvement |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy on Acquisition and Project Management Continuous Improvement Report on Acquisition and Project Management Continuous Improvement EM senior management has committed to extensive management reforms and has completed several robust improvements in contract and project management. Additional improvement initiatives are continuing and this document outlines the consolidated plan of these initiatives in a top-down framework of EM vision, goals, strategies, performance metrics,

  15. Upcoming Funding Opportunity for Wind Forecasting Improvement Project in

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Complex Terrain | Department of Energy Wind Forecasting Improvement Project in Complex Terrain Upcoming Funding Opportunity for Wind Forecasting Improvement Project in Complex Terrain February 12, 2014 - 10:47am Addthis On February 11, 2014 the Wind Program announced a Notice of Intent to issue a funding opportunity entitled "Wind Forecasting Improvement Project in Complex Terrain." By researching the physical processes that take place in complex terrain, this funding would improve

  16. 2012 Quality Assurance Improvement Project Plan

    Office of Environmental Management (EM)

    ... Committee Focus Area 1 - Adequate NQA-1 Suppliers DOE Lead: Christian Palay EFCOG ... Focus Areas Project Focus Area 1 -NQA-1 Suppliers Target Completion Date: ...

  17. Improving\tProject\tManagement

    Office of Environmental Management (EM)

    ... system projects, and report progress (in accordance ... Executive role should be delegated to Under Secretary-level. Establish a Portfolio Review Board to provide ...

  18. Raytheon: Compressed Air System Upgrade Saves Energy and Improves Performance

    SciTech Connect (OSTI)

    Not Available

    2005-04-01

    In 2003, Raytheon Company upgraded the efficiency of the compressed air system at its Integrated Air Defense Center in Andover, Massachusetts, to save energy and reduce costs. Worn compressors and dryers were replaced, a more sophisticated control strategy was installed, and an aggressive leak detection and repair effort was carried out. The total cost of these improvements was $342,000; however, National Grid, a utility service provider, contributed a $174,000 incentive payment. Total annual energy and maintenance cost savings are estimated at $141,500, and energy savings are nearly 1.6 million kWh. This case study was prepared for the U.S. Department of Energy's Industrial Technologies Program.

  19. Improved Estimates of Air Pollutant Emissions from Biorefinery

    SciTech Connect (OSTI)

    Tan, Eric C. D.

    2015-11-13

    We have attempted to use detailed kinetic modeling approach for improved estimation of combustion air pollutant emissions from biorefinery. We have developed a preliminary detailed reaction mechanism for biomass combustion. Lignin is the only biomass component included in the current mechanism and methane is used as the biogas surrogate. The model is capable of predicting the combustion emissions of greenhouse gases (CO2, N2O, CH4) and criteria air pollutants (NO, NO2, CO). The results are yet to be compared with the experimental data. The current model is still in its early stages of development. Given the acknowledged complexity of biomass oxidation, as well as the components in the feed to the combustor, obviously the modeling approach and the chemistry set discussed here may undergo revision, extension, and further validation in the future.

  20. TYPE A FISSILE PACKAGING FOR AIR TRANSPORT PROJECT OVERVIEW

    SciTech Connect (OSTI)

    Eberl, K.; Blanton, P.

    2013-10-11

    This paper presents the project status of the Model 9980, a new Type A fissile packaging for use in air transport. The Savannah River National Laboratory (SRNL) developed this new packaging to be a light weight (<150-lb), drum-style package and prepared a Safety Analysis for Packaging (SARP) for submission to the DOE/EM. The package design incorporates unique features and engineered materials specifically designed to minimize packaging weight and to be in compliance with 10CFR71 requirements. Prototypes were fabricated and tested to evaluate the design when subjected to Normal Conditions of Transport (NCT) and Hypothetical Accident Conditions (HAC). An overview of the design details, results of the regulatory testing, and lessons learned from the prototype fabrication for the 9980 will be presented.

  1. 2012 Quality Assurance Improvement Project Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    2 Quality Assurance Improvement Project Plan 2012 Quality Assurance Improvement Project Plan This Project Plan is jointly developed by the Department of Energy (DOE) Office of Environmental Management (EM) and the Energy Facility Contractors Group (EFCOG), to provide execution support to the EM Quality Assurance (QA) Corporate Board. The Board serves a vital and critical role in ensuring that the EM mission is completed safely, correctly, and efficiently. 2012 Quality Assurance Improvement

  2. Funding Opportunity Announcement for Wind Forecasting Improvement Project

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    in Complex Terrain | Department of Energy Funding Opportunity Announcement for Wind Forecasting Improvement Project in Complex Terrain Funding Opportunity Announcement for Wind Forecasting Improvement Project in Complex Terrain April 4, 2014 - 9:47am Addthis On April 4, 2014 the U.S. Department of Energy announced a $2.5 million funding opportunity entitled "Wind Forecasting Improvement Project in Complex Terrain." By researching the physical processes that take place in complex

  3. Wind Forecast Improvement Project Southern Study Area Final Report |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy Wind Forecast Improvement Project Southern Study Area Final Report Wind Forecast Improvement Project Southern Study Area Final Report Wind Forecast Improvement Project Southern Study Area Final Report.pdf (15.76 MB) More Documents & Publications QER - Comment of Edison Electric Institute (EEI) 1 QER - Comment of Canadian Hydropower Association Team roster: Dan Paikowsky, Management; Christian Bain, Entrepreneurship; Noah Meunier, Mechanical Engineering &

  4. NREL Announces Two New Competitiveness Improvement Project Awards |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy NREL Announces Two New Competitiveness Improvement Project Awards NREL Announces Two New Competitiveness Improvement Project Awards September 12, 2014 - 10:39am Addthis A photo of a wind turbine from the point of view of looking upward at the blades and nacelle. In July, the U.S. Department of Energy's (DOE's) National Renewable Energy Laboratory (NREL) announced two new Competitiveness Improvement Project (CIP) awards. Northern Power Systems of Barre, Vermont, and Urban

  5. PROJECT PROFILE: Improving PV performance Estimates in the System...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    This project will improve the forecasting of lifetime PV system performance as well as operations and maintenance costs by incorporating the Photovoltaic Reliability and ...

  6. 2010 Quality Assurance Improvement Project Plan

    Energy.gov [DOE]

    This Project Plan is jointly developed by  the Department of Energy (DOE) Office of Environmental Management (EM) and the Energy Facility Contractors Group (EFCOG), to provide execution support to...

  7. NREL Distributes Wind Competitiveness Improvement Project Round Four

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Funding - News Releases | NREL NREL Distributes Wind Competitiveness Improvement Project Round Four Funding May 13, 2016 The Energy Department's (DOE) National Renewable Energy Laboratory (NREL) is awarding four subcontracts under the fourth round of funding through DOE's Distributed Wind Competitiveness Improvement Project (CIP). The CIP aims to help manufacturers of small and mid-size wind turbines improve their turbine design and manufacturing processes while reducing costs and improving

  8. Class 8 Truck Freight Efficiency Improvement Project

    Energy.gov (indexed) [DOE]

    Derek Rotz (PI & Presenter) Dr. Maik Ziegler Daimler Truck ... controls integration (aux, hybrid, powertrain, waste heat, ... 20% improvement through a heavy-duty diesel engine capable ...

  9. Smart Grid Projects Are Improving Performance and Helping Consumers Better

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Manage their Energy Use | Department of Energy Projects Are Improving Performance and Helping Consumers Better Manage their Energy Use Smart Grid Projects Are Improving Performance and Helping Consumers Better Manage their Energy Use November 14, 2014 - 5:07pm Addthis Hank Kenchington Hank Kenchington Deputy Assistant Secretary, Cybersecurity and Emerging Threats Research and Development After nearly five years, the 131 smart grid projects funded through the 2009 Recovery Act are nearing

  10. BETO Project Improves Production of Renewable Chemical from Cellulosic

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Feedstocks | Department of Energy Project Improves Production of Renewable Chemical from Cellulosic Feedstocks BETO Project Improves Production of Renewable Chemical from Cellulosic Feedstocks October 13, 2015 - 1:43pm Addthis Renewable chemical company Genomatica made significant progress toward increasing the range of feedstocks that can be used to commercially produce high-quality bio-based chemicals, in a project funded by the Energy Department's Bioenergy Technologies Office (BETO).

  11. FY 2008 Overall Contract and Project Management Improvement Performance

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Metrics and Targets | Department of Energy 8 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2008 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2008 4th Quarter Metrics Final -- Overall Contract and Project Management Performance Metrics and Targets. FY 2008 4th Quarter Metrics (71.09 KB) Key Resources Internal DOE Tools PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents

  12. 2014 Quality Assurance Improvement Project Plan

    Energy.gov [DOE]

    This Project Plan is jointly developed by the Department of Energy (DOE) Office of Environmental Management (EM) and the Energy Facility Contractors Group (EFCOG), to provide execution support to the EM Quality Assurance (QA) Corporate Board. The Board serves a vital and critical role in ensuring that the EM mission is completed safely, correctly, and efficiently.

  13. 2015 Quality Assurance Improvement Project Plan

    Energy.gov [DOE]

    This Project Plan is jointly developed by the Department of Energy (DOE) Office of Environmental Management (EM) and the Energy Facility Contractors Group (EFCOG), to provide execution support to the EM Quality Assurance (QA) Corporate Board. The Board serves a vital and critical role in ensuring that the EM mission is completed safely, correctly, and efficiently.

  14. Savings Project: How to Seal Air Leaks with Caulk | Department...

    Office of Environmental Management (EM)

    alykat6737403523">Alyson Hurt. Sealing air leaks around windows and doors can save you energy and money. | Courtesy of Flickr user Alyson Hurt. Air leaks can waste a...

  15. Solar Forecast Improvement Project | Department of Energy

    Energy Savers

    Energy Systems Integration » Solar Energy Grid Integration Systems-Advanced Concepts Solar Energy Grid Integration Systems-Advanced Concepts On September 1, 2011, DOE announced $25.9 million to fund eight solar projects that are targeting ways to develop power electronics and build smarter, more interactive systems and components so that solar energy can be integrated into the electric power distribution and transmission grid at higher levels. Part of the SunShot Systems Integration

  16. Outage project productivity improvement of TVA fossil

    SciTech Connect (OSTI)

    Picard, H.E.; Seay, C.R. Jr.

    1996-10-01

    Competition in the utility industry forces management to look closely at the cost effectiveness of power plant outage projects. At TVA Fossil and Hydro Power, innovative work measurement is proving effective as a project management tool to do more with less. Labor-hours to complete outage work scopes are reduced by some 20 to 30%, not by working harder or sacrificing safety, or quality, but by working and managing smarter. Fossil power plant outages and shutdowns are costly. They are labor-intensive construction projects, often with expanding work scope, and executed on a fast track. Outage work is inherently complex and dynamic, and often unpredictable. Many activities and tasks must be integrated, coordinated and completed safely and efficiently by multiple crafts and work groups. As a result, numerous productivity factors can influence the cost and schedule of outage completion. This provides owners, contractors and labor with unique opportunities for competitive advantage--by making radical changes in how they manage labor-hours and time.

  17. CXD 4604, Development CONOPS Improvement Project (4604)

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    effort to improve its facility conditions. The focus will be on removal of accumulated trash, de-cluttering of work areas, and identification and removal of any unneeded materials...

  18. Class 8 Truck Freight Efficiency Improvement Project

    Energy.gov (indexed) [DOE]

    least 20% improvement through a heavy-duty diesel engine capable of ... Tractor Trailer 16.5% 2.4% (incl. hybrid) NEXT STEP: build the truck Approach Daimler Trucks and Buses ...

  19. NAPA Collaboration Project: Worker Dialogue to Improve Worker Health,

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Safety and Security | Department of Energy NAPA Collaboration Project: Worker Dialogue to Improve Worker Health, Safety and Security NAPA Collaboration Project: Worker Dialogue to Improve Worker Health, Safety and Security Beginning on June 14, 2010, the Office of Health, Safety and Security (HSS) at DOE, in partnership with the nonprofit, non-partisan National Academy of Public Administration, will host A Worker Dialogue: Improving Health, Safety and Security at DOE. This web-based

  20. NREL Provides Guidance to Improve Air Mixing and Thermal Comfort...

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    proper air mixing and thermal comfort in homes. As U.S. homes become more energy efficient, heating, ventilation, and cooling (HVAC) systems will be downsized, and the air flow ...

  1. Montenay recyclable trash improvements (RTI) project

    SciTech Connect (OSTI)

    Smith, D.M.; Smith, E.F.

    1998-07-01

    Municipal trash is converted to a solid fuel for an off-site boiler installation. Existing Miami-Dade Resources Recovery Facilities were modified and new processing facilities were added at a cost of $26 million dollars. This major recycling project was developed over three years, was built in 1996 and was successfully commissioned in 1997. Process machinery includes three modified shredders with a final throughput capacity of 110 tons per hour, conveyors, trommels, and raw product separation equipment. The RTI process makes commercial grade biomass fuel and two soil products. A discussion of process design and testing is presented. Other bulk material handling issues such as delivery contracts for raw trash ad remote site fuel delivery is included. Elements of the plant designs for truck tipping, rejects separation, process and storage buildings are also discussed.

  2. Hybrid and Advanced Air Cooling Geothermal Lab Call Project ...

    Open Energy Information (Open El) [EERE & EIA]

    various strategies for boosting the performance of air coolers in hot weather. Computer modeling and experimental measurements have been done on the use of evaporative media...

  3. NREL Releases RFP for Distributed Wind Turbine Competitiveness Improvement Projects

    Office of Energy Efficiency and Renewable Energy (EERE)

    In support of DOE's efforts to further develop distributed wind technology, NREL's National Wind Technology Center has released a Request for Proposal for the following Distributed Wind Turbine Competitiveness Improvement Projects on the Federal Business

  4. Energy Department Announces Five Research Projects to Improve Mining

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Efficiency | Department of Energy Research Projects to Improve Mining Efficiency Energy Department Announces Five Research Projects to Improve Mining Efficiency May 5, 2005 - 12:42pm Addthis WASHINGTON, DC - As part of the Bush Administration's continuing effort to make more efficient use of America's domestic energy resources while maintaining sound stewardship of the environment, the U.S. Department of Energy (DOE) today announced the selection of five new research and development

  5. Security Improvements Project Completed Ahead of Schedule, $20 Million

    National Nuclear Security Administration (NNSA)

    Under Budget | National Nuclear Security Administration | (NNSA) Security Improvements Project Completed Ahead of Schedule, $20 Million Under Budget April 07, 2014 The National Nuclear Security Administration's (NNSA) Security Improvements Project (SIP) was recently completed ahead of schedule and approximately $20 million under its original budget of $72 million. File 2014-04-08 SIP.docx NPO Press Releases September 2016 (1) August 2016 (1) May 2016 (1) February 2016 (1) January 2016 (1)

  6. Security Improvements Project Completed Ahead of Schedule, $20 Million

    National Nuclear Security Administration (NNSA)

    Under Budget | National Nuclear Security Administration | (NNSA) Security Improvements Project Completed Ahead of Schedule, $20 Million Under Budget April 07, 2014 WASHINGTON, D.C. - The National Nuclear Security Administration's (NNSA) Security Improvements Project (SIP) was recently completed ahead of schedule and approximately $20 million under its original budget of $72 million. SIP upgraded security at Y-12 by replacing existing alarm stations and access control systems with Argus, a

  7. Class 8 Truck Freight Efficiency Improvement Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    2 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting arravt080_vss_rotz_2012_o.pdf (2.58 MB) More Documents & Publications Vehicle Technologies Office Merit Review 2014: Class 8 Truck Freight Efficiency Improvement Project Class 8 Truck Freight Efficiency Improvement Project Vehicle Technologies Office Merit Review 2015: Class 8 Truck Freight Efficiency

  8. Class 8 Truck Freight Efficiency Improvement Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    3 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting arravt080_vss_rotz_2013_o.pdf (1.46 MB) More Documents & Publications Vehicle Technologies Office Merit Review 2015: Class 8 Truck Freight Efficiency Improvement Project Vehicle Technologies Office Merit Review 2014: Class 8 Truck Freight Efficiency Improvement Project Class 8 Truck Freight Efficiency

  9. FY 2009 Overall Contract and Project Management Improvement Performance

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Metrics and Targets | Department of Energy 9 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2009 Overall Contract and Project Management Improvement Performance Metrics and Targets Overall Contract and Project Management Performance Metrics and Targets for FY 2009, first quarter through fourth quarter. FY 2009 1st Quarter Metrics (71.1 KB) FY 2009 2nd Quarter Metrics (68.4 KB) FY 2009 3rd Quarter Metrics (71.31 KB) FY 2009 4th Quarter Metrics (74.16

  10. FY 2013 Overall Contract and Project Management Improvement Performance

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Metrics and Targets | Department of Energy 3 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2013 Overall Contract and Project Management Improvement Performance Metrics and Targets Overall Contract and Project Management Performance Metrics and Targets for FY 2013, first quarter through fourth quarter. FY 2013 1st Quarter Metrics (36.93 KB) FY 2013 2nd Quarter Metrics (36.62 KB) FY 2013 3rd Quarter Metrics (37.04 KB) FY 2013 4th Quarter Metrics (37.15

  11. An Innovative Reactor Technology to Improve Indoor Air Quality

    SciTech Connect (OSTI)

    Rempel, Jane

    2013-03-30

    As residential buildings achieve tighter envelopes in order to minimize energy used for space heating and cooling, accumulation of indoor air pollutants such as volatile organic compounds (VOCs), becomes a major concern causing poor air quality and increased health risks. Current VOC removal methods include sorbents, ultraviolet photocatalytic oxidation (UVPCO), and increased ventilation, but these methods do not capture or destroy all VOCs or are prohibitively expensive to implement. TIAX's objective in this program was to develop a new VOC removal technology for residential buildings. This novel air purification technology is based on an innovative reactor and light source design along with UVPCO properties of the chosen catalyst to purify indoor air and enhance indoor air quality (IAQ). During the program we designed, fabricated and tested a prototype air purifier to demonstrate its feasibility and effectiveness. We also measured kinetics of VOC destruction on photocatalysts, providing deep insight into reactor design.

  12. Air-Quality Improvement Tax Incentives | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Administrator Ohio Department of Development Website http:www.ohioairquality.orgenergyairpollutioncontrol.asp State Ohio Program Type Other Incentive Summary The Ohio Air...

  13. Compressed Air System Optimization Saves Energy and Improves Production at Synthetic Textile Plant (Solutia, Inc. Plant)

    SciTech Connect (OSTI)

    2001-05-01

    BestPractices technical case study gives an overview of a compressed air system improvement in a textile plant in South Carolina.

  14. SustainX Inc Isothermal Compressed Air Energy Storage Project Description

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    SustainX Inc Isothermal Compressed Air Energy Storage Project Description SustainX is developing and demonstrating a modular, market-ready energy storage system that uses compressed air as the storage medium. SustainX uses a crankshaft-based drivetrain to convert electrical energy into potential energy stored as compressed air. SustainX's ICAES system captures the heat from compression in water and stores the captured heat until it is needed again for expansion. Storing the captured heat

  15. Opportunities for Saving Energy and Improving Air Quality in...

    Office of Scientific and Technical Information (OSTI)

    ... of heat from hot surfaces, and man-made heat (exhaust from cars, buildings, etc.). ... The contribution of man-made heat (e.g., air conditioning, cars) is very small, compared ...

  16. Opportunities for Saving Energy and Improving Air Quality in...

    Office of Scientific and Technical Information (OSTI)

    of heat from hot surfaces, and man-made heat (exhaust from cars, buildings, etc.). ... The contribution of man-made heat (e.g., air conditioning, cars) is very small, compared ...

  17. Materials that Improve the Cost‐Effectiveness of Air Barrier Systems

    Energy.gov [DOE]

    This project aims to develop and demonstrate new air sealing technologies for residential and commercial buildings that have the potential to reduce that energy loss at an installed cost that is less than current technologies.

  18. Improving Air-Conditioner and Heat Pump Modeling (Presentation)

    SciTech Connect (OSTI)

    Winkler, J.

    2012-03-01

    A new approach to modeling residential air conditioners and heat pumps allows users to model systems by specifying only the more readily-available SEER/EER/HSPF-type metrics. Manufacturer data was used to generate full sets of model inputs for over 450 heat pumps and air conditioners. A sensitivity analysis identified which inputs can be safely defaulted 'behind-the-scenes' without negatively impacting the reliability of energy simulations.

  19. Improving Air-Conditioner and Heat Pump Modeling

    SciTech Connect (OSTI)

    Winkler, Jon

    2012-03-02

    This presentation describes a new approach to modeling residential air conditioners and heat pumps, which allows users to model systems by specifying only the more readily-available SEER/EER/HSPF-type metrics. Manufacturer data was used to generate full sets of model inputs for over 450 heat pumps and air conditioners. A sensitivity analysis identified which inputs can be safely defaulted “behind-the-scenes” without negatively impacting the reliability of energy simulations.

  20. Cool Colored Roofs to Save Energy and Improve Air Quality

    SciTech Connect (OSTI)

    Akbari, Hashem; Levinson, Ronnen; Miller, William; Berdahl, Paul

    2005-08-23

    Urban areas tend to have higher air temperatures than their rural surroundings as a result of gradual surface modifications that include replacing the natural vegetation with buildings and roads. The term ''Urban Heat Island'' describes this phenomenon. The surfaces of buildings and pavements absorb solar radiation and become extremely hot, which in turn warm the surrounding air. Cities that have been ''paved over'' do not receive the benefit of the natural cooling effect of vegetation. As the air temperature rises, so does the demand for air-conditioning (a/c). This leads to higher emissions from power plants, as well as increased smog formation as a result of warmer temperatures. In the United States, we have found that this increase in air temperature is responsible for 5-10% of urban peak electric demand for a/c use, and as much as 20% of population-weighted smog concentrations in urban areas. Simple ways to cool the cities are the use of reflective surfaces (rooftops and pavements) and planting of urban vegetation. On a large scale, the evapotranspiration from vegetation and increased reflection of incoming solar radiation by reflective surfaces will cool a community a few degrees in the summer. As an example, computer simulations for Los Angeles, CA show that resurfacing about two-third of the pavements and rooftops with reflective surfaces and planting three trees per house can cool down LA by an average of 2-3K. This reduction in air temperature will reduce urban smog exposure in the LA basin by roughly the same amount as removing the basin entire onroad vehicle exhaust. Heat island mitigation is an effective air pollution control strategy, more than paying for itself in cooling energy cost savings. We estimate that the cooling energy savings in U.S. from cool surfaces and shade trees, when fully implemented, is about $5 billion per year (about $100 per air-conditioned house).

  1. Saving energy and improving IAQ through application of advanced air cleaning technologies

    SciTech Connect (OSTI)

    Fisk, W.J; Destaillats, H.; Sidheswaran, M.A.

    2011-03-01

    In the future, we may be able use air cleaning systems and reduce rates of ventilation (i.e., reduce rates of outdoor air supply) to save energy, with indoor air quality (IAQ) remaining constant or even improved. The opportunity is greatest for commercial buildings because they usually have a narrower range of indoor pollutant sources than homes. This article describes the types of air cleaning systems that will be needed in commercial buildings.

  2. Improved Modeling of Residential Air Conditioners and Heat Pumps for Energy Calculations

    SciTech Connect (OSTI)

    Cutler, D.; Winkler, J.; Kruis, N.; Christensen, C.; Brendemuehl, M.

    2013-01-01

    This report presents improved air conditioner and heat pump modeling methods in the context of whole-building simulation tools, with the goal of enabling more accurate evaluation of cost effective equipment upgrade opportunities and efficiency improvements in residential buildings.

  3. Supplemental Environmental Projects Using Renewable Energy: A New Approach to Addressing Air Quality Violation Penalties

    SciTech Connect (OSTI)

    Sinclair, K.

    2001-08-09

    Supplemental environmental projects, or SEPs, are environmentally beneficial projects that offer pollution prevention, energy efficiency, green energy, and community-based programs that may include investment in cost-effective alternative energy technologies, such as wind energy. This fact sheet explains how SEPs can help companies mitigate all or part of penalties imposed as a result of air pollution violations.

  4. Columbia River Channel Improvement Project Rock Removal Blasting: Monitoring Plan

    SciTech Connect (OSTI)

    Carlson, Thomas J.; Johnson, Gary E.

    2010-01-29

    This document provides a monitoring plan to evaluate take as outlined in the National Marine Fisheries Service 2002 Biological Opinion for underwater blasting to remove rock from the navigation channel for the Columbia River Channel Improvement Project. The plan was prepared by the Pacific Northwest National Laboratory (PNNL) for the U.S. Army Corps of Engineers (USACE), Portland District.

  5. Laboratory Evaluation of Air Flow Measurement Methods for Residential...

    Office of Scientific and Technical Information (OSTI)

    Returns Citation Details In-Document Search Title: Laboratory Evaluation of Air Flow Measurement Methods for Residential HVAC Returns This project improved the accuracy of air flow...

  6. Recommendations for improvements to program and project management

    SciTech Connect (OSTI)

    Not Available

    1994-01-01

    Oak Ridge National Laboratory (ORNL) has operated with a balanced matrix organization for over sixteen years. Much of the work at the Laboratory is accomplished with good customer satisfaction through programs, projects, and matrix management. During the past several years concerns about program and project management at ORNL have been expressed by both the Department of Energy and ORNL staff. In May 1993 the ORNL Division/Program/Office Directors Caucus chartered a ``fox team`` to identity and to recommend improvements to matrix management that would lead to resolution of these concerns. Nine experienced ORNL staff members served on this Matrix Management Upgrade Solutions Team (MMUST). The MMUST adopted a four-phase approach in which they first gathered information and then developed and proposed recommended actions. In the fourth phase the team was available to support implementation of the recommendations. They began work in June 1993, gathering and evaluating information in biweekly meetings for six months. Recommendations developed in October and November 1993 were presented to ORNL management in December. The MMUST issued three principal recommendations based on their evaluation of the information gathered. They are: Renew and enhance the ORNL management commitment to matrix management, program managers, and project managers; Implement actions to ensure career path parity between the program/project manager family of positions and the technical line manager family of positions across all directorates and divisions; and Clarify and document program/project manager roles, responsibilities, and authorities.

  7. Needs and perspectives of air quality improvement in Cracow

    SciTech Connect (OSTI)

    Wertz, J.

    1995-12-31

    In 1970s and 80s the Cracow province area belonged to the regions of highest concentration of air pollutants throughout Europe. The majority of inhabitants, terrified of continuously worsening conditions of the environment, were of the opinion that this situation was caused by the industrial plants located within the Cracow area (town and/or province) as well as by the advection of pollutants from the neighboring Katowice province - the most industrialized region of Poland. The results of two large measurement series carried out in Cracow in 1984 and 1986 were surprising for the majority of the people. It appeared that 40% of the pollution came from local coal-fired boiler houses and household coal-fired stoves. These emission sources, situated at relatively low altitude above the ground level, were called low emission sources. The quantity of such sources has been estimated. It was estimated that the number of local boiler houses was close to 1,600 while the total number of household tile stoves reached 200,000. A full inventory of these sources drawn up in 1989-90 confirmed the quantity of existing boiler houses and the verified total number of tile stoves was 130,000. In 1986, the elimination of low emission sources was admitted to be one of the strategic directions of actions in the field of air quality protection. The following two solutions to this problem were accepted for implementation: (1) boiler house elimination by means of an administrative, compulsory decision, and (2) co-financing or even complete financing from the environmental protection fund, of the capital investment related to the elimination of a boiler house or its conversion to another mode of heating (gas, fuel-oil or connection to the municipal district heating loop). These two solutions are discussed.

  8. Steam Pressure-Reducing Station Safety and Energy Efficiency Improvement Project

    SciTech Connect (OSTI)

    Lower, Mark D; Christopher, Timothy W; Oland, C Barry

    2011-06-01

    reduce its overall utility costs by decreasing the amount of fuel used to generate steam. Reduced fuel consumption also decreased air emissions. These improvements also helped lower the risk of burn injuries to workers and helped prevent shrapnel injuries resulting from missiles produced by pressurized component failures. In most cases, the economic benefit and cost effectiveness of the SPRS Safety and Energy Efficiency Improvement Project is reflected in payback periods of 1 year or less.

  9. Materials that Improve the Cost-Effectiveness of Air Barrier Systems |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy Materials that Improve the Cost-Effectiveness of Air Barrier Systems Materials that Improve the Cost-Effectiveness of Air Barrier Systems 1 of 3 3M has developed a primer-less self-adhered membrane that serves as an air, liquid water, and water vapor barrier. This technology installs in up to half the time of asphalt-based membranes, which will lead to installed costs that are similar or lower than that of asphalt-based membranes. Image: 3M 2 of 3 3M has developed a

  10. Improved Performance of an Air Cooled Condenser (ACC) Using SPX Wind Guide Technology at Coal-Based Thermoelectric Power Plants

    SciTech Connect (OSTI)

    Ken Mortensen

    2010-12-31

    This project added a new airflow enhancement technology to an existing ACC cooling process at a selected coal power plant. Airflow parameters and efficiency improvement for the main plant cooling process using the applied technology were determined and compared with the capabilities of existing systems. The project required significant planning and pre-test execution in order to reach the required Air Cooled Condenser system configuration for evaluation. A host Power Plant ACC system had to be identified, agreement finalized, and addition of the SPX ACC Wind Guide Technology completed on that site. Design of the modification, along with procurement, fabrication, instrumentation, and installation of the new airflow enhancement technology were executed. Baseline and post-modification cooling system data was collected and evaluated. The improvement of ACC thermal performance after SPX wind guide installation was clear. Testing of the improvement indicates there is a 5% improvement in heat transfer coefficient in high wind conditions and 1% improvement at low wind speed. The benefit increased with increasing wind speed. This project was completed on schedule and within budget.

  11. Improving Best Air Conditioner Efficiency by 20-30% through a High Efficiency Fan and Diffuser Stage Coupled with an Evaporative Condenser Pre-Cooler

    SciTech Connect (OSTI)

    Parker, Danny S; Sherwin, John R; Raustad, Richard

    2014-04-10

    The Florida Solar Energy Center (FSEC) conducted a research project to improve the best residential air conditioner condenser technology currently available on the market by retrofitting a commercially-available unit with both a high efficiency fan system and an evaporative pre-cooler. The objective was to integrate these two concepts to achieve an ultra-efficient residential air conditioner design. The project produced a working prototype that was 30% more efficient compared to the best currently-available technologies; the peak the energy efficiency ratio (EER) was improved by 41%. Efficiency at the Air-Conditioning and Refrigeration Institute (ARI) standard B-condition which is used to estimate seasonal energy efficiency ratio (SEER), was raised from a nominal 21 Btu/Wh to 32 Btu/Wh.

  12. Improved Modeling of Residential Air Conditioners and Heat Pumps for Energy Calculations

    SciTech Connect (OSTI)

    Cutler, D.; Winkler, J.; Kruis, N.; Christensen, C.; Brandemuehl, M.

    2013-01-01

    This report presents improved air conditioner and heat pump modeling methods in the context of whole-building simulation tools, with the goal of enabling more accurate evaluation of cost-effective equipment upgrade opportunities and efficiency improvements in residential buildings.

  13. Yakima Habitat Improvement Project Master Plan, Technical Report 2003.

    SciTech Connect (OSTI)

    Golder Associates, Inc.

    2003-04-22

    The Yakima Urban Growth Area (UGA) is a developing and growing urban area in south-central Washington. Despite increased development, the Yakima River and its tributaries within the UGA continue to support threatened populations of summer steelhead and bull trout as well as a variety of non-listed salmonid species. In order to provide for the maintenance and recovery of these species, while successfully planning for the continued growth and development within the UGA, the City of Yakima has undertaken the Yakima Habitat Improvement Project. The overall goal of the project is to maintain, preserve, and restore functioning fish and wildlife habitat within and immediately surrounding the Yakima UGA over the long term. Acquisition and protection of the fish and wildlife habitat associated with key properties in the UGA will prevent future subdivision along riparian corridors, reduce further degradation or removal of riparian habitat, and maintain or enhance the long term condition of aquatic habitat. By placing these properties in long-term protection, the threat of development from continued growth in the urban area will be removed. To most effectively implement the multi-year habitat acquisition and protection effort, the City has developed this Master Plan. The Master Plan provides the structure and guidance for future habitat acquisition and restoration activities to be performed within the Yakima Urban Area. The development of this Master Plan also supports several Reasonable and Prudent Alternatives (RPAs) of the NOAA Fisheries 2000 Biological Opinion (BiOp), as well as the Water Investment Action Agenda for the Yakima Basin, local planning efforts, and the Columbia Basin Fish and Wildlife Authority's 2000 Fish and Wildlife Program. This Master Plan also provides the framework for coordination of the Yakima Habitat Improvement Project with other fish and wildlife habitat acquisition and protection activities currently being implemented in the area. As a result of

  14. Improvement to Air2Air Technology to Reduce Fresh-Water Evaporative Cooling Loss at Coal-Based Thermoelectric Power Plants

    SciTech Connect (OSTI)

    Ken Mortensen

    2011-12-31

    This program was undertaken to enhance the manufacturability, constructability, and cost of the Air2Air{TM} Water Conservation and Plume Abatement Cooling Tower, giving a validated cost basis and capability. Air2Air{TM} water conservation technology recovers a portion of the traditional cooling tower evaporate. The Condensing Module provides an air-to-air heat exchanger above the wet fill media, extracting the heat from the hot saturated moist air leaving in the cooling tower and condensing water. The rate of evaporate water recovery is typically 10% - 25% annually, depending on the cooling tower location (climate). This program improved the efficiency and cost of the Air2Air{TM} Water Conservation Cooling Tower capability, and led to the first commercial sale of the product, as described.

  15. Recovery Act--Class 8 Truck Freight Efficiency Improvement Project

    SciTech Connect (OSTI)

    Trucks, Daimler

    2015-07-26

    Daimler Trucks North America completed a five year, $79.6M project to develop and demonstrate a concept vehicle with at least 50% freight efficiency improvement over a weighted average of several drive cycles relative to a 2009 best-in-class baseline vehicle. DTNA chose a very fuel efficient baseline vehicle, the 2009 Freightliner Cascadia with a DD15 engine, yet successfully demonstrated a 115% freight efficiency improvement. DTNA learned a great deal about the various technologies that were incorporated into Super Truck and those that, through down-selection, were discarded. Some of the technologies competed with each other for efficiency, and notably some of the technologies complemented each other. For example, we found that Super Truck’s improved aerodynamic drag resulted in improved fuel savings from eCoast, relative to a similar vehicle with worse aerodynamic drag. However, some technologies were in direct competition with each other, namely the predictive technologies which use GPS and 3D digital maps to efficiently manage the vehicles kinetic energy through controls and software, versus hybrid which is a much costlier technology that essentially targets the same inefficiency. Furthermore, the benefits of a comprehensive, integrated powertrain/vehicle approach was proven, in which vast improvements in vehicle efficiency (e.g. lower aero drag and driveline losses) enabled engine strategies such as downrating and downspeeding. The joint engine and vehicle developments proved to be a multiplier-effect which resulted in large freight efficiency improvements. Although a large number of technologies made the selection process and were used on the Super Truck demonstrator vehicle, some of the technologies proved not feasible for series production.

  16. National air toxics information clearinghouse: Ongoing research and regulatory development projects, July 1992. Final report

    SciTech Connect (OSTI)

    Not Available

    1992-07-01

    The purpose of the document is to inform State and local agencies and other Clearinghouse users of current research and regulatory development projects underway at the US EPA, the National Institute for Occupational Safety and Health, the Agency for Toxic Substances and Disease Registry, and State and local agencies, and to help them identify sources of specific air toxics information. Every effort has been made to ensure accuracy as of April 1992, the date that compilation of information was completed. However, further changes in agency priorities and funding levels may change the scope and estimated project completion dates.

  17. Cotton gin trash incinerator-air heat project. Consultant report (final)

    SciTech Connect (OSTI)

    Not Available

    1980-05-01

    The California Energy Commission has funded the final phase of a four year project resulting in development of a successful system for burning cotton gin trash as a fuel providing the heat for ginning. The incinerator - air heater system installed in Corcoran, California operates continuously throughout the ginning season. Trash feeding and burning rate is automatically controlled from the combustion temperature, hot air temperature is controlled by the drying needs, and ashes are automatically removed from the system and pneumatically conveyed to the disposal site. The system complies with state and county air pollution codes by means of baghouse collectors. Savings in fossil fuel and trash disposal costs have demonstrated the equipment system is feasible for a four year payback at large, well utilized gins.

  18. Coal air turbine ``CAT`` program, invention 604. Fifth quarter project report, October--December 1995

    SciTech Connect (OSTI)

    Foster-Pegg, R.W.

    1995-12-31

    The primary objective of this ``CAT`` (Coal Air Turbine) project is to complete a conceptual design of this unique new combination of existing technology with cost estimates to show that the CAT system offers the economic incentive with low technical risk for a plant to be built which will demonstrate its viability. The technologies involved in the components of a CAT plant are proven, and the integration of the components into a complete plant is the only new developmental activity involved. Industry and the Federal General Services Administration (GSA), require the demonstration of a commercial plant before the viability of a new concept is accepted. To satisfy this requirement the construction of a plant of commercially viable size in excess of 15 MW if cogeneration and above 30 MW if all power, is proposed. This plant will produce economical power and heat for the owner. The plant will operate for a full commercial life and continue as an operating demonstration of the viability of the technology, gathering long term life and maintenance data, all adding to the credibility of the concept. The major components of CAT plants are an air turbine, a heater of compressed air, a coal combustion system, means to recover waste heat and a steam turbine when appropriate. The plant burns raw coal in a fluid bed at atmospheric pressure. The air turbine operates on clean compressed air heated inside tubes immersed in the fluid bed. Progress during the fifth quarter is described.

  19. Nellis Air Force Base solar array provides model for renewable projects

    Energy.gov [DOE]

    A public-private partnership has helped one Air Force base reduce its energy costs and convert to 25 percent renewable energy. Nellis Air Force Base, just north of Las Vegas, took a big step in 2007 when it installed a 14.2-megawatt, 70,000-panel photovoltaic solar array that reduced carbon dioxide emissions by 24,000 tons a year. Built partly on a landfill, the field of solar panels takes advantage of two resources plentiful in Nevada: sunshine and empty land. At its unveiling in December of 2007, the Nellis array was the largest solar panel installation in North America. The project was originally expected to produce about 30,000 megawatt-hours of electricity per year, but Steven Dumont, Air Combat Command Energy Manager, says it’s actually producing closer to 32,000 megawatt-hours, which is about 8 percent above expectations. Despite this success, Dumont said he nearly didn’t pursue the project.

  20. American Recovery and Reinvestment Act (ARRA) Federal Energy Management Program Technical Assistance Project 224 Altus Air Force Base Solar Technologies

    SciTech Connect (OSTI)

    Russo, Bryan J.

    2010-09-30

    The principal goal of this project was to evaluate altus Air Force Base for building integrated silicon or thin film module photovoltaic opportunities. This report documents PNNL's efforts and documents study conclusions.

  1. Annual Progress Report Fish Research Project Oregon : Project title, Evaluation of Habitat Improvements -- John Day River.

    SciTech Connect (OSTI)

    Olsen, Erik A.

    1984-01-01

    This report summarizes data collected in 1983 to evaluate habitat improvements in Deer, Camp, and Clear creeks, tributaries of the John Day River. The studies are designed to evaluate changes in abundance of spring chinook and summer steelhead due to habitat improvement projects and to contrast fishery benefits with costs of construction and maintenance of each project. Structure types being evaluated are: (1) log weirs, rock weirs, log deflectors, and in stream boulders in Deer Creek; (2) log weirs in Camp Creek; and (3) log weir-boulder combinations and introduced spawning gravel in Clear Creek. Abundance of juvenile steelhead ranged from 16% to 119% higher in the improved (treatment) area than in the unimproved (control) area of Deer Creek. However, abundance of steelhead in Camp Creek was not significantly different between treatment and control areas. Chinook and steelhead abundance in Clear Creek was 50% and 25% lower, respectively in 1983, than the mean abundance estimated in three previous years. The age structure of steelhead was similar between treatment and control areas in Deer and Clear creeks. The treatment area in Camp Creek, however, had a higher percentage of age 2 and older steelhead than the control. Steelhead redd counts in Camp Creek were 36% lower in 1983 than the previous five year average. Steelhead redd counts in Deer Creek were not made in 1983 because of high streamflows. Chinook redds counted in Clear Creek were 64% lower than the five year average. Surface area, volume, cover, and spawning gravel were the same or higher than the corresponding control in each stream except in Deer Creek where there was less available cover and spawning gravel in sections with rock weirs and in those with log deflectors, respectively. Pool:riffle ratios ranged from 57:43 in sections in upper Clear Creek with log weirs to 9:91 in sections in Deer Creek with rock weirs. Smolt production following habitat improvements is estimated for each stream

  2. The Wind Forecast Improvement Project (WFIP): A Public/Private Partnership

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations | Department of Energy The Wind Forecast Improvement Project (WFIP): A Public/Private Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations The Wind Forecast Improvement Project (WFIP): A Public/Private Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations The Wind Forecast Improvement

  3. J.R. Simplot: Burner Upgrade Project Improves Performance and...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    ... air results in lost heat-indicating lower boiler fuel-to-steam efficiency. Natural- gas-fired boilers that operate ... 50% and to take the plant's fve condensate pumps off-line. ...

  4. Project Profile: Solar Power Tower Improvements with the Potential...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Publications, Patents, and Awards At this time, this project does not have published articles, patents, or awards. Learn about other DOE competitive awards for concentrating solar ...

  5. FY 2014 Projects for Improving the Design, Construction, and...

    Energy Savers

    Institute (Des Plaines, Ill.) - Simultaneous Waste Heat and Water Recovery from Power Plant Flue Gases for Advanced Energy Systems. The project team will further develop an...

  6. Commercialization of air conditioning heat pump/water heater. Final technical report, Volume 1: Transmittal documents; Executive summary; Project summary

    SciTech Connect (OSTI)

    1996-01-30

    This is the final technical report on a commercialization project for an air conditioning heat pump water heater. The objective of the project was to produce a saleable system which would be economically competitive with natural gas and cost effective with regard to initial cost versus annual operating costs. The development and commercialization of the system is described.

  7. Department of Energy Announces 10 New Projects to Improve Connected and

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Automated Vehicle Efficiency | Department of Energy Department of Energy Announces 10 New Projects to Improve Connected and Automated Vehicle Efficiency Department of Energy Announces 10 New Projects to Improve Connected and Automated Vehicle Efficiency November 2, 2016 - 10:51am Addthis News Media Contact 202-586-4940 DOENews@hq.doe.gov Department of Energy Announces 10 New Projects to Improve Connected and Automated Vehicle Efficiency ARPA-E Awards $32 Million to Use Connected Technologies

  8. Draft Air Pathway Report: Phase 1 of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Not Available

    1990-07-20

    This report summarizes the air pathway portion of the first phase of the Hanford Environmental Dose Reconstruction (HEDR) Project, conducted by Battelle staff at the Pacific Northwest Laboratory under the direction of an independent Technical Steering Panel. The HEDR Project is estimating historical radiation doses that could have been received by populations near the Department of Energy's Hanford Site, in southeastern Washington State. Phase 1 of the air-pathway dose reconstruction sought to determine whether dose estimates could be calculated for populations in the 10 counties nearest the Hanford Site from atmospheric releases of iodine-131 from the site from 1944--1947. Phase 1 demonstrated the following: HEDR-calculated source-term estimates of iodine-131 releases to the atmosphere were within 20% of previously published estimates; calculated vegetation concentrations of iodine-131 agree well with previously published measurements; the highest of the Phase 1 preliminary dose estimates to the thyroid are consistent with independent, previously published estimates of doses to maximally exposed individuals; and relatively crude, previously published measurements of thyroid burdens for Hanford workers are in the range of average burdens that the HEDR model estimated for similar reference individuals'' for the period 1944--1947. 4 refs., 10 figs., 9 tabs.

  9. Salt Repository Project site study plan for meteorology/air quality: Revision 1

    SciTech Connect (OSTI)

    Not Available

    1987-12-01

    The Site Study Plan for Meteorology/Air Quality describes a field program consisting of continuous measurements of wind speed and direction, temperature, humidity, dew point, and pressure neede for later modeling and dose calculations. These measurements will include upper level winds, vertical temperature structure, and vertical wind speed. All measurements will be made at a site located within the 9-m/sup 2/ site area but remote from the ESF. The SSP describes the need for each study; its design and design rationale; analysis, management, and use of data; schedule of field activities, organization of field personnel and sample management and quality assurance requirements. These studies will provide data needed to satisfy requirements contained in, or derived from, the Salt Repository Project Requirements Document. Although titled Meteorology/Air Quality, this SSP addresses only meteorology, as there are no air quality data needs in the SCP. A correction to the title will be made in a later revision. 27 refs., 6 figs., 3 tabs.

  10. EM Focuses on Contract, Project Management Improvements in Three-Day Workshop

    Energy.gov [DOE]

    ORLANDO, Fla. – EM held a three-day workshop in Orlando this month focusing on strategies to improve contract and project management across the EM complex.

  11. Motor Assembly Plant Saves $85,000 with Compressed Air System Improvements (Bodine Electric's Chicago Facility)

    SciTech Connect (OSTI)

    2001-06-01

    This case study is one in a series on industrial firms who are implementing energy efficient technologies and system improvements into their manufacturing processes. This case study documents the activities, savings, and lessons learned on the Bodine Electric motor assembly plant project.

  12. Compressed Air System Modifications Improve Efficiency at a Plastics Blow Molding Plant (Southeastern Container Plant)

    SciTech Connect (OSTI)

    None

    2001-06-01

    This case study is one in a series on industrial firms who are implementing energy efficient technologies and system improvements into their manufacturing processes. This case study documents the activities, savings, and lessons learned on the plastics blow molding plant project.

  13. The Yucca Mountain Project prototype air-coring test, U12g tunnel, Nevada test site

    SciTech Connect (OSTI)

    Ray, J.M.; Newsom, J.C.

    1994-12-01

    The Prototype Air-Coring Test was conducted at the Nevada Test Site (NTS) G-Tunnel facility to evaluate standard coring techniques, modified slightly for air circulation, for use in testing at a prospective nuclear waste repository at Yucca Mountain, Nevada. Air-coring technology allows sampling of subsurface lithology with minimal perturbation to ambient characteristic such as that required for exploratory holes near aquifers, environmental applications, and site characterization work. Two horizontal holes were cored, one 50 ft long and the other 150 ft long, in densely welded fractured tuff to simulate the difficult drilling conditions anticipated at Yucca Mountain. Drilling data from seven holes on three other prototype tests in nonwelded tuff were also collected for comparison. The test was used to establish preliminary standards of performance for drilling and dust collection equipment and to assess procedural efficiencies. The Longyear-38 drill achieved 97% recovery for HQ-size core (-2.5 in.), and the Atlas Copco dust collector (DCT-90) captured 1500 lb of fugitive dust in a mine environment with only minor modifications. Average hole production rates were 6-8 ft per 6-h shift in welded tuff and almost 20 ft per shift on deeper holes in nonwelded tuff. Lexan liners were successfully used to encapsulate core samples during the coring process and protect core properties effectively. The Prototype Air-Coring Test demonstrated that horizontal air coring in fractured welded tuff (to at least 150 ft) can be safely accomplished by proper selection, integration, and minor modification of standard drilling equipment, using appropriate procedures and engineering controls. The test also indicated that rig logistics, equipment, and methods need improvement before attempting a large-scale dry drilling program at Yucca Mountain.

  14. Security Improvements Project Completed Ahead of Schedule, $20...

    National Nuclear Security Administration (NNSA)

    2010 (1) July 2010 (1) June 2010 (5) April 2010 (2) January 2010 (1) December 2009 (1) 1 of 3 Related Topics apm project management llnl defense nuclear security Y-12 npo...

  15. SHINES SunShot Project to Improve Energy Storage

    ScienceCinema (OSTI)

    Sekaric, Lidija

    2016-07-12

    Our SunShot Initiative’s new solar storage projects will supply solar energy at any time of day while helping to modernize the electrical grid.

  16. BETO Project Improves Production of Renewable Chemical from Cellulosic Feedstocks

    Energy.gov [DOE]

    Renewable chemical company Genomatica made significant progress toward increasing the range of feedstocks that can be used to commercially produce high-quality bio-based chemicals, in a project...

  17. Improving Energy Efficiency of Compressed Air System Based onSystem Audit

    SciTech Connect (OSTI)

    Shanghai, Hongbo Qin; McKane, Aimee

    2007-06-01

    Industrial electric motor systems consume more than 600billion kWh annually, accounting for more than 50 percent of China selectricity use. The International Energy Agency estimates thatoptimizing motor systems results in an improvement of 20-25 percent,which is well-supported by experience in both the U.S. and China.Compressed air systems in China use 9.4 percent of all electricity.Compressed air use in China is growing rapidly, as new industrial plantsare built and the production processes of existing plants expand andchange. Most of these systems, whether existing or new, are not optimizedfor energy efficiency. This paper will present a practitioner'sperspective on theemergence of compressed air auditing services inChina, specifically as it pertains to Shanghai and surrounding areas.Both the methodology used and the market development of these compressedair system services will be addressed. Finally, the potential for energysaving opportunities will be described based on highlights from over 50compressed air system energy audits completed by Shanghai EnergyConservation Service Center, both during the United Nations IndustrialDevelopment Organization (UNIDO) China Motor System Energy ConservationProgram, and after this training program was completed.

  18. Investigation of Techniques to Improve Continuous Air Monitors Under Conditions of High Dust Loading in Environmental Settings

    SciTech Connect (OSTI)

    Suilou Huang; Stephen D. Schery; John C. Rodgers

    2002-07-23

    A number of DOE facilities, such as the Los Alamos National Laboratory (LANL) and the Waste Isolation Pilot Plant (WIPP), use alpha-particle environmental continuous air monitors (ECAMs) to monitor air for unwanted releases of radioactive aerosols containing such materials as plutonium and uranium. High sensitivity, ease of operation, and lack of false alarms are all important for ECAMs. The object of the project was to conduct investigations to improve operation of ECAMs, particularly under conditions where a lot of nonradioactive dust may be deposited on the filters (conditions of high dust loading). The presence of such dust may increase the frequency with which filters must be changed and can lead to an increased incidence of false alarms due to deteriorated energy resolution and response specificity to the radionuclides of interest. A major finding of the investigation, not previously documented, was that under many conditions thick layers of underlying nonradioactive dust do not decrease energy resolution and specificity for target radionuclides if the radioactive aerosol arrives as a sudden thin burst deposit, as commonly occurs in the early-warning alarm mode. As a result, operators of ECAMs may not need to change filters as often as previously thought and have data upon which to base more reliable operating procedures.

  19. Recovery Act: Hydroelectric Facility Improvement Project - Replacement of Current Mechanical Seal System with Rope Packing System

    SciTech Connect (OSTI)

    Stephens, Jessica D.

    2013-05-29

    On January 27, 2010 the City of North Little Rock, Arkansas received notification of the awarding of a Department of Energy (DOE) grant totaling $450,000 in funding from the American Recovery and Reinvestment Act (ARRA) under the Project Title: Recovery Act: Hydroelectric Facility Improvement Project – Automated Intake Clearing Equipment and Materials Management. The purpose of the grant was for improvements to be made at the City’s hydroelectric generating facility located on the Arkansas River. Improvements were to be made through the installation of an intake maintenance device (IMD) and the purchase of a large capacity wood grinder. The wood grinder was purchased in order to receive the tree limbs, tree trunks, and other organic debris that collects at the intake of the plant during high flow. The wood grinder eliminates the periodic burning of the waste material that is cleared from the intake and reduces any additional air pollution to the area. The resulting organic mulch has been made available to the public at no charge. Design discussion and planning began immediately and the wood grinder was purchased in July of 2010 and immediately put to work mulching debris that was gathered regularly from the intake of the facility. The mulch is currently available to the public for free. A large majority of the design process was spent in discussion with the Corps of Engineers to obtain approval for drawings, documents, and permits that were required in order to make changes to the structure of the powerhouse. In April of 2011, the City’s Project Engineer, who had overseen the application, resigned and left the City’s employ. A new Systems Mechanical Engineer was hired and tasked with overseeing the project. The transfer of responsibility led to a re-examination of the original assumptions and research upon which the grant proposal was based. At that point, the project went under review and a trip was booked for July 2011 to visit facilities that currently

  20. The Environmental Management Project Manager`s Handbook for improved project definition

    SciTech Connect (OSTI)

    1995-02-01

    The United States Department of Energy (DOE) is committed to providing high quality products that satisfy customer needs and are the associated with this goal, DOE personnel must possess the knowledge, skills, and abilities to ensure successful job performance. In addition, there must be recognition that the greatest obstacle to proper project performance is inadequate project definition. Without strong project definition, DOE environmental management efforts are vulnerable to fragmented solutions, duplication of effort, and wastes resources. The primary means of ensuring environmental management projects meet cost and schedule milestones is through a structured and graded approach to project definition, which is the focus of this handbook.

  1. NAPA Collaboration Project: Worker Dialogue to Improve Worker...

    Energy Savers

    will host A Worker Dialogue: Improving Health, Safety and Security at DOE. This web-based "conversation" will engage the DOE workforce in an open, online dialogue to ...

  2. EERE Success Story-BETO Project Improves Production of Renewable Chemical

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    from Cellulosic Feedstocks | Department of Energy BETO Project Improves Production of Renewable Chemical from Cellulosic Feedstocks EERE Success Story-BETO Project Improves Production of Renewable Chemical from Cellulosic Feedstocks October 20, 2015 - 11:18am Addthis Renewable chemical company Genomatica made significant progress toward increasing the range of feedstocks that can be used to commercially produce high-quality bio-based chemicals, in a project funded by the Energy Department's

  3. Hopper:Improving I/O performance to GSCRATCH and PROJECT

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    GSCRATCH/PROJECT Performance Tuning on Hopper Hopper:Improving I/O performance to GSCRATCH and PROJECT What are GSCRATCH/PROJECT? GSCRATCH and PROJECT are two file systems at NERSC that one can access on most computational systems. They are both based on the IBM GPFS file system and have multiple racks of dedicated servers and disk arrays. How are GSCRATCH/PROJECT connected to Hopper? As shown in the figure below, GSCRATCH and PROJECT are each connected to several Private NSD Servers (PNSD; for

  4. Air pathway report: Phase I of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Not Available

    1991-07-01

    Phase 1 of the air-pathway portion of the Hanford Environmental Dose Reconstruction (HEDR) Project sought to determine whether dose estimates could be calculated for populations in the 10 counties nearest the Hanford Site from atmospheric releases of iodine-131 from the site from 1944--1947. Phase 1 demonstrated the following: HEDR-calculated source-term estimates of iodine-131 releases to the atmosphere were within 20% of previously published estimates; calculated vegetation concentrations of iodine-131 agree well with previously published measurements; the highest of the Phase 1 preliminary dose estimates to the thyroid are consistent with independent, previously published estimates of doses to maximally exposed individuals; and, relatively crude, previously published measurements of thyroid burdens for Hanford workers are in the range of average burdens that the HEDR model estimated for similar reference individuals'' for the period 1944--1947. Preliminary median dose estimates summed over the year 1945--1947 for the primary pathway, air-pasture-cow-milk-thyroid, ranged from low median values of 0.006 rad for upwind adults who obtained milk from backyard cows not on pasture to high median values of 68.0 rad for downwind infants who drank milk from pasture-fed cows. Extremes of the estimated range are a low of essentially zero to upwind adults and a high of almost 3000 rem to downwind infants. 37 refs., 37 figs., 2 tabs.

  5. Technology Solutions Case Study: Sealed Air-Return Plenum Retrofit

    SciTech Connect (OSTI)

    none,

    2012-08-01

    In this project, Pacific Northwest National Laboratory researchers greatly improved indoor air quality and HVAC performance by replacing an old, leaky air handler with a new air handler with an air-sealed return plenum with filter; they also sealed the ducts, and added a fresh air intake.

  6. Improving Energy Efficiency in Pharmaceutical ManufacturingOperations -- Part I: Motors, Drives and Compressed Air Systems

    SciTech Connect (OSTI)

    Galitsky, Christina; Chang, Sheng-chien; Worrell, Ernst; Masanet,Eric

    2006-04-01

    In Part I of this two-part series, we focus on efficient use of motors, drives and pumps, both for process equipment and compressed air systems. Pharmaceutical manufacturing plants in the U.S. spend nearly $1 billion each year for the fuel and electricity they need to keep their facilities running (Figure 1, below). That total that can increase dramatically when fuel supplies tighten and oil prices rise, as they did last year. Improving energy efficiency should be a strategic goal for any plant manager or manufacturing professional working in the drug industry today. Not only can energy efficiency reduce overall manufacturing costs, it usually reduces environmental emissions, establishing a strong foundation for a corporate greenhouse-gas-management program. For most pharmaceutical manufacturing plants, Heating, Ventilation and Air Conditioning (HVAC) is typically the largest consumer of energy, as shown in Table 1 below. This two-part series will examine energy use within pharmaceutical facilities, summarize best practices and examine potential savings and return on investment. In this first article, we will focus on efficient use of motors, drives and pumps, both for process equipment and compressed air systems. Part 2, to be published in May, will focus on overall HVAC systems, building management and boilers.

  7. Battery Manufacturing Processes Improved by Johnson Controls Project

    Energy.gov [DOE]

    Improving battery manufacturing processes can help make plug-in electric vehicles more affordable and convenient. This will help meet the governments EV Everywhere goal of producing by 2022 plug...

  8. EA-1075: Proposed Casey's Pond Improvement Project, Batavia, Illinois

    Energy.gov [DOE]

    This EA evaluates the environmental impacts of a proposed system upgrade to meet improved operational criteria on the current Industrial Cooling Water distribution system used in the fixed target...

  9. NREL Announces Two New Competitiveness Improvement Project Awards...

    Office of Environmental Management (EM)

    The CIP aims to help U.S. manufacturers of small and mid-sized wind turbines with rotor swept areas up to 1,000 square meters improve their turbine design and manufacturing ...

  10. Chicago Clean Air, Clean Water Project: Environmental Monitoring for a Healthy, Sustainable Urban Future

    SciTech Connect (OSTI)

    none, none; Tuchman, Nancy

    2015-11-11

    The U.S. Department of Energy awarded Loyola University Chicago and the Institute of Environmental Sustainability (IES) $486,000.00 for the proposal entitled “Chicago clean air, clean water project: Environmental monitoring for a healthy, sustainable urban future.” The project supported the purchase of analytical instruments for the development of an environmental analytical laboratory. The analytical laboratory is designed to support the testing of field water and soil samples for nutrients, industrial pollutants, heavy metals, and agricultural toxins, with special emphasis on testing Chicago regional soils and water affected by coal-based industry. Since the award was made in 2010, the IES has been launched (fall 2013), and the IES acquired a new state-of-the-art research and education facility on Loyola University Chicago’s Lakeshore campus. Two labs were included in the research and education facility. The second floor lab is the Ecology Laboratory where lab experiments and analyses are conducted on soil, plant, and water samples. The third floor lab is the Environmental Toxicology Lab where lab experiments on environmental toxins are conducted, as well as analytical tests conducted on water, soil, and plants. On the south end of the Environmental Toxicology Lab is the analytical instrumentation collection purchased from the present DOE grant, which is overseen by a full time Analytical Chemist (hired January 2016), who maintains the instruments, conducts analyses on samples, and helps to train faculty and undergraduate and graduate student researchers.

  11. Ford Van Dyke: Compressed Air Management Program Leads to Improvements that Reduce Energy Consumption at an Automotive Transmission Plant

    SciTech Connect (OSTI)

    2010-06-25

    Staff at the Ford Van Dyke Transmission Plant in Sterling Heights, Michigan, have increased the efficiency of the plant’s compressed air system to enhance its performance while saving energy and improving production.

  12. J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    at a Large Food Processing Plant | Department of Energy J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy at a Large Food Processing Plant J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy at a Large Food Processing Plant This case study describes how the J.R. Simplot Company saved energy and money by increasing the efficiency of the steam system in its potato processing plant in Caldwell, Idaho. J.R. Simplot: Burner Upgrade Project Improves

  13. SHINES SunShot Project to Improve Energy Storage | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    SHINES SunShot Project to Improve Energy Storage SHINES SunShot Project to Improve Energy Storage Addthis Description Below is the text version for the SHINES SunShot Project to Improve Energy Storage video. Text appears on the screen: The SunShot Initiative just launched the Sustainable and Holistic Integration of Energy Storage and Solar PV Program. We call it... SHINES. The video cuts to a shot of Lidijia Sekaric, SunShot Acting Director. SHINES is the first program in our renewable portfolio

  14. Project B: Improved Liquid Steel Feed For Slab Casters

    SciTech Connect (OSTI)

    Brent S. Isaacson; Mike Slepian; Thomas Richter

    1998-10-01

    This report describes the completion of the development of an electromagnetic valve to control liquid steel flow for improved liquid steel feeding for slab casters. Achievements result from a joint research effort between Westinghouse Science and Technology Center, North American Refractories and U.S. Steel. This effort is part of the American Iron and Steel Institute's (AISI) Advanced Process Control Program, a collaboration between the U.S. Department of Energy (DOE) and fifteen North American steel makers.

  15. Westinghouse TRU Solutions LLC Earns Corporate Award For Air...

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Awards Program recognizes extraordinary projects, teams and individuals. Washington Group International is the parent company of WTS. The Air Monitoring Improvement Team from WTS...

  16. DOE RFP Seeks Projects for Improving Environmental Performance of Unconventional Natural Gas Technologies

    Energy.gov [DOE]

    Research projects to study ways for improving the environmental performance of unconventional gas development are being sought by the National Energy Technology Laboratory, a facility of the U.S. Department of Energy’s Office of Fossil Energy.

  17. FY 2014 Projects for Improving the Design, Construction, and Operation of Fossil Energy Systems

    Office of Energy Efficiency and Renewable Energy (EERE)

    In FY 2014, the U.S. Department of Energy selected 38 new projects from across the nation under the Crosscutting Research Program that target innovative concepts and technologies to improve...

  18. Energy Department Awards $8.4 Million for Projects to Improve Engine and

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Powertrain Efficiency | Department of Energy 8.4 Million for Projects to Improve Engine and Powertrain Efficiency Energy Department Awards $8.4 Million for Projects to Improve Engine and Powertrain Efficiency September 27, 2011 - 3:12pm Addthis WASHINGTON, D.C. - Secretary Chu today announced $8.4 million over three to four years for suppliers and vehicle manufacturers to develop and demonstrate technologies that increase the efficiency of engines and powertrain systems for future highway

  19. New Project To Improve Characterization of U.S. Gas Hydrate Resources |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy Project To Improve Characterization of U.S. Gas Hydrate Resources New Project To Improve Characterization of U.S. Gas Hydrate Resources October 22, 2014 - 10:02am Addthis WASHINGTON, D.C. -The U.S. Department of Energy (DOE) today announced the selection of a multi-year, field-based research project designed to gain further insight into the nature, formation, occurrence and physical properties of methane hydrate-bearing sediments for the purpose of methane hydrate

  20. Projections of air toxic emissions from coal-fired utility combustion: Input for hazardous air pollutant regulators

    SciTech Connect (OSTI)

    Szpunar, C.B.

    1993-08-01

    The US Environmental Protection Agency (EPA) is required by the 1990 CAAA to promulgate rules for all ``major`` sources of any of these HAPs. According to the HAPs section of the new Title III, any stationary source emitting 10 tons per year (TPY) of one HAP or 25 TPY of a combination of HAPs will be considered and designated a major source. In contrast to the original National Emission Standards for Hazardous Air Pollutants (NESHAP), which were designed to protect public health to ``an ample margin of safety,`` the new Title III, in its first phase, will regulate by industrial category those sources emitting HAPs in excess of the 10/25-TPY threshold levels, regardless of health risks. The trace elements normally associated with coal mineral matter and the various compounds formed during coal combustion have the potential to produce hazardous air toxic emissions from coal-fired electric utilities. Under Title III, the EPA is required to perform certain studies, prior to any regulation of electric utilities; these studies are currently underway. Also, the US Department of Energy (DOE) maintains a vested interest in addressing those energy policy questions affecting electric utility generation, coal mining, and steel producing critical to this country`s economic well-being, where balancing the costs to the producers and users of energy with the benefits of environmental protection to the workers and the general populace remains of significant concern.

  1. Compressed Air System Optimization Saves Energy and Improves Production at a Textile Manufacturing Mill (Peerless Division, Thomastown Mills, Inc.)

    SciTech Connect (OSTI)

    2001-06-01

    This case study is one in a series on industrial firms who are implementing energy efficient technologies and system improvements into their manufacturing processes. This case study documents the activities, savings, and lessons learned on the textile manufacturing mill project.

  2. Improving computer simulations of heat transfer for projecting fenestration products: Using radiation view-factor models

    SciTech Connect (OSTI)

    Griffith, B.; Tuerler, D.; Arasteh, D.K.; Curcija, D.

    1998-10-01

    The window well formed by the concave surface on the warm side of skylights and garden windows can cause surface heat-flow rates to be different for these projecting types of fenestration products than for normal planar windows. Current methods of simulating fenestration thermal conductance (U-factor) use constant boundary condition values for overall surface heat transfer. Simulations that account for local variations in surface heat transfer rates (radiation and convection) may be more accurate for rating and labeling window products whose surfaces project outside a building envelope. This paper, which presents simulation and experimental results for one projecting geometry, is the first step in documenting the importance of these local effects. A generic specimen, called the foam garden window, was used in simulations and experiments to investigate heat transfer of projecting surfaces. Experiments focused on a vertical cross section (measurement plane) located at the middle of the window well on the warm side of the specimen. The specimen was placed between laboratory thermal chambers that were operated at American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) winter heating design conditions. Infrared thermography was used to map surface temperatures. Air temperature and velocity were mapped throughout the measurement plane using a mechanical traversing system. Finite-element computer simulations that directly modeled element-to-element radiation were better able to match experimental data than simulations that used fixed coefficients for total surface heat transfer. Air conditions observed in the window well suggest that localized convective effects were the reason for the difference between actual and modeled surface temperatures. U-value simulation results were 5% to 10% lower when radiation was modeled directly.

  3. Light oil yield improvement project at Granite City Division Coke/By-Product Plant

    SciTech Connect (OSTI)

    Holloran, R.A.

    1995-12-01

    Light oil removal from coke oven gas is a process that has long been proven and utilized throughout many North American Coke/By-Products Plants. The procedures, processes, and equipment requirements to maximize light oil recovery at the Granite City By-Products Plant will be discussed. The Light Oil Yield Improvement Project initially began in July, 1993 and was well into the final phase by February, 1994. Problem solving techniques, along with utilizing proven theoretical recovery standards were applied in this project. Process equipment improvements and implementation of Operator/Maintenance Standard Practices resulted in an average yield increase of 0.4 Gals./NTDC by the end of 1993.

  4. Investigation of techniques to improve continuous air monitors under conditions of high dust loading in environmental setting

    SciTech Connect (OSTI)

    Huang, Suilou; Schery, Stephen D.; Rodgers, John

    2000-06-01

    Improvement in understanding the deposition of ambient dust particles on environmental continuous air monitor (ECAM) filters, reduction of the alpha-particle interference of radon progeny and other radioactive aerosols in different particle size ranges on filters, and development of ECAMs with increased sensitivity under dusty outdoor conditions.

  5. Compressed Air System Optimization Saves Energy and Improves Production at a Synthetic Textile Plant: Office of Industrial Technologies (OIT) BestPractices Technical Case Study

    SciTech Connect (OSTI)

    Wogsland, J.

    2001-05-17

    BestPractices technical case study gives an overview of a compressed air system improvement in a textile plant in South Carolina.

  6. Final Report on the Clean Energy/Air Quality Integration Initiative Pilot Project of the U.S. Department of Energy's Mid-Atlantic Regional Office

    SciTech Connect (OSTI)

    Jacobson, D.; O'Connor, P.; High, C.; Brown, J.

    2006-08-01

    The MARO pilot project represents the first effort in the country to seek to obtain credit under a Clean Air Act (CAA) State Implementation Plan (SIP) for nitrogen oxide (NOx) emission reductions.

  7. Report: Removal of EM Projects from the GAO High Risk List: Strategies for Improving the Effectiveness of Project and Contract Management in the Office of Environmental Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    U.S. Department of Energy REPORT TO THE ENVIRONMENTAL MANAGEMENT ADVISORY BOARD Removal of EM Projects from the GAO High Risk List: Strategies for Improving the Effectiveness of Project and Contract Management in the Office of Environmental Management Submitted by the EMAB Acquisition and Project Management Subcommittee December 5, 2011 Introduction: This report provides a comprehensive summary of the work performed by the Acquisition and Project Management Subcommittee (APMS) of the

  8. Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project, Annual Report 2002-2003.

    SciTech Connect (OSTI)

    Sears, Sheryl

    2004-01-01

    The construction of Chief Joseph and Grand Coulee Dams completely and irrevocably blocked anadromous fish migrations to the Upper Columbia River. Historically this area hosted vast numbers of salmon returning to their natal waters to reproduce and die. For the native peoples of the region, salmon and steelhead were a principle food source, providing physical nourishment and spiritual sustenance, and contributing to the religious practices and the cultural basis of tribal communities. The decaying remains of spawned-out salmon carcasses contributed untold amounts of nutrients into the aquatic, aerial, and terrestrial ecosystems of tributary habitats in the upper basin. Near the present site of Kettle Falls, Washington, the second largest Indian fishery in the state existed for thousands of years. Returning salmon were caught in nets and baskets or speared on their migration to the headwater of the Columbia River in British Columbia. Catch estimates at Kettle Falls range from 600,000 in 1940 to two (2) million around the turn of the century (UCUT, Report No.2). The loss of anadromous fish limited the opportunities for fisheries management and enhancement exclusively to those actions addressed to resident fish. The Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project is a mitigation project intended to enhance resident fish populations and to partially mitigate for anadromous fish losses caused by hydropower system impacts. This substitution of resident fish for anadromous fish losses is considered in-place and out-of-kind mitigation. Upstream migration and passage barriers limit the amount of spawning and rearing habitat that might otherwise be utilized by rainbow trout. The results of even limited stream surveys and habitat inventories indicated that a potential for increased natural production exists. However, the lack of any comprehensive enhancement measures prompted the Upper Columbia United Tribes Fisheries Center (UCUT), Colville Confederated

  9. Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project, Annual Report 2001-2002.

    SciTech Connect (OSTI)

    Sears, Sheryl

    2003-01-01

    The construction of Chief Joseph and Grand Coulee Dams completely and irrevocably blocked anadromous fish migrations to the Upper Columbia River. Historically this area hosted vast numbers of salmon returning to their natal waters to reproduce and die. For the native peoples of the region, salmon and steelhead were a principle food source, providing physical nourishment and spiritual sustenance, and contributing to the religious practices and the cultural basis of tribal communities. The decaying remains of spawned-out salmon carcasses contributed untold amounts of nutrients into the aquatic, aerial, and terrestrial ecosystems of tributary habitats in the upper basin. Near the present site of Kettle Falls, Washington, the second largest Indian fishery in the state existed for thousands of years. Returning salmon were caught in nets and baskets or speared on their migration to the headwater of the Columbia River in British Columbia. Catch estimates at Kettle Falls range from 600,000 in 1940 to two (2) million around the turn of the century (UCUT, Report No.2). The loss of anadromous fish limited the opportunities for fisheries management and enhancement exclusively to those actions addressed to resident fish. The Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project is a mitigation project intended to enhance resident fish populations and to partially mitigate for anadromous fish losses caused by hydropower system impacts. This substitution of resident fish for anadromous fish losses is considered in-place and out-of-kind mitigation. Upstream migration and passage barriers limit the amount of spawning and rearing habitat that might otherwise be utilized by rainbow trout. The results of even limited stream surveys and habitat inventories indicated that a potential for increased natural production exists. However, the lack of any comprehensive enhancement measures prompted the Upper Columbia United Tribes Fisheries Center (UCUT), Colville Confederated

  10. Improved particle impactor assembly for size selective high volume air sampler

    DOE Patents [OSTI]

    Langer, G.

    1987-03-23

    Air containing entrained particulate matter is directed through a plurality of parallel, narrow, vertically oriented apertures of an inlet element toward an adjacently located, relatively large, dust impaction surface preferably covered with an adhesive material. The air flow turns over the impaction surface, leaving behind, the relatively larger particles and passes through two elongate apertures defining the outer bounds of the impaction collection surface to pass through divergent passages which slow down and distribute the air flow, with entrained smaller particles, over a fine filter element that separates the fine particles from the air. By appropriate selection of dimensions and the number of inlet apertures air flow through the inlet element is provided a nonuniform velocity distribution with the lower velocities being obtained near the center of the inlet apertures, to separate out particles larger than a certain predetermined size on the impaction collection surface. The impaction collection surface, even in a moderately sized apparatus, is thus relatively large and permits the prolonged sampling of air for periods extending to four weeks. 6 figs.

  11. Coal air turbine {open_quotes}CAT{close_quotes} program invention 604. Fourth quarter project report, July 1995--September 1995

    SciTech Connect (OSTI)

    Foster-Pegg, R.W.

    1995-10-31

    A coal air turbine `CAT` generates electric power and heat from coal combustion. The purpose of this project is the conceptual design of a `CAT` plant, and to make a comparison of the capital cost and and cost of power and steam from the `CAT` plant with power produced by alternate plants at the same site. Three configurations investigated include: condensing plant utilizing coal fuel and a condenser tower, or river, for cooling; a cogeneration plant utilizing coal and a steam turbine; and a cogeneration plant utilizing steam export and injection with waste coal fuel.

  12. Safety Improves Dramatically In Fluor Hanford Soil and Groundwater Remediation Project

    SciTech Connect (OSTI)

    Foster, A.L.; Gerber, M.S.; VonBargen, B.H.

    2008-07-01

    This paper describes dramatic improvements in the safety record of the Soil and Groundwater Remediation Project (SGRP) at the Hanford Site in southeast Washington state over the past four years. During a period of enormous growth in project work and scope, contractor Fluor Hanford reduced injuries, accidents, and other safety-related incidents and enhanced a safety culture that earned the SGRP Star Status in the Department of Energy's (DOE's) Voluntary Protection Program (VPP) in 2007. This paper outlines the complex and multi-faceted work of Fluor Hanford's SGRP and details the steps taken by the project's Field Operations and Safety organizations to improve safety. Holding field safety meetings and walk-downs, broadening safety inspections, organizing employee safety councils, intensively flowing down safety requirements to subcontractors, and adopting other methods to achieve remarkable improvement in safety are discussed. The roles of management, labor and subcontractors are detailed. Finally, SGRP's safety improvements are discussed within the context of overall safety enhancements made by Fluor Hanford in the company's 11 years of managing nuclear waste cleanup at the Hanford Site. (authors)

  13. Improved Decision Making through the Integration of Program and Project Management with National Environmental Policy Act Compliance

    Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-06-12

    Recommendations from the DOE Field Management Council (FMC), NEPA Improvement Team, and the Council on Environmental Quality (CEQ) for improving NEPA compliance through the integration of Program ad Project Management

  14. Coal Air Turbine ``CAT`` program invention 604. Eighth quarter project report and final for the project, August--September 1996

    SciTech Connect (OSTI)

    Foster-Pegg, R.W.

    1996-09-30

    The primary objective of this ``CAT`` project is to complete a conceptual design of this unique new combination of existing technology with cost estimates to show that the ``CAT`` system offers the economic incentive with low technical risk for a plant to be built which will demonstrate its viability. The technologies involved in the components of a ``CAT`` plant are proven, and the integration of the components into a complete plant is the only new developmental activity involved. Industry and the Federal General Services Administration (GSA), require the demonstration of a ``commercial plant`` before the viability of a new concept is accepted. To satisfy this requirement the construction of a plant of commercially viable size in excess of 15 MW if cogeneration and above 30 MW if all power, is proposed. This plant will produce economical power and heat for the owner. The plant will operate for a full commercial life and continue as an operating demonstration of the viability of the technology, gathering long term life and maintenance data, all adding to the credibility of the concept.

  15. Development of an Improved Process for Installation Projects of High Technology Manufacturing Equipment

    SciTech Connect (OSTI)

    Quintana, Sarah V.

    2014-04-30

    High technology manufacturing equipment is utilized at Los Alamos National Laboratory (LANL) to support nuclear missions. This is undertaken from concept initiation where equipment is designed and then taken through several review phases, working closely with system engineers (SEs) responsible for each of the affected systems or involved disciplines (from gasses to HVAC to structural, etc.). After the design is finalized it moves to procurement and custom fabrication of the equipment and equipment installation, including all of the paperwork involved. Not only are the engineering and manufacturing aspects important, but also the scheduling, financial forecasting, and planning portions that take place initially and are sometimes modified as the project progresses should requirements, changes or additions become necessary. The process required to complete a project of this type, including equipment installation, is unique and involves numerous steps to complete. These processes can be improved and recent work on the Direct Current Arc (DC Arc) Glovebox Design, Fabrication and Installation Project provides an opportunity to identify some important lessons learned (LL) that can be implemented in the future for continued project improvement and success.

  16. Proposed IMS infrastructure improvement project, Seward, Alaska. Final environmental impact statement

    SciTech Connect (OSTI)

    Not Available

    1994-09-01

    This Environmental Impact Statement (EIS) examines a proposal for improvements at the existing University of Alaska, Fairbanks, Institute of Marine Science (IMS), Seward Marine Center. The Exxon Valdez Oil Spill (EVOS) Trustee Council is proposing to improve the existing research infrastructure to enhance the EVOS Trustee Council`s capabilities to study and rehabilitate marine mammals, marine birds, and the ecosystem injured by the Exxon Valdez oil spill. The analysis in this document focuses on the effects associated with construction and operation of the proposed project and its proposed alternatives. The EIS gives a detailed description of all major elements of the proposed project and its alternatives; identifies resources of major concern that were raised during the scoping process; describes the environmental background conditions of those resources; defines and analyzes the potential effects of the proposed project and its alternatives on these conditions; and identifies mitigating measures that are part of the project design as well as those proposed to minimize or reduce the adverse effects. Included in the EIS are written and oral comments received during the public comment period.

  17. Reducing Plug Loads in Office Spaces: Hawaii and Guam Energy Improvement Technology Demonstration Project

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. Contract No. DE-AC36-08GO28308 National Renewable Energy Laboratory 15013 Denver West Parkway Golden, CO 80401 303-275-3000 * www.nrel.gov Reducing Plug Loads in Office Spaces Hawaii and Guam Energy Improvement Technology Demonstration Project M. Sheppy, I. Metzger, D. Cutler, and G. Holland National Renewable Energy Laboratory A. Hanada Naval Facilities Engineering Command Technical Report NREL/TP-5500-60382 January

  18. Lake Roosevelt Rainbow Trout : Habitat/Passage Improvement Project Annual Report 1999.

    SciTech Connect (OSTI)

    Jones, Charles D.

    2000-02-01

    Lake Franklin D. Roosevelt was created with the completion of the Grand Coulee Dam in 1942. The lake stretches 151 miles up-stream to the International border between the United States and Canada at the 49th parallel. Increased recreational use, subsistence and sport fishing has resulted in intense interest and possible exploitation of the resources within the lake. Previous studies of the lake and its fishery have been limited. Early studies indicate that natural reproduction within the lake and tributaries are not sufficient to support a rainbow trout (Onchoryhnchus mykiss) fishery (Scholz et. al., 1988). These studies indicate that the rainbow trout population may be limited by lack of suitable habitat for spawning and rearing (Scholz et. al., 1988). The initial phase of this project (Phase I, baseline data collection- 1990-91) was directed at the assessment of limiting factors such as quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other limiting factors. Population estimates were conducted using the Seber/LeCren removal/depletion method. After the initial assessment of stream parameters, several streams were selected for habitat/passage improvement projects (Phase II, implementation-1992-96). At the completion of project habitat improvements, the final phase (Phase III, monitoring) began. This phase will assess changes and gauge the success achieved through the improvements. The objective of the project is to correct passage barriers and improve habitat conditions of selected tributaries to Lake Roosevelt for adfluvial rainbow trout that utilize tributary streams for spawning and rearing. Streams with restorable habitats were selected for improvements. Completion of improvement efforts should increase the adfluvial rainbow trout contribution to the resident fishery in Lake Roosevelt. Three co-operating agencies, the Confederated Tribes of the Colville Reservation (CCT), the Spokane Tribe of Indians (STI

  19. Lake Roosevelt Rainbow Trout : Habitat/Passage Improvement Project : Annual Report 1998.

    SciTech Connect (OSTI)

    Jones, Charles D.

    1999-02-01

    Lake Franklin D. Roosevelt was created with the completion of the Grand Coulee Dam in 1942. The lake stretches 151 miles up-stream to the International border between the United States and Canada at the 49th parallel. Increased recreational use, subsistence and sport fishing has resulted in intense interest and possible exploitation of the resources within the lake. Previous studies of the lake and its fishery have been limited. Early studies indicate that natural reproduction within the lake and tributaries are not sufficient to support a rainbow trout (Onchoryhnchus mykiss) fishery (Scholz et. al., 1988). These studies indicate that the rainbow trout population may be limited by lack of suitable habitat for spawning and rearing (Scholz et. al., 1988). The initial phase of this project (Phase I, baseline data collection) was directed at the assessment of limiting factors such as quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other limiting factors. Population estimates were conducted using the Seber/LeCren removal/depletion method. After the initial assessment of stream parameters, several streams were selected for habitat/passage improvement projects (Phase II, implementation). At the completion of project habitat improvements, the final phase (Phase III, monitoring) began. This phase will assess changes and gauge the success achieved through the improvements. The objective of the project is to correct passage barriers and improve habitat conditions of selected tributaries to Lake Roosevelt for adfluvial rainbow trout that utilize tributary streams for spawning and rearing. Streams with restorable habitats were selected for improvements. Completion of improvement efforts should increase the adfluvial rainbow trout contribution to the resident fishery in Lake Roosevelt. Personnel of three co-operating agencies, the Confederated Tribes of the Colville Reservation (CCT), the Spokane Tribe of Indians (STI) and

  20. Lake Roosevelt Rainbow Trout : Habitat/Passage Improvement Project Annual Report 2000.

    SciTech Connect (OSTI)

    Sear, Sheri

    2001-02-01

    Lake Franklin D. Roosevelt was created with the completion of the Grand Coulee Dam in 1942. The lake stretches 151 miles up-stream to the International border between the United States and Canada at the 49th parallel. Increased recreational use, subsistence and sport fishing has resulted in intense interest and possible exploitation of the resources within the lake. Previous studies of the lake and its fishery have been limited. Early studies indicate that natural reproduction within the lake and tributaries are not sufficient to support a rainbow trout (Onchoryhnchus mykiss) fishery (Scholz et. al., 1988). These studies indicate that the rainbow trout population may be limited by lack of suitable habitat for spawning and rearing (Scholz et. al., 1988). The initial phase of this project (Phase I, baseline data collection- 1990-91) was directed at the assessment of limiting factors such as quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other limiting factors. Population estimates were conducted using the Seber/LeCren removal/depletion method. After the initial assessment of stream parameters, several streams were selected for habitat/passage improvement projects (Phase II, implementation-1992-96). At the completion of project habitat improvements, the final phase (Phase III, monitoring) began. This phase will assess changes and gauge the success achieved through the improvements. The objective of the project is to correct passage barriers and improve habitat conditions of selected tributaries to Lake Roosevelt for adfluvial rainbow trout that utilize tributary streams for spawning and rearing. Streams with restorable habitats were selected for improvements. Completion of improvement efforts should increase the adfluvial rainbow trout contribution to the resident fishery in Lake Roosevelt. Three co-operating agencies, the Confederated Tribes of the Colville Reservation (CCT), the Spokane Tribe of Indians (STI

  1. Improving the Operating Efficiency of Packaged Air Conditioners and Heat Pumps

    SciTech Connect (OSTI)

    Katipamula, Srinivas; Wang, Weimin; Vowles, Mira

    2014-03-10

    This article discusses several control strategies that can significantly reduce energy consumption associated with packaged rooftop units RTUs). Although all of the considered strategies are widely used in built-up air-handing units, they are not commonly used in existing RTUs. Both simulation and field evaluations show that adding these control strategies to existing RTUs can reduce their energy consumption by between 30% and 60%.

  2. Planning phase for the New Mexico Improved Oil Recovery Project. Final report

    SciTech Connect (OSTI)

    Martin, F.D.; Weiss, W.W.

    1991-06-01

    This project is a collaborative effort with Los Alamos National Laboratory, Sandia National Laboratories, and a number of universities throughout the country. Field and laboratory tests were proposed to investigate advanced technologies in reservoir characterization, reservoir simulation, and recovery enhancement. Basically, the approach was to acquire an oilfield property for experimental purposes where interdisciplinary testing could be performed. Several researchers, especially in the academic area, would like to have access to field data and have expressed interest in participating in the project. A standardized dataset from a well-characterized site could be made available to anyone who is developing and validating new simulators. The data-gathering phase should be coordinated fully with the principal users of the data, and all data should be stored in an easily accessible form. A database for the New Mexico Improved Oil Recovery Project (NMIORP) could be established which would be designed for access by various computer networks. Initially, this project provided for a planning phase for the NMIORP. A field site, the Sulimar Queen Unit, has been acquired by New Mexico Tech, and the activities specified in the planning phase have been completed. A data acquisition well was drilled, logged, and cored. Geological and reservoir studies for the Sulimar Queen Unit were conducted. Results of these studies indicate that the Sulimar Queen Unit is a suitable field site for the NMIORP. This report describes the results of the studies that were conducted and outlines possible future tests that could be performed at the field site.

  3. The Wind Forecast Improvement Project (WFIP). A Public-Private Partnership Addressing Wind Energy Forecast Needs

    SciTech Connect (OSTI)

    Wilczak, James M.; Finley, Cathy; Freedman, Jeff; Cline, Joel; Bianco, L.; Olson, J.; Djalaova, I.; Sheridan, L.; Ahlstrom, M.; Manobianco, J.; Zack, J.; Carley, J.; Benjamin, S.; Coulter, R. L.; Berg, Larry K.; Mirocha, Jeff D.; Clawson, K.; Natenberg, E.; Marquis, M.

    2015-10-30

    The Wind Forecast Improvement Project (WFIP) is a public-private research program, the goals of which are to improve the accuracy of short-term (0-6 hr) wind power forecasts for the wind energy industry and then to quantify the economic savings that accrue from more efficient integration of wind energy into the electrical grid. WFIP was sponsored by the U.S. Department of Energy (DOE), with partners that include the National Oceanic and Atmospheric Administration (NOAA), private forecasting companies (WindLogics and AWS Truepower), DOE national laboratories, grid operators, and universities. WFIP employed two avenues for improving wind power forecasts: first, through the collection of special observations to be assimilated into forecast models to improve model initial conditions; and second, by upgrading NWP forecast models and ensembles. The new observations were collected during concurrent year-long field campaigns in two high wind energy resource areas of the U.S. (the upper Great Plains, and Texas), and included 12 wind profiling radars, 12 sodars, 184 instrumented tall towers and over 400 nacelle anemometers (provided by private industry), lidar, and several surface flux stations. Results demonstrate that a substantial improvement of up to 14% relative reduction in power root mean square error (RMSE) was achieved from the combination of improved NOAA numerical weather prediction (NWP) models and assimilation of the new observations. Data denial experiments run over select periods of time demonstrate that up to a 6% relative improvement came from the new observations. The use of ensemble forecasts produced even larger forecast improvements. Based on the success of WFIP, DOE is planning follow-on field programs.

  4. Project 57 Air Monitoring Annual Report - Fiscal Year 2013 (October 1, 2012 to September 30, 2013)

    SciTech Connect (OSTI)

    Miller, Julianne J.; McCurdy, Greg; Mizell, Steve A

    2014-07-01

    The U.S. Department of Energy (DOE), National Nuclear Security Administration, Nevada Field Office (NNSA/NFO) is currently working to achieve regulatory closure of radionuclide-contaminated Soils sites under its auspices. Corrective Action Unit (CAU) 415, Project 57 No. 1 Plutonium Dispersion Site is located in Emigrant Valley, Nevada, on Range 4808A of the Nevada Test and Training Range (NTTR), and consists of one Corrective Action Site (CAS): NAFR-23-02, Pu Contaminated Soil. Closure plans being developed for the CAUs both on and off of the Nevada National Security Site (NNSS) may include postclosure monitoring for the possible release of radioactive contaminants. Determining the potential for transport of radionuclide-contaminated soils under ambient climatic conditions will facilitate an appropriate closure design and postclosure monitoring program. The DOE has authorized the Desert Research Institute (DRI) to conduct field assessments of potential transport of radionuclide-contaminated soil from the Project 57 site during ambient wind events. The assessment is intended to provide site-specific information on meteorological conditions that result in airborne soil particle redistribution, as well as determine which, if any, radiological contaminants may be entrained with the soil particles and estimate their concentrations.

  5. Development of improved iron Fischer-Tropsch catalysts. Final technical report: Project 6464

    SciTech Connect (OSTI)

    Bukur, D.B.; Ledakowicz, S.; Koranne, M.

    1994-02-28

    Despite the current worldwide oil glut, the United States will ultimately require large-scale production of liquid (transportation) fuels from coal. Slurry phase Fischer Tropsch (FT) technology, with its versatile product slate, may be expected to play a major role in production of transportation fuels via indirect coal liquefaction. Texas A&M University (TAMU) with sponsorship from the US Department of Energy, Center for Energy and Mineral Resources at TAMU, Texas Higher Education Coordinating Board, and Air Products and Chemicals, Inc., has been working on development of improved iron FT catalysts and characterization of hydrodynamic parameters in two- and three-phase bubble columns with FT derived waxes. Our previous studies have provided an improved understanding of the role of promoters (Cu and K), binders (silica) and pretreatment procedures on catalyst activity, selectivity and longevity (deactivation). The objective of the present contract was to develop improved catalysts with enhanced slurry phase activity and higher selectivity to liquid fuels and wax. This was accomplished through systematic studies of the effects of pretreatment procedures and variations in catalyst composition (promoters and binders). The major accomplishments and results in each of these two main areas of research are summarized here.

  6. BEETIT: Building Cooling and Air Conditioning

    SciTech Connect (OSTI)

    2010-09-01

    BEETIT Project: The 14 projects that comprise ARPA-E’s BEETIT Project, short for “Building Energy Efficiency Through Innovative Thermodevices,” are developing new approaches and technologies for building cooling equipment and air conditioners. These projects aim to drastically improve building energy efficiency and reduce greenhouse gas emissions such as carbon dioxide (CO2) at a cost comparable to current technologies.

  7. Modeling Improvements for Air Source Heat Pumps using Different Expansion Devices at Varied Charge Levels Part II

    SciTech Connect (OSTI)

    Shen, Bo [ORNL

    2011-01-01

    This paper describes steady-state performance simulations performed on a 3-ton R-22 split heat pump in heating mode. In total, 150 steady-state points were simulated, which covers refrigerant charge levels from 70 % to 130% relative to the nominal value, the outdoor temperatures at 17 F (-8.3 C), 35 F (1.7 C) and 47 F (8.3 C), indoor air flow rates from 60% to 150% of the rated air flow rate, and two types of expansion devices (fixed orifice and thermostatic expansion valve). A charge tuning method, which is to calibrate the charge inventory model based on measurements at two operation conditions, was applied and shown to improve the system simulation accuracy significantly in an extensive range of charge levels. In addition, we discuss the effects of suction line accumulator in modeling a heat pump system using either a fixed orifice or thermal expansion valve. Last, we identify the issue of refrigerant mass flow mal-distribution at low charge levels and propose an improved modeling approach.

  8. Final Report Collaborative Project. Improving the Representation of Coastal and Estuarine Processes in Earth System Models

    SciTech Connect (OSTI)

    Bryan, Frank; Dennis, John; MacCready, Parker; Whitney, Michael

    2015-11-20

    This project aimed to improve long term global climate simulations by resolving and enhancing the representation of the processes involved in the cycling of freshwater through estuaries and coastal regions. This was a collaborative multi-institution project consisting of physical oceanographers, climate model developers, and computational scientists. It specifically targeted the DOE objectives of advancing simulation and predictive capability of climate models through improvements in resolution and physical process representation. The main computational objectives were: 1. To develop computationally efficient, but physically based, parameterizations of estuary and continental shelf mixing processes for use in an Earth System Model (CESM). 2. To develop a two-way nested regional modeling framework in order to dynamically downscale the climate response of particular coastal ocean regions and to upscale the impact of the regional coastal processes to the global climate in an Earth System Model (CESM). 3. To develop computational infrastructure to enhance the efficiency of data transfer between specific sources and destinations, i.e., a point-to-point communication capability, (used in objective 1) within POP, the ocean component of CESM.

  9. Interim Report: Air-Cooled Condensers for Next Generation Geothermal Power Plants Improved Binary Cycle Performance

    SciTech Connect (OSTI)

    Daniel S. Wendt; Greg L. Mines

    2010-09-01

    As geothermal resources that are more expensive to develop are utilized for power generation, there will be increased incentive to use more efficient power plants. This is expected to be the case with Enhanced Geothermal System (EGS) resources. These resources will likely require wells drilled to depths greater than encountered with hydrothermal resources, and will have the added costs for stimulation to create the subsurface reservoir. It is postulated that plants generating power from these resources will likely utilize the binary cycle technology where heat is rejected sensibly to the ambient. The consumptive use of a portion of the produced geothermal fluid for evaporative heat rejection in the conventional flash-steam conversion cycle is likely to preclude its use with EGS resources. This will be especially true in those areas where there is a high demand for finite supplies of water. Though they have no consumptive use of water, using air-cooling systems for heat rejection has disadvantages. These systems have higher capital costs, reduced power output (heat is rejected at the higher dry-bulb temperature), increased parasitics (fan power), and greater variability in power generation on both a diurnal and annual basis (larger variation in the dry-bulb temperature). This is an interim report for the task ‘Air-Cooled Condensers in Next- Generation Conversion Systems’. The work performed was specifically aimed at a plant that uses commercially available binary cycle technologies with an EGS resource. Concepts were evaluated that have the potential to increase performance, lower cost, or mitigate the adverse effects of off-design operation. The impact on both cost and performance were determined for the concepts considered, and the scenarios identified where a particular concept is best suited. Most, but not all, of the concepts evaluated are associated with the rejection of heat. This report specifically addresses three of the concepts evaluated: the use of

  10. Innovative Evaporative and Thermally Activated Technologies Improve Air Conditioning; The Spectrum of Clean Energy Innovation (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2010-06-01

    Fact sheet describes NREL's work on a desiccant enhanced evaporative air conditioner (DEVap) that uses 90% less electricity than traditional air conditioning units.

  11. Low cost improvements in air pollution control for ARMCO's Ashland, Kentucky Works Sinter Plant

    SciTech Connect (OSTI)

    Felton, S.S. )

    1987-01-01

    Particulate emissions from sinter plants can contribute a significant percentage of the total emissions from integrated steelmaking facilities. A well-known sinter plant air pollution phenomenon is called blue haze emissions. These emissions are caused when hydrocarbons introduced by filter cake, coke breeze, and mill scale are not burned in the sintering process and pass through the system as a very finely divided stable dispersed fog. The Sinter Plant at Ashland Works consists of Dravo-Lurgi traveling grate sintering machine which processes a mixture of materials including iron ore, iron pellet fines, blast furnace flue dust, limestone, melt shop slag, coke breeze and sinter return fines. This system is illustrated by the authors. Upon completion of the sintering process, the hot agglomerated sinter product is discharged to the sinter crusher. The sinter is then cooled and screened for use in Ashland Works' Amanda Blast Furnace. This system is illustrated. The Ashland Works Sinter Plant complex consists of a Sintering Machine Building, Sinter Screens Building and Ore Screens Building. For the purposes of this study, the Ore Transfer Tower Building was also included. The general layout of the complex is illustrated.

  12. Methods to Improve the Lower Limit of Detection for Tritium in the Air and on Surfaces

    Office of Environmental Management (EM)

    Hydrogen Storage » Materials-Based Storage » Metal Hydride Storage Materials Metal Hydride Storage Materials The Fuel Cell Technologies Office's (FCTO's) metal hydride storage materials research focuses on improving the volumetric and gravimetric capacities, hydrogen adsorption/desorption kinetics, cycle life, and reaction thermodynamics of potential material candidates. Technical Overview Figure shows pressure composition isotherms and van't Hoff traces for metal hydride materials. Metal

  13. Preheated Combustion Air

    Energy.gov [DOE]

    This tip sheet describes how to improve process heating efficiency by preheating combustion air for burners.

  14. Improved Formulations for Air-Surface Exchanges Related to National Security Needs: Dry Deposition Models

    SciTech Connect (OSTI)

    Droppo, James G.

    2006-07-01

    The Department of Homeland Security and others rely on results from atmospheric dispersion models for threat evaluation, event management, and post-event analyses. The ability to simulate dry deposition rates is a crucial part of our emergency preparedness capabilities. Deposited materials pose potential hazards from radioactive shine, inhalation, and ingestion pathways. A reliable characterization of these potential exposures is critical for management and mitigation of these hazards. A review of the current status of dry deposition formulations used in these atmospheric dispersion models was conducted. The formulations for dry deposition of particulate materials from am event such as a radiological attack involving a Radiological Detonation Device (RDD) is considered. The results of this effort are applicable to current emergency preparedness capabilities such as are deployed in the Interagency Modeling and Atmospheric Assessment Center (IMAAC), other similar national/regional emergency response systems, and standalone emergency response models. The review concludes that dry deposition formulations need to consider the full range of particle sizes including: 1) the accumulation mode range (0.1 to 1 micron diameter) and its minimum in deposition velocity, 2) smaller particles (less than .01 micron diameter) deposited mainly by molecular diffusion, 3) 10 to 50 micron diameter particles deposited mainly by impaction and gravitational settling, and 4) larger particles (greater than 100 micron diameter) deposited mainly by gravitational settling. The effects of the local turbulence intensity, particle characteristics, and surface element properties must also be addressed in the formulations. Specific areas for improvements in the dry deposition formulations are 1) capability of simulating near-field dry deposition patterns, 2) capability of addressing the full range of potential particle properties, 3) incorporation of particle surface retention/rebound processes, and

  15. EA-1941: Boyer-Tillamook Access Road Improvement Project, Tillamook and Yamhill Counties, Oregon

    Office of Energy Efficiency and Renewable Energy (EERE)

    BPA prepared an EA, FONSI, and Mitigation Action Plan to assess the potential environmental impacts of proposed improvements to 13 miles of access roads for its existing 115-kV Boyer-Tillamook No. 1 Transmission Line in Tillamook and Yamhill counties, Oregon. Associated activities would include resurfacing roads, adding drainage, widening 3 miles of road, constructing 0.1 mile of new road, maintaining culverts, and constructing outlet ditches and retaining walls. In addition, new bridges would be built, and culverts that currently block fish passage for anadromous and resident fish would be replaced. Additional information is available at the project website: http://efw.bpa.gov/environmental_services/Document_Library/Boyer-Tillamook/.

  16. Improved test method to verify the power rating of a photovoltaic (PV) project.

    SciTech Connect (OSTI)

    Panchula, A.; Pligavko, A.; King, D.; Marion, B.; Townsend, T.; Mitchell, L.; Dierauf, T.; Kimber, A.; Osterwald, C. R.; Newmiller, Jeff; Emery, K.; Talmud, F.; Whitaker, Chuck; Myers, D.; Forbess, J.; Granata, Jennifer E.; Levitsky, T.

    2010-03-01

    This paper reviews the PVUSA power rating method and presents two additional methods that seek to improve this method in terms of model precision and increased seasonal applicability. It presents the results of an evaluation of each method based upon regression analysis of over 12 MW of operating photovoltaic (PV) systems located in a wide variety of climates. These systems include a variety of PV technologies, mounting configurations, and array sizes to ensure the conclusions are applicable to a wide range of PV designs and technologies. The work presented in this paper will be submitted to ASTM for use in the development of a standard test method for certifying the power rating of PV projects.

  17. Advanced reservoir characterization for improved oil recovery in a New Mexico Delaware basin project

    SciTech Connect (OSTI)

    Martin, F.D.; Kendall, R.P.; Whitney, E.M.

    1997-08-01

    The Nash Draw Brushy Canyon Pool in Eddy County, New Mexico is a field demonstration site in the Department of Energy Class III program. The basic problem at the Nash Draw Pool is the low recovery typically observed in similar Delaware fields. By comparing a control area using standard infill drilling techniques to a pilot area developed using advanced reservoir characterization methods, the goal of the project is to demonstrate that advanced technology can significantly improve oil recovery. During the first year of the project, four new producing wells were drilled, serving as data acquisition wells. Vertical seismic profiles and a 3-D seismic survey were acquired to assist in interwell correlations and facies prediction. Limited surface access at the Nash Draw Pool, caused by proximity of underground potash mining and surface playa lakes, limits development with conventional drilling. Combinations of vertical and horizontal wells combined with selective completions are being evaluated to optimize production performance. Based on the production response of similar Delaware fields, pressure maintenance is a likely requirement at the Nash Draw Pool. A detailed reservoir model of pilot area was developed, and enhanced recovery options, including waterflooding, lean gas, and carbon dioxide injection, are being evaluated.

  18. Comparison of Global Model Results from the Carbon-Land Model Intercomparison Project (C-LAMP) with Free-Air Carbon Dioxide Enrichment (FACE) Manipulation Experiments

    SciTech Connect (OSTI)

    Hoffman, Forrest M; Randerson, Jim; Fung, Inez; Thornton, Peter E; Covey, Curtis; Bonan, Gordon; Running, Steven; Norby, Richard J

    2008-01-01

    Free-Air CO{sub 2} Enrichment (FACE) manipulation experiments have been carried out at a handful of sites to gauge the response of the biosphere to significant increases in atmospheric [CO{sub 2}]. Early synthesis results from four temperate forest sites suggest that the response of net primary productivity (NPP) is conserved across a broad range of productivity with a stimulation at the median of 23 {+-} 2% when the surrounding air [CO{sub 2}] was raised to 550{approx}ppm. As a part of the Carbon-Land Model Intercomparison Project (C-LAMP), a community-based model-data comparison activity, the authors have performed a global FACE modeling experiment using two terrestrial biogeochemistry modules, CLM3-CASA and CLM3-CN, coupled to the National Center for Atmospheric Research (NCAR) Community Climate System Model (CCSM). The two models were forced with an improved NCEP/NCAR reanalysis data set and reconstructed atmospheric [CO{sub 2}] and N deposition data through 1997. At the beginning of 1997 in the transient simulations, global atmospheric [CO{sub 2}] was abruptly raised to 550{approx}ppm, the target value used at the FACE sites. In the control runs, [CO{sub 2}] continued to rise following observations until 2004, after which it was held constant out to year 2100. In both simulations, the last 25 years of reanalysis forcing and a constant N deposition were applied after year 2004. Across all forest biomes, the NPP responses from both models are weaker than those reported for the four FACE sites. Moreover, model responses vary widely geographically with a decreasing trend of NPP increases from 40{sup o}N to 70{sup o}N. For CLM3-CASA, the largest responses occur in arid regions of western North America and central Asia, suggesting that responses are most strongly influenced by increased water use efficiency for this model. CLM3-CN exhibits consistently weaker responses than CLM3-CASA' with the strongest responses in central Asia, but significantly constrained by N

  19. Means of improving the operating efficiency of air condensers at the Verkhne-Mutnovskaya Geothermal Power Plant in Kamchatka

    SciTech Connect (OSTI)

    Parshin, B. E.; Muratov, P. V.; Pashkevich, R. I.

    2007-07-15

    Operation of the Verkhne-Mutnovskaya Geothermal Power Plant (VMGPP) has revealed ineffective summer-time performance of air condensers (AC), which is caused by an insufficient heat reserve. Four alternate schemes are examined for improvement of the operational efficiency of the AC: replacement of the four-by five-tier heat-exchange modules; installation of high-output fans; a combination of the first two schemes; and, installation of additional sections in each power-generating set. Based on thermodynamic analysis that we have adapted for conditions at the VMGPP, it is established that the last alternate scheme is optimal, andwill have a payback period of six years, and a heat reserve of more than 40%, a figure approaching requirements now in force.

  20. Transportation Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Technology Validation » Transportation Projects Transportation Projects Because highway vehicles account for a large share of petroleum use, carbon dioxide (a primary greenhouse gas) emissions, and air pollution, advances in fuel cell power systems for transportation could substantially improve our energy security and air quality. However, few fuel-cell-powered vehicles are in use today; even fewer are available commercially. A number of fuel cell vehicle demonstrations are currently underway

  1. Recommendations to Improve Earned Value Management (EVM) and Project Management Integration in the Department of Energy (DOE)

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Recommendations to Improve Earned Value Management (EVM) and Project Management Integration in the Department of Energy (DOE) Conducted for: Office of Project Management Oversight and Assessments (PMOA) PM-1 Prepared by: Humphreys & Associates, Inc. 9910 Research Drive Irvine, CA 92618 (714) 685-1730; Fax (714) 685-1734 www.humphreys-assoc.com August 14, 2015 © 2015 Humphreys & Associates, Inc. All rights reserved. i www.humphreys-assoc.com Table of Contents Table of Figures

  2. FY 2012 Overall Contract and Project Management Improvement Performance Metrics and Targets

    Energy.gov [DOE]

    Overall Contract and Project Management Performance Metrics and Targets for FY 2012, first quarter through fourth quarter.

  3. FY 2014 Overall Contract and Project Management Improvement Performance Metrics and Targets

    Energy.gov [DOE]

    Overall Contract and Project Management Performance Metrics and Targets for FY 2014, first quarter through fourth quarter.

  4. FY 2011 Overall Contract and Project Management Improvement Performance Metrics and Targets

    Energy.gov [DOE]

    Overall Contract and Project Management Performance Metrics and Targets for FY 2011, first quarter through fourth quarter.

  5. FY 2010 Overall Contract and Project Management Improvement Performance Metrics and Targets

    Energy.gov [DOE]

    Overall Contract and Project Management Performance Metrics and Targets for FY 2010, first quarter through fourth quarter.

  6. FY 2016 Overall Contract and Project Management Improvement Performance Metrics and Targets

    Energy.gov [DOE]

    Overall Contract and Project Management Performance Metrics and Targets for FY 2016, first quarter through fourth quarter.

  7. Aire Valley Environmental | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    Aire Valley Environmental Jump to: navigation, search Name: Aire Valley Environmental Place: United Kingdom Product: Leeds-based waste-to-energy project developer. References: Aire...

  8. Chapter 22: Compressed Air Evaluation Protocol. The Uniform Methods Project: Methods for Determining Energy Efficiency Savings for Specific Measures: September 2011 … December 2014

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    2: Compressed Air Evaluation Protocol The Uniform Methods Project: Methods for Determining Energy Efficiency Savings for Specific Measures Created as part of subcontract with period of performance September 2011 - December 2014 Nathanael Benton Nexant, Inc. San Francisco, California NREL Technical Monitor: Charles Kurnik Subcontract Report NREL/SR-7A40-63210 November 2014 NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency & Renewable Energy Operated by

  9. Olkiluoto 1 and 2 - Plant efficiency improvement and lifetime extension-project (PELE) implemented during outages 2010 and 2011

    SciTech Connect (OSTI)

    Kosonen, M.; Hakola, M.

    2012-07-01

    Teollisuuden Voima Oyj (TVO) is a non-listed public company founded in 1969 to produce electricity for its stakeholders. TVO is the operator of the Olkiluoto nuclear power plant. TVO follows the principle of continuous improvement in the operation and maintenance of the Olkiluoto plant units. The PELE project (Plant Efficiency Improvement and Lifetime Extension), mainly completed during the annual outages in 2010 and 2011, and forms one part of the systematic development of Olkiluoto units. TVO maintains a long-term development program that aims at systematically modernizing the plant unit systems and equipment based on the latest technology. According to the program, the Olkiluoto 1 and Olkiluoto 2 plant units are constantly renovated with the intention of keeping them safe and reliable, The aim of the modernization projects is to improve the safety, reliability, and performance of the plant units. PELE project at Olkiluoto 1 was done in 2010 and at Olkiluoto 2 in 2011. The outage length of Olkiluoto 1 was 26 d 12 h 4 min and Olkiluoto 2 outage length was 28 d 23 h 46 min. (Normal service-outage is about 14 days including refueling and refueling-outage length is about seven days. See figure 1) The PELE project consisted of several single projects collected into one for coordinated project management. Some of the main projects were as follows: - Low pressure turbines: rotor, stator vane, casing and turbine instrumentation replacement. - Replacement of Condenser Cooling Water (later called seawater pumps) pumps - Replacement of inner isolation valves on the main steam lines. - Generator and the generator cooling system replacement. - Low voltage switchgear replacement. This project will continue during future outages. PELE was a success. 100 TVO employees and 1500 subcontractor employees participated in the project. The execution of the PELE projects went extremely well during the outages. The replacement of the low pressure turbines and seawater pumps improved the

  10. Improving Vortex Generators to Enhance the Performance of Air-Cooled Condensers in a Geothermal Power Plant

    SciTech Connect (OSTI)

    Manohar S. Sohal

    2005-09-01

    Colburn j-factor) associated with deployment of the winglets with circular as well as oval tubes. In general, toe-in (common flow up) type winglets appear to have better performance than the toe-out (common flow down) type winglets. Comparisons of heat transfer and pressure drop results for the elliptical tube versus a circular tube with and without winglets are provided. During the course of their independent research, all of the researchers have established that about 10 to 30% enhancement in Colburn j-factor is expected. However, actual increase in heat transfer rate from a heat exchanger employing finned tubes with winglets may be smaller, perhaps on the order of 2 to 5%. It is also concluded that for any specific application, more full-size experimentation is needed to optimize the winglet design for a specific heat exchanger application. If in place of a circular tube, an oval tube can be economically used in a bundle, it is expected that the pressure drop across the tube bundle with the application of vortex generators (winglets) will be similar to that in a conventional circular tube bundle. It is hoped that the results of this research will demonstrate the benefits of applying vortex generators (winglets) on the fins to improve the heat transfer from the air-side of the tube bundle.

  11. Improve Compressed Air System Performance with AIRMaster+, Software Tools for Industry, Industrial Technologies Program (ITP) (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2008-12-01

    This fact sheet describes how the Industrial Technologies Program AIRMaster+ software tool can help industrial plants optimize compressed air system efficiency.

  12. Department of Energy Announces 22 New Projects to Enable Emissions Reductions and Improve Energy Efficiency

    Energy.gov [DOE]

    The Energy Department’s Advanced Research Projects Agency-Energy (ARPA-E) today announced $60 million in funding for 22 innovative new projects aimed at detecting and measuring methane emissions and developing localized thermal management systems that reduce the energy needed to heat and cool buildings. The projects are funded through ARPA-E’s two newest programs: Methane Observation Networks with Innovative Technology to Obtain Reductions (MONITOR) and Delivering Efficient Local Thermal Amenities (DELTA).

  13. PROJECT PROFILE: Improving PV performance Estimates in the System Advisor Model with Component and System Reliability Metrics

    Office of Energy Efficiency and Renewable Energy (EERE)

    This project will improve the forecasting of lifetime PV system performance as well as operations and maintenance costs by incorporating the Photovoltaic Reliability and Performance Model (PV-RPM) developed by Sandia into the widely-used Solar Advisor Model (SAM) software platform.

  14. Energy Department Awards $8.4 Million for Projects to Improve...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    The four projects selected for award are: Filter Sensing Technologies, Inc. - Cambridge, MA - 2.0 million Filter Sensing Technologies will develop and demonstrate low-cost, robust ...

  15. FY 2015 Overall Contract and Project Management Improvement Performance Metrics and Targets

    Energy.gov [DOE]

    The Root Cause Analysis report identifies the key elements necessary to make the meaningful changes required to consistently deliver projects within cost and schedule performance parameters.

  16. Riding the Clean Energy Wave: New Projects Aim to Improve Water Power Devices

    Energy.gov [DOE]

    The Energy Department announces two projects as part of a larger effort to deploy innovative technologies for clean, domestic power generation from water power resources.

  17. One of EM's Last Recovery Act Projects at Oak Ridge Improves...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    arriving at a safer, cleaner campus to conduct their advanced research." The project's main objective was to deactivate a ventilation branch connected to ORNL's central gaseous...

  18. Investigation of techniques to improve continuous air monitors under conditions of high dust loading in environmental setting. 1998 annual progress report

    SciTech Connect (OSTI)

    Schery, S.D.; Wasiolek, P.T. [New Mexico Inst. of Mining and Technology, Socorro, NM (US); Rodgers, J. [Los Alamos National Lab., NM (US)

    1998-06-01

    'Improvement in understanding of the deposition of ambient dust particles on ECAM (Environmental Continuous Air Monitor) filters, reduction of the alpha-particle interference of radon progeny and other radioactive aerosols in different particle size ranges on filters, and development of ECAM''s with increased sensitivity under dusty outdoor conditions. As of May 1, 1998 (1/2 year into the project) the research-prototype 30-cm pulsed ionization chamber (PIC) is assembled and operational with an alpha particle energy resolution of better than 45 keV for 5-MeV alpha particles. Measurements of spectral resolution for alpha particles from radon decay products have been made as a function of filter type and dust loading conditions. So far, a study of ten filter types has found that the best combination of resolution and throughput is obtained with 3.0 \\265m Millipore fluoropore and 1.0 \\265m Corning FNMB filters. Experiments with gypsum and Portland cement dust in the size range 1 to 20 \\265m indicate significant degradation in alpha particle resolution for dust loading above about 0.5 mg cm{sup -2}. Study of metalized films for possible use as a PIC window indicate a minimum broadening of 5-MeV alpha particle peaks from 43 (no film) to 301 keV (with film) for AVR film type B8 (0.20 mg cm{sup -2} polycarbonate). A modified ECAM sampling head, equipped with an optical microscopy system feeding data to a high resolution video data capture and logging instrument, was constructed. This system will enable time-lapse study of dust build-up on ECAM filters and formation of dendrite structures that can reduce alpha-particle resolution.'

  19. Custom Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Energy Management Small Industrial Lighting Compressed Air ESUE Motors Federal Agriculture Custom Projects No two industrial customers are alike; each has its own unique...

  20. Improving DOE Project Performance Using the DOD Integrated Master Plan - 12481

    SciTech Connect (OSTI)

    Alleman, Glen B.; Nosbisch, Michael R.

    2012-07-01

    DOE O 413 measures a project's progress to plan by the consumption of funding, the passage of time, and the meeting of milestones. In March of 2003, then Under Secretary, Energy, Science, Card received a memo directing the implementation of Project Management and the Project Management Manual, including the Integrated Master Plan and Integrated Master Schedule. This directive states 'the integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress'. This paper shows how restoring the IMP/IMS paradigm to DOE program management increases the probability of program success in ways not currently available using DOD O 413 processes alone. Using DOE O 413 series guidance, adding the Integrated Master Plan and Integrated Master Schedule paradigm would provide a hierarchical set of performance measures for each 'package of work,' that provides measurable visibility to the increasing maturity of the project. This measurable maturity provides the mechanism to forecast future performance of cost, schedule, and technical outcomes in ways not available using just the activities in DOE O 413. With this information project managers have another tool available to address the issues identified in GAO-07-336 and GAO-09-406. (authors)

  1. NATURALHY Project Overview

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    step towards the hydrogen economy by using the existing natural gas grid (the NATURALHY-project) Onno Florisson N.V. Nederlandse Gasunie Prepared by O. Florisson Gasunie Main political drivers towards H2 * Improvement of the energy security * Reduction of the CO2-emission (Kyoto, > 8% reduction by 2010) * Improvement of region air quality Prepared by O. Florisson Gasunie The transition to the hydrogen-economy will be lengthy, costly and will require significant R&D PRACTICAL STRATEGY

  2. Fact #568: April 27, 2009 For Modern Cars, Replacing an Air Filter Will Improve Performance but Not Fuel Economy

    Energy.gov [DOE]

    A February 2009 study conducted by Oak Ridge National Laboratory found that for modern computer-controlled, fuel-injected engines, changing a clogged air filter has no measurable affect on fuel...

  3. Projecting

    U.S. Energy Information Administration (EIA) (indexed site)

    Projecting the scale of the pipeline network for CO2-EOR and its implications for CCS infrastructure development Matthew Tanner Office of Petroleum, Gas, & Biofuels Analysis U.S. Energy Information Administration October 25, 2010 This paper is released to encourage discussion and critical comment. The analysis and conclusions ex- pressed here are those of the author and not necessarily those of the U.S. Energy Information Administration. Author: Matthew Tanner, matthew.tanner@eia.gov

  4. Lessons from Iowa : development of a 270 megawatt compressed air energy storage project in midwest Independent System Operator : a study for the DOE Energy Storage Systems Program.

    SciTech Connect (OSTI)

    Holst, Kent; Huff, Georgianne; Schulte, Robert H.; Critelli, Nicholas

    2012-01-01

    The Iowa Stored Energy Park was an innovative, 270 Megawatt, $400 million compressed air energy storage (CAES) project proposed for in-service near Des Moines, Iowa, in 2015. After eight years in development the project was terminated because of site geological limitations. However, much was learned in the development process regarding what it takes to do a utility-scale, bulk energy storage facility and coordinate it with regional renewable wind energy resources in an Independent System Operator (ISO) marketplace. Lessons include the costs and long-term economics of a CAES facility compared to conventional natural gas-fired generation alternatives; market, legislative, and contract issues related to enabling energy storage in an ISO market; the importance of due diligence in project management; and community relations and marketing for siting of large energy projects. Although many of the lessons relate to CAES applications in particular, most of the lessons learned are independent of site location or geology, or even the particular energy storage technology involved.

  5. Rooftop Unitary Air Conditioner with Integral Dedicated Outdoor Air System

    SciTech Connect (OSTI)

    Tiax Llc

    2006-02-28

    Energy use of rooftop and other unitary air-conditioners in commercial applications accounts for about 1 quad (10{sup 15} Btu) of primary energy use annually in the U.S. [Reference 7]. The realization that this cooling equipment accounts for the majority of commercial building cooled floorspace and the majority also of commercial building energy use has spurred development of improved-efficiency equipment as well as development of stricter standards addressing efficiency levels. Another key market driver affecting design of rooftop air-conditioning equipment has been concern regarding comfort and the control of humidity. Trends for increases in outdoor air ventilation rates in certain applications, and the increasing concern about indoor air quality problems associated with humidity levels and moisture in buildings points to a need for improved dehumidification capability in air-conditioning equipment of all types. In many cases addressing this issue exacerbates energy efficiency, and vice versa. The integrated dedicated outdoor air system configuration developed in this project addresses both energy and comfort/humidity issues.

  6. Using Net-Zero Energy Projects to Enable Sustainable Economic Redevelopment at the Former Brunswick Air Naval Base

    SciTech Connect (OSTI)

    Huffman, S.

    2011-10-01

    A Study Prepared in Partnership with the Environmental Protection Agency for the RE-Powering America's Land Initiative: Siting Renewable Energy on Potentially Contaminated Land and Mine Sites. The Brunswick Naval Air Station is a naval air facility and Environmental Protection Agency (EPA) Super Fund site that is being cleaned up, and closed down. The objective of this report is not only to look at the economics of individual renewable energy technologies, but also to look at the systemic benefits that can be gained when cost-effective renewable energy technologies are integrated with other systems and businesses in a community; thus multiplying the total monetary, employment, and quality-of-life benefits they can provide to a community.

  7. Compressed Air System Modifications Improve Efficiency at a Plastics Blow Molding Plant (Southeastern Container Plant): Office of Industrial Technologies (OIT) BestPractices Technical Case Study

    SciTech Connect (OSTI)

    Wogsland, J.

    2001-06-18

    This case study is one in a series on industrial firms who are implementing energy efficient technologies and system improvements into their manufacturing processes. This case study documents the activities, savings, and lessons learned on the plastics blow molding plant project.

  8. Reducing Plug Loads in Office Spaces: Hawaii and Guam Energy Improvement Technology Demonstration Project

    SciTech Connect (OSTI)

    Sheppy, M.; Metzger, I.; Cutler, D.; Holland, G.; Hanada, A.

    2014-01-01

    As part of its overall strategy to meet its energy goals, the Naval Facilities Engineering Command (NAVFAC) partnered with the Department of Energy's National Renewable Energy Laboratory (NREL) to rapidly demonstrate and deploy cost-effective renewable energy and energy efficiency technologies. This project was one of several demonstrations of new or underutilized commercial energy technologies. The common goal was to demonstrate and measure the performance and economic benefit of the system while monitoring any ancillary impacts to related standards of service and operation and maintenance (O&M) practices. In short, demonstrations at naval facilities simultaneously evaluate the benefits and compatibility of the technology with the U.S. Department of Defense (DOD) mission, and with NAVFAC's design, construction, operations, and maintenance practices, in particular. This project demonstrated the performance of commercially available advanced power strips (APSs) for plug load energy reductions in building A4 at Joint Base Pearl Harbor-Hickam (JBPHH), Hawaii.

  9. Residential Energy Efficiency Demonstration: Hawaii and Guam Energy Improvement Technology Demonstration Project

    SciTech Connect (OSTI)

    Earle, L.; Sparn, B.; Rutter, A.; Briggs, D.

    2014-03-01

    In order to meet its energy goals, the Department of Defense (DOD) has partnered with the Department of Energy (DOE) to rapidly demonstrate and deploy cost-effective renewable energy and energy-efficiency technologies. The scope of this project was to demonstrate tools and technologies to reduce energy use in military housing, with particular emphasis on measuring and reducing loads related to consumer electronics (commonly referred to as 'plug loads'), hot water, and whole-house cooling.

  10. General Motors LLC Final Project Report: Improving Energy Efficiency by Developing Components for Distributed Cooling and Heating Based on Thermal Comfort Modeling

    SciTech Connect (OSTI)

    Bozeman, Jeffrey; Chen, Kuo-Huey

    2014-12-09

    On November 3, 2009, General Motors (GM) accepted U.S. Department of Energy (DOE) Cooperative Agreement award number DE-EE0000014 from the National Energy Technology Laboratory (NETL). GM was selected to execute a three-year cost shared research and development project on Solid State Energy Conversion for Vehicular Heating, Ventilation & Air Conditioning (HVAC) and for Waste Heat Recovery.

  11. Compliance Monitoring of Underwater Blasting for Rock Removal at Warrior Point, Columbia River Channel Improvement Project, 2009/2010

    SciTech Connect (OSTI)

    Carlson, Thomas J.; Johnson, Gary E.; Woodley, Christa M.; Skalski, J. R.; Seaburg, Adam

    2011-05-10

    The U.S. Army Corps of Engineers, Portland District (USACE) conducted the 20-year Columbia River Channel Improvement Project (CRCIP) to deepen the navigation channel between Portland, Oregon, and the Pacific Ocean to allow transit of fully loaded Panamax ships (100 ft wide, 600 to 700 ft long, and draft 45 to 50 ft). In the vicinity of Warrior Point, between river miles (RM) 87 and 88 near St. Helens, Oregon, the USACE conducted underwater blasting and dredging to remove 300,000 yd3 of a basalt rock formation to reach a depth of 44 ft in the Columbia River navigation channel. The purpose of this report is to document methods and results of the compliance monitoring study for the blasting project at Warrior Point in the Columbia River.

  12. Lawrence Livermore National Laboratory Quality Assurance Project Plan for National Emission Standards for Hazardous Air Pollutants (NESHAPs), Subpart H

    SciTech Connect (OSTI)

    Hall, L.; Biermann, A

    2000-06-27

    As a Department of Energy (DOE) Facility whose operations involve the use of radionuclides, Lawrence Livermore National Laboratory (LLNL) is subject to the requirements of 40 CFR 61, the National Emission Standards for Hazardous Air Pollutants (NESHAPs). Subpart H of this Regulation establishes standards for exposure of the public to radionuclides (other than radon) released from DOE Facilities (Federal Register, 1989). These regulations limit the emission of radionuclides to ambient air from DOE facilities (see Section 2.0). Under the NESHAPs Subpart H Regulation (hereafter referred to as NESHAPs), DOE facilities are also required to establish a quality assurance program for radionuclide emission measurements; specific requirements for preparation of a Quality Assurance Program Plan (QAPP) are given in Appendix B, Method 114 of 40 CFR 61. Throughout this QAPP, the specific Quality Assurance Method elements of 40 CFR 61 Subpart H addressed by a given section are identified. In addition, the US Environmental Protection Agency (US EPA) (US EPA, 1994a) published draft requirements for QAPP's prepared in support of programs that develop environmental data. We have incorporated many of the technical elements specified in that document into this QAPP, specifically those identified as relating to measurement and data acquisition; assessment and oversight; and data validation and usability. This QAPP will be evaluated on an annual basis, and updated as appropriate.

  13. Radioactive Air Emission Notice of Construction for (NOC) Plutonium Finishing Plant (PFP) Project W-460 Plutonium Stabilization and Handling

    SciTech Connect (OSTI)

    JANSKY, M.T.

    2000-03-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions & Defense Waste Section as a notice of construction (NOC) in accordance with Washington Administrative Code (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A,'' Appendix A (WAC 246-247-1 IO) lists the requirements that must be addressed. Additionally, the following description, attachments, and references are provided to the U.S. Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40 Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants.'' The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI) and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also constitutes EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2), will be provided later. This NOC covers the activities associated with the construction and operation activities involving stabilization and/or repackaging of plutonium in the 2736-ZB Building. An operations support trailer will be installed in the proximity of the 2736-ZB Building. A new

  14. Advanced Overfire Air system and design

    SciTech Connect (OSTI)

    Gene berkau

    2004-07-30

    The objective of the proposed project is to design, install and optimize a prototype advanced tangential OFA air system on two mass feed stoker boilers that can burn coal, biomass and a mixture of these fuels. The results will be used to develop a generalized methodology for retrofit designs and optimization of advanced OFA air systems. The advanced OFA system will reduce particulate and NOx emissions and improve overall efficiency by reducing carbon in the ash and excess oxygen. The advanced OFA will also provide capabilities for carrying full load and improved load following and transitional operations.

  15. Project W420 Air Sampler Probe Placement Qualification Tests for Four 6-Inch Diameter Stacks: 296-A-25, 296-B-28, 296-S-22, and 296-T-18

    SciTech Connect (OSTI)

    Maughan, A.D.; Glissmeyer, J.A.

    1998-09-30

    The W420 project covers the upgrading of effluent monitoring systems at six ventilation exhaust stacks in tank-farm facilities at the U.S. Department of Energy's Hanford Site. The discharge stacks of five of the six systems will be completely replaced. Four of these (296-A-25, 296-B-28, 296-S-22, and 296-T-18) will be of the same size, 6-inches in diameter and about 12-ft high. This report documents tests that were conducted to verify that these four stacks meet the applicable regulatory criteria regarding the placement of the air sampling probe. These criteria ensure that the contaminants in the stack are well mixed with the airflow at the location of the probe such that the extracted sample represents the whole. There are also criteria addressing the transport of the sample to the collection device. These are not covered in this report, but will need to be addressed later. These tests were conducted by Pacific Northwest National Laboratory on a full-scale model of the 6-inch stick. The sequence of tests addresses the acceptability of the flow angle relative to the probe and the uniformity of air velocity and gaseous and particle tracers in the cross section of the stack. All tests were successful, and all acceptance criteria were met.

  16. A proposal to improve ecological compensation practice in road and railway projects in Spain

    SciTech Connect (OSTI)

    Villarroya, Ana Puig, Jordi

    2013-09-15

    To reduce ecological impacts caused by development projects, avoidance, minimization and compensation techniques have to be taken together into consideration along Environmental Impact Assessment (EIA) procedures. This paper explores the particular role that ecological compensation has had in recent road and railway EIA procedures in Spain, as seen through the review of a set of recent EIA Records of Decision (RODs) that confirms precedent findings. Noticing that residual impacts are not paid much attention, and that there is no evidence of a solid public participation in ecological impact evaluation, it proposes to increase the awareness on residual impacts, as a way to make easier public access to the allegedly most sensitive moment of EIA implementation: (residual) impact evaluation. -- Highlights: ► Ecological compensation practice in Spain is much lower than avoidance or mitigation. ► Residual impacts are overlooked in EIA processes and public participation is low. ► An increased awareness of residual impacts may also promote public participation. ► Current context needs these small steps to move towards better compensation practice.

  17. DOE Secretarial Memorandum on Improved Decision Making through the Integration of Program and Project Management with National Environmental Policy Act Compliance (DOE, 2012)

    Energy.gov [DOE]

    Declaring that “Compliance with [NEPA] is a pre-requisite to successful implementation of DOE programs and projects,” the Secretary has signed a memorandum on "Improved Decision Making through the...

  18. An Improved Method to Determine {sup 210}Pb, {sup 210}Bi and {sup 210}Po in air Aerosol Filters

    SciTech Connect (OSTI)

    Miguel, E. G. San; Bolivar, J. P.; Teran, T.

    2008-08-07

    {sup 222}Rn daughters (e.g. {sup 210}Pb, {sup 210}Po, {sup 210}Bi) have been widely used to study a variety of atmospheric processes. Many works in literature about {sup 222}Rn daughters do not specify the way by the activities of these radionuclides are calculated. Besides, {sup 210}Po corrections due to the in-growth of {sup 210}Bi, if taken into account, are not indicated. In this work, the increase in uncertainties of radionuclides activities due to delay between air sampling and radionuclides determinations have been evaluated and the influence of neglecting the contribution of {sup 210}Bi in-growth to {sup 210}Po determination has been estimated. The results indicate that, in general, ignoring the {sup 210}Bi in-growth in {sup 210}Po determinations lead to significant differences (could reach until 100%) between the estimation of {sup 210}Po activity and its true value.

  19. Surface Environmental Surveillance Project: Locations Manual Volume 1 – Air and Water Volume 2 – Farm Products, Soil & Vegetation, and Wildlife

    SciTech Connect (OSTI)

    Fritz, Brad G.; Patton, Gregory W.; Stegen, Amanda; Poston, Ted M.

    2009-01-01

    This report describes all environmental monitoring locations associated with the Surface Environmental Surveillance Project. Environmental surveillance of the Hanford site and surrounding areas is conducted by the Pacific Northwest National Laboratory (PNNL) for the U.S. Department of Energy (DOE). Sampling is conducted to evaluate levels of radioactive and nonradioactive pollutants in the Hanford environs, as required in DOE Order 450.1, Environmental Protection Program, and DOE Order 5400.5, Radiation Protection of the Public and the Environment. The environmental surveillance sampling design is described in the Hanford Site Environmental Monitoring Plan, United States Department of Energy, Richland Operation Office (DOE/RL-91-50). This document contains the locations of sites used to collect samples for the Surface Environmental Surveillance Project (SESP). Each section includes directions, maps, and pictures of the locations. A general knowledge of roads and highways on and around the Hanford Site is necessary to successfully use this manual. Supplemental information (Maps, Gazetteer, etc.) may be necessary if user is unfamiliar with local routes. The SESP is a multimedia environmental surveillance effort to measure the concentrations of radionuclides and chemicals in environmental media to demonstrate compliance with applicable environmental quality standards and public exposure limits, and assessing environmental impacts. Project personnel annually collect selected samples of ambient air, surface water, agricultural products, fish, wildlife, and sediments. Soil and vegetation samples are collected approximately every 5 years. Analytical capabilities include the measurement of radionuclides at very low environmental concentrations and, in selected media, nonradiological chemicals including metals, anions, volatile organic compounds, and total organic carbon.

  20. Coal air turbine {open_quotes}CAT{close_quotes} program, Invention 604. Third quarter project report, April 1995--June 1995

    SciTech Connect (OSTI)

    Foster-Pegg, R.W.

    1995-07-31

    The primary objective of this {open_quotes}CAT{close_quotes} project is to complete a conceptual design of this unique new combination of existing technology with cost estimates to show that the {open_quotes}CAT{close_quotes} system offers the economic incentive with low technical risk for a plant to be built which will demonstrate its viability. The technologies involved in the components of a {open_quotes}CAT{close_quotes} plant are proven, and the integration of the components into a complete plant is the only new development activity involved. Industry and the Federal General Services Administration (GSA), require the demonstration of a {open_quotes}commercial plant{close_quotes} before the viability of a new concept is accepted. To satisfy this requirement and construction of a plant of commercially viable size in excess of 15 MW if cogeneration and above 30 MW if all power, is proposed. This plant will produce economical power and heat for the owner. The plant will operate a full commercial life and continue as an operating demonstration of the viability of the technology, gathering long term life and maintenance data, all adding to the credibility of the concept.

  1. DunoAir | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    DunoAir Jump to: navigation, search Name: DunoAir Place: Hessen, Germany Zip: 6865 VX Sector: Wind energy Product: Doorwerth-based wind project developer. References: DunoAir1...

  2. Building America: Smarter Indoor Air Quality Solutions | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Energy Building America: Smarter Indoor Air Quality Solutions Building America: Smarter Indoor Air Quality Solutions The Building America projects exemplify how added tightness with improved source control, dilution, and high efficiency filtration can have little or no energy penalty. This page provides a brief description of the teams, areas of focus, and key team members. Learn more about Building America's world-class research. Team Lead: Gas Technology Institute-Des Plaines, IL Team

  3. Optimization of hybrid-water/air-cooled condenser in an enhanced turbine

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    geothermal ORC system | Department of Energy Optimization of hybrid-water/air-cooled condenser in an enhanced turbine geothermal ORC system Optimization of hybrid-water/air-cooled condenser in an enhanced turbine geothermal ORC system DOE Geothermal Program Peer Review 2010 - Presentation. Project objective: To improve the efficiency and output variability of geothermal-based ORC power production systems with minimal water consumption by deploying: 1) a hybrid-water/air cooled condenser with

  4. Are Ventilation Filters Degrading Indoor Air Quality in California Classrooms?

    SciTech Connect (OSTI)

    Fisk, William J.; Destaillats, H.; Apte, M.G.; Destaillats,, Hugo; Fisk, Michael G. Apte and William J.

    2008-10-01

    Heating, ventilating, and cooling classrooms in California consume substantial electrical energy. Indoor air quality (IAQ) in classrooms affects studenthealth and performance. In addition to airborne pollutants that are emitted directly by indoor sources and those generated outdoors, secondary pollutants can be formed indoors by chemical reaction of ozone with other chemicals and materials. Filters are used in nearly all classroom heating, ventilation and air?conditioning (HVAC) systems to maintain energy-efficient HVAC performance and improve indoor air quality; however, recent evidence indicates that ozone reactions with filters may, in fact, be a source of secondary pollutants. This project quantitatively evaluated ozone deposition in HVAC filters and byproduct formation, and provided a preliminary assessment of the extent towhich filter systems are degrading indoor air quality. The preliminary information obtained will contribute to the design of subsequent research efforts and the identification of energy efficient solutions that improve indoor air quality in classrooms and the health and performance of students.

  5. Compressed Air

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Lighting Compressed Air ESUE Motors Federal Agriculture Compressed Air Compressed Air Roadmap The Bonneville Power Administration created the roadmap to help utilities find energy...

  6. Air Quality

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Air Quality Air Quality To preserve our existing wilderness-area air quality, LANL implements a conscientious program of air monitoring. March 17, 2015 Real-time data monitoring ...

  7. Integrated Technology Air Cleaners (ITAC): Design and Evaluation

    SciTech Connect (OSTI)

    Fisk, William J.; Cohn, Sebastian; Destaillats, Hugo; Henzel, Victor; Sidheswaran, Meera; Sullivan, Douglas P.

    2013-09-13

    The primary objective of this project was to design, build, and test an air cleaner for residential use with the potential to substantially improve indoor air quality, or maintain indoor air quality unchanged, when outdoor air ventilation rates are reduced to save energy. Two air cleaners were designed and fabricated. The design targets for airflow rate, fan power, and projected cost were met. In short term laboratory studies, both units performed as expected; however, during field studies in homes, the formaldehyde removal performance of the air cleaners was much lower than expected. In subsequent laboratory studies, incomplete decomposition of some indoor air volatile organic compounds, with formaldehyde as a product of partial decomposition of volatile organic compounds, was confirmed as the explanation for the poor formaldehyde removal performance in the field studies. The amount of formaldehyde produced per unit of decomposition of other volatile organic compounds was substantially diminished by increasing the amount of catalyst on the filter and also by decreasing the air velocity. Together, these two measures reduced formaldehyde production, per unit destruction of other volatile organic compounds, by a factor of four, while increasing the removal efficiency of volatile organic compounds by a factor of 1.4. A company with a southern California office is conducting studies in conjunction with Lawrence Berkeley National Laboratory, with the goal of incorporating the ITAC catalytic air cleaning technology in their future commercial products.

  8. Laboratory Evaluation of Air Flow Measurement Methods for Residential HVAC Returns

    SciTech Connect (OSTI)

    Walker, Iain; Stratton, Chris

    2015-07-01

    This project improved the accuracy of air flow measurements used in commissioning California heating and air conditioning systems in Title 24 (Building and Appliance Efficiency Standards), thereby improving system performance and efficiency of California residences. The research team at Lawrence Berkeley National Laboratory addressed the issue that typical tools used by contractors in the field to test air flows may not be accurate enough to measure return flows used in Title 24 applications. The team developed guidance on performance of current diagnostics as well as a draft test method for use in future evaluations. The series of tests performed measured air flow using a range of techniques and devices. The measured air flows were compared to reference air flow measurements using inline air flow meters built into the test apparatus. The experimental results showed that some devices had reasonable results (typical errors of 5 percent or less) but others had much bigger errors (up to 25 percent).

  9. Biological testing of sediment for the Olympia Harbor Navigation Improvement Project, 1988: Geoduck, amphipod, and echinoderm bioassays

    SciTech Connect (OSTI)

    Ward, J.A.; Word, J.Q.; Antrim, L.D.

    1989-05-01

    The Olympia Harbor Navigation Improvement Project requires the dredging of approximately 330,000 cubic yards (cy) of sediment from the harbor entrance channel and 205,185 cy from the turning basin. Puget Sound Dredged Disposal Analysis (PSDDA) partial characterization studies were used to plan a full sediment characterization in which chemical analyses and biological testing of sediments evaluated the suitability of the dredged material for unconfined, open-water disposal. The US Army Corps of Engineers (COE), Seattle District, contracted with NOAA/NMFS, Environmental Conservation Division, to perform the chemical analysis and Microtox bioassay tests, and with the Battelle/Marine Sciences Laboratory (MSL) in Sequim to perform flow-through solid-phase bioassays utilizing juvenile (8 to 10 mm) geoduck clams, Panopea generosa, and static solid phase bioassays using the phoxocephalid amphipod, Rhepoxynius abronius, developing embryos and gametes of the purple sea urchin, Strongylocentrotus purpuratus, and the larvae of the Pacific oyster Crassostrea gigas. When the results of the biological tests were evaluated under PSDDA guidelines, it was found that all the tested sediment treatments from Olympia Harbor are suitable for unconfined open-water disposal. 14 refs., 12 figs., 3 tabs.

  10. High Performance Cathodes for Li-Air Batteries

    SciTech Connect (OSTI)

    Xing, Yangchuan

    2013-08-22

    The overall objective of this project was to develop and fabricate a multifunctional cathode with high activities in acidic electrolytes for the oxygen reduction and evolution reactions for Li-air batteries. It should enable the development of Li-air batteries that operate on hybrid electrolytes, with acidic catholytes in particular. The use of hybrid electrolytes eliminates the problems of lithium reaction with water and of lithium oxide deposition in the cathode with sole organic electrolytes. The use of acid electrolytes can eliminate carbonate formation inside the cathode, making air breathing Li-air batteries viable. The tasks of the project were focused on developing hierarchical cathode structures and bifunctional catalysts. Development and testing of a prototype hybrid Li-air battery were also conducted. We succeeded in developing a hierarchical cathode structure and an effective bifunctional catalyst. We accomplished integrating the cathode with existing anode technologies and made a pouch prototype Li-air battery using sulfuric acid as catholyte. The battery cathodes contain a nanoscale multilayer structure made with carbon nanotubes and nanofibers. The structure was demonstrated to improve battery performance substantially. The bifunctional catalyst developed contains a conductive oxide support with ultra-low loading of platinum and iridium oxides. The work performed in this project has been documented in seven peer reviewed journal publications, five conference presentations, and filing of two U.S. patents. Technical details have been documented in the quarterly reports to DOE during the course of the project.

  11. Contracts for field projects and supporting research on enhanced oil recovery and improved drilling technology. Progress review No. 34, quarter ending March 31, 1983

    SciTech Connect (OSTI)

    Linville, B.

    1983-07-01

    Progress achieved for the quarter ending March 1983 are presented for field projects and supporting research for the following: chemical flooding; carbon dioxide injection; and thermal/heavy oil. In addition, progress reports are presented for: resource assessment technology; extraction technology; environmental and safety; microbial enhanced oil recovery; oil recovered by gravity mining; improved drilling technology; and general supporting research. (ATT)

  12. NREL Improves System Efficiency and Increases Energy Transfer with Wind2H2 Project, Enabling Reduced Cost Electrolysis Production (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2010-11-01

    This fact sheet describes NREL's accomplishments in improving energy transfer within a wind turbine-based hydrogen production system. Work was performed by the Wind2H2 Project team at the National Wind Technology Center in partnership with Xcel Energy.

  13. Air Risk Information Support Center

    SciTech Connect (OSTI)

    Shoaf, C.R.; Guth, D.J.

    1990-12-31

    The Air Risk Information Support Center (Air RISC) was initiated in early 1988 by the US Environmental Protection Agency`s (EPA) Office of Health and Environmental Assessment (OHEA) and the Office of Air Quality Planning and Standards (OAQPS) as a technology transfer effort that would focus on providing information to state and local environmental agencies and to EPA Regional Offices in the areas of health, risk, and exposure assessment for toxic air pollutants. Technical information is fostered and disseminated by Air RISCs three primary activities: (1) a {open_quotes}hotline{close_quotes}, (2) quick turn-around technical assistance projects, and (3) general technical guidance projects. 1 ref., 2 figs.

  14. Membrane Based Air Conditioning

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Membrane Based Air Conditioning 2016 Building Technologies Office Peer Review Brian Johnson, brian.johnson@daisanalytic.com Dais Analytic Corporation INSERT PROJECT SPECIFIC PHOTO (replacing this shape) 2 Project Summary Timeline: Start date: October 1, 2015 NEW PROJECT Planned end date: September 30, 2017 Key Milestones 1. System Design Review; March 2016 2. Compressor testing review; September 2016 3. Go/No-Go based on bench testing; September 2016 4. Experimental evaluation of V1 prototype;

  15. Evaluation Project 4492

    National Nuclear Security Administration (NNSA)

    project, to be managed through the U.S. Air Force (USAF) Operationally Responsive Space (ORS) Office. Sandia Site Office Missile System LEONIDAS Component Development ...

  16. Fuel Economy Improvements from a Hybrid-Electric/Diesel Powertrain in a Class 4 Parcel Delivery Vehicle

    Energy.gov [DOE]

    The goal of this project is to provide data to help bridge the gap between R&D and the commercial availability of advanced vehicle technologies that reduce petroleum use in the U.S. and improve air quality.

  17. Air Products & Chemicals, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Air Products & Chemicals, Inc. Air Products & Chemicals, Inc. Image courtesy of Air Products and Chemicals, Inc Image courtesy of Air Products and Chemicals, Inc APCI PORT ARTHUR ICCS PROJECT In October 2009, DOE selected the Air Products and Chemicals, Inc. (APCI) team to conduct one of 12 projects in Phase 1 of its Industrial Carbon Capture and Storage (ICCS) program. DOE again selected the project in June 2010 as one of three projects to receive continued (Phase 2) funding. In total,

  18. New process modeling [sic], design, and control strategies for energy efficiency, high product quality, and improved productivity in the process industries. Final project report

    SciTech Connect (OSTI)

    Ray, W. Harmon

    2002-06-05

    This project was concerned with the development of process design and control strategies for improving energy efficiency, product quality, and productivity in the process industries. In particular, (i) the resilient design and control of chemical reactors, and (ii) the operation of complex processing systems, was investigated. Specific topics studied included new process modeling procedures, nonlinear controller designs, and control strategies for multiunit integrated processes. Both fundamental and immediately applicable results were obtained. The new design and operation results from this project were incorporated into computer-aided design software and disseminated to industry. The principles and design procedures have found their way into industrial practice.

  19. Air Quality

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Air Quality Air Quality Tour The Laboratory calculates the dose to the maximally exposed individual (MEI) to determine effects of Laboratory operations on the public.

  20. Air Quality

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Air Quality Air Quality Tour The Laboratory calculates the dose to the maximally exposed individual (MEI) to determine effects of Laboratory operations on the public.

  1. Air Quality

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Air Quality Air Quality Tour The Laboratory calculates the dose to the maximally exposed individual (MEI) to determine effects of Laboratory operations on the public. Open full...

  2. Air Barriers for Residential and Commercial Buildings | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Air Barriers for Residential and Commercial Buildings Air Barriers for Residential and Commercial Buildings Emerging Technologies Project for the 2013 Building Technologies ...

  3. Mid-section of a can-annular gas turbine engine with an improved rotation of air flow from the compressor to the turbine

    DOE Patents [OSTI]

    Little, David A.; Schilp, Reinhard; Ross, Christopher W.

    2016-03-22

    A midframe portion (313) of a gas turbine engine (310) is presented and includes a compressor section with a last stage blade to orient an air flow (311) at a first angle (372). The midframe portion (313) further includes a turbine section with a first stage blade to receive the air flow (311) oriented at a second angle (374). The midframe portion (313) further includes a manifold (314) to directly couple the air flow (311) from the compressor section to a combustor head (318) upstream of the turbine section. The combustor head (318) introduces an offset angle in the air flow (311) from the first angle (372) to the second angle (374) to discharge the air flow (311) from the combustor head (318) at the second angle (374). While introducing the offset angle, the combustor head (318) at least maintains or augments the first angle (372).

  4. Guide to Air Sealing

    SciTech Connect (OSTI)

    2011-02-01

    Air sealing is one of the most cost-effective ways to improve the comfort and energy efficiency of your home. Hire a certified professional contractor for best results.

  5. Improved Hydrogen Utilization and Carbon Recovery for Higher Efficiency Thermochemical Bio-oil Pathways Presentation for BETO 2015 Project Peer Review

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    International RTI International RTI International is a trade name of Research Triangle Institute. www.rti.org 2015 DOE Bioenergy Technologies Office (BETO) Project Peer Review WBS 2.4.1.403 - Improved Hydrogen Utilization and Carbon Recovery for Higher Efficiency Thermochemical Bio-oil Pathways March 25, 2015 Bio-Oil Technology Area Review David C. Dayton, PI RTI International This presentation does not contain any proprietary, confidential, or otherwise restricted information RTI International

  6. Air Sealing

    SciTech Connect (OSTI)

    2000-02-01

    This fact sheet describes ventilation and the importance of sealing air leaks and providing controlled ventilation.

  7. Ventilation System Effectiveness and Tested Indoor Air Quality Impacts

    SciTech Connect (OSTI)

    Rudd, Armin; Bergey, Daniel

    2014-02-01

    In this project, Building America research team Building Science Corporation tested the effectiveness of ventilation systems at two unoccupied, single-family, detached lab homes at the University of Texas - Tyler. Five ventilation system tests were conducted with various whole-building ventilation systems. Multizone fan pressurization testing characterized building and zone enclosure leakage. PFT testing showed multizone air change rates and interzonal airflow. Cumulative particle counts for six particle sizes, and formaldehyde and other Top 20 VOC concentrations were measured in multiple zones. The testing showed that single-point exhaust ventilation was inferior as a whole-house ventilation strategy. This was because the source of outside air was not direct from outside, the ventilation air was not distributed, and no provision existed for air filtration. Indoor air recirculation by a central air distribution system can help improve the exhaust ventilation system by way of air mixing and filtration. In contrast, the supply and balanced ventilation systems showed that there is a significant benefit to drawing outside air from a known outside location, and filtering and distributing that air. Compared to the exhaust systems, the CFIS and ERV systems showed better ventilation air distribution and lower concentrations of particulates, formaldehyde and other VOCs. System improvement percentages were estimated based on four system factor categories: balance, distribution, outside air source, and recirculation filtration. Recommended system factors could be applied to reduce ventilation fan airflow rates relative to ASHRAE Standard 62.2 to save energy and reduce moisture control risk in humid climates. HVAC energy savings were predicted to be 8-10%, or $50-$75/year.

  8. U.S. NO₂ trends (2005–2013): EPA air quality system (AQS) data versus improved observations from the Ozone Monitoring Instrument (OMI)

    DOE PAGES-Beta [OSTI]

    Lamsal, Lok N.; Duncan, Bryan N.; Yoshida, Yasuko; Krotkov, Nickolay A.; Pickering, Kenneth E.; Streets, David G.; Lu, Zifeng

    2015-06-01

    Emissions of nitrogen oxides (NOx) and, subsequently, atmospheric levels of nitrogen dioxide (NO₂) have decreased over the U.S. due to a combination of environmental policies and technological change. Consequently, NO₂ levels have decreased by 30–40% in the last decade. We quantify NO₂ trends (2005–2013) over the U.S. using surface measurements from the U.S. Environmental Protection Agency (EPA) Air Quality System (AQS) and an improved tropospheric NO₂ vertical column density (VCD) data product from the Ozone Monitoring Instrument (OMI) on the Aura satellite.We demonstrate that the current OMI NO₂ algorithm is of sufficient maturity to allow a favorable correspondence of trendsmore » and variations in OMI and AQS data. Our trend model accounts for the non-linear dependence of NO₂ concentration on emissions associated with the seasonal variation of the chemical lifetime, including the change in the amplitude of the seasonal cycle associated with the significant change in NOx emissions that occurred over the last decade. The direct relationship between observations and emissions becomes more robust when one accounts for these non-linear dependencies. We improve the OMI NO₂ standard retrieval algorithm and, subsequently, the data product by using monthly vertical concentration profiles, a required algorithm input, from a high-resolution chemistry and transport model (CTM) simulation with varying emissions (2005-2013). The impact of neglecting the time-dependence of the profiles leads to errors in trend estimation, particularly in regions where emissions have changed substantially. For example, trends calculated from retrievals based on time-dependent profiles offer 18% more instances of significant trends and up to 15% larger total NO₂ reduction versus the results based on profiles for 2005. Using a CTM, we explore the theoretical relation of the trends estimated from NO₂ VCDs to those estimated from ground-level concentrations. The model

  9. U.S. NO₂ trends (2005–2013): EPA air quality system (AQS) data versus improved observations from the Ozone Monitoring Instrument (OMI)

    SciTech Connect (OSTI)

    Lamsal, Lok N.; Duncan, Bryan N.; Yoshida, Yasuko; Krotkov, Nickolay A.; Pickering, Kenneth E.; Streets, David G.; Lu, Zifeng

    2015-06-01

    Emissions of nitrogen oxides (NOx) and, subsequently, atmospheric levels of nitrogen dioxide (NO₂) have decreased over the U.S. due to a combination of environmental policies and technological change. Consequently, NO₂ levels have decreased by 30–40% in the last decade. We quantify NO₂ trends (2005–2013) over the U.S. using surface measurements from the U.S. Environmental Protection Agency (EPA) Air Quality System (AQS) and an improved tropospheric NO₂ vertical column density (VCD) data product from the Ozone Monitoring Instrument (OMI) on the Aura satellite.We demonstrate that the current OMI NO₂ algorithm is of sufficient maturity to allow a favorable correspondence of trends and variations in OMI and AQS data. Our trend model accounts for the non-linear dependence of NO₂ concentration on emissions associated with the seasonal variation of the chemical lifetime, including the change in the amplitude of the seasonal cycle associated with the significant change in NOx emissions that occurred over the last decade. The direct relationship between observations and emissions becomes more robust when one accounts for these non-linear dependencies. We improve the OMI NO₂ standard retrieval algorithm and, subsequently, the data product by using monthly vertical concentration profiles, a required algorithm input, from a high-resolution chemistry and transport model (CTM) simulation with varying emissions (2005-2013). The impact of neglecting the time-dependence of the profiles leads to errors in trend estimation, particularly in regions where emissions have changed substantially. For example, trends calculated from retrievals based on time-dependent profiles offer 18% more instances of significant trends and up to 15% larger total NO₂ reduction versus the results based on profiles for 2005. Using a CTM, we explore the theoretical relation of the trends estimated from NO₂ VCDs to those estimated from ground-level concentrations

  10. Building America Case Study: Air Leakage and Air Transfer Between...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    This project builds on previous work by Rudd and Bergey (2013) to further examine and evaluate the problem of unwanted air transfer from garage to living space and the ...

  11. Contract/Project Management

    Energy.gov (indexed) [DOE]

    and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- & ...

  12. Transmission Commercial Project Integration

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Projects Expand Projects Skip navigation links Ancillary and Control Area Services (ACS) Practices Forum Attachment K Commercial Business Process Improvement (CBPI) Customer...

  13. Contract/Project Management

    Energy.gov (indexed) [DOE]

    Second Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Forecast ...

  14. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 ...

  15. Contract/Project Management

    Energy.gov (indexed) [DOE]

    3 First Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2013 Target FY 2013 Final FY ...

  16. Contract/Project Management

    Energy.gov (indexed) [DOE]

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Forecast ...

  17. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Final FY ...

  18. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 ...

  19. EA-1752: Pacific Gas & Electric Company (PG&E), Compressed Air Energy Storage (CAES) Compression Testing Phase Project, San Joaquin County, California

    Energy.gov [DOE]

    DOE is preparing this EA to evaluate the potential environmental impacts of providing a financial assistance grant under the American Recovery and Reinvestment Act of 2009 for the construction of an advanced compressed air energy storage plant in San Francisco, California.

  20. RM12-2703 Advanced Rooftop Unit Control Retrofit Kit Field Demonstration: Hawaii and Guam Energy Improvement Technology Demonstration Project

    SciTech Connect (OSTI)

    Doebber, I.; Dean, J.; Dominick, J.; Holland, G.

    2014-03-01

    As part of its overall strategy to meet its energy goals, the Naval Facilities Engineering Command (NAVFAC) partnered with U.S. Department of Energy's (DOE) National Renewable Energy Laboratory (NREL) to rapidly demonstrate and deploy cost-effective renewable energy and energy efficiency technologies. This was one of several demonstrations of new and underutilized commercial energy efficiency technologies. The consistent year-round demand for air conditioning and dehumidification in Hawaii provides an advantageous demonstration location for advanced rooftop control (ARC) retrofit kits to packaged rooftop units (RTUs). This report summarizes the field demonstration of ARCs installed on nine RTUs serving a 70,000-ft2 exchange store (large retail) and two RTUs, each serving small office buildings located on Joint Base Pearl Harbor-Hickam (JBPHH).

  1. Sabdia's Radial Flow Air Bearing Heat Exchanger

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    The Sandia Cooler) vapor chamber hydrodynamic air bearing heat-sink-impeller Dr. Jeff Koplow, jkoplow@sandia.gov Sandia National Laboratories Project Summary Timeline: Start date: ...

  2. California Hydrogen Infrastructure Project

    SciTech Connect (OSTI)

    Heydorn, Edward C

    2013-03-12

    Air Products and Chemicals, Inc. has completed a comprehensive, multiyear project to demonstrate a hydrogen infrastructure in California. The specific primary objective of the project was to demonstrate a model of a real-world retail hydrogen infrastructure and acquire sufficient data within the project to assess the feasibility of achieving the nation's hydrogen infrastructure goals. The project helped to advance hydrogen station technology, including the vehicle-to-station fueling interface, through consumer experiences and feedback. By encompassing a variety of fuel cell vehicles, customer profiles and fueling experiences, this project was able to obtain a complete portrait of real market needs. The project also opened its stations to other qualified vehicle providers at the appropriate time to promote widespread use and gain even broader public understanding of a hydrogen infrastructure. The project engaged major energy companies to provide a fueling experience similar to traditional gasoline station sites to foster public acceptance of hydrogen. Work over the course of the project was focused in multiple areas. With respect to the equipment needed, technical design specifications (including both safety and operational considerations) were written, reviewed, and finalized. After finalizing individual equipment designs, complete station designs were started including process flow diagrams and systems safety reviews. Material quotes were obtained, and in some cases, depending on the project status and the lead time, equipment was placed on order and fabrication began. Consideration was given for expected vehicle usage and station capacity, standard features needed, and the ability to upgrade the station at a later date. In parallel with work on the equipment, discussions were started with various vehicle manufacturers to identify vehicle demand (short- and long-term needs). Discussions included identifying potential areas most suited for hydrogen fueling stations

  3. Laboratory Evaluation of Air Flow Measurement Methods for Residential HVAC Returns for New Instrument Standards

    SciTech Connect (OSTI)

    Walker, Iain; Stratton, Chris

    2015-08-01

    This project improved the accuracy of air flow measurements used in commissioning California heating and air conditioning systems in Title 24 (Building and Appliance Efficiency Standards), thereby improving system performance and efficiency of California residences. The research team at Lawrence Berkeley National Laboratory addressed the issue that typical tools used by contractors in the field to test air flows may not be accurate enough to measure return flows used in Title 24 applications. The team developed guidance on performance of current diagnostics as well as a draft test method for use in future evaluations. The study team prepared a draft test method through ASTM International to determine the uncertainty of air flow measurements at residential heating ventilation and air conditioning returns and other terminals. This test method, when finalized, can be used by the Energy Commission and other entities to specify required accuracy of measurement devices used to show compliance with standards.

  4. Air filter

    SciTech Connect (OSTI)

    Jackson, R.E.; Sparks, J.E.

    1981-03-03

    An air filter is described that has a counter rotating drum, i.e., the rotation of the drum is opposite the tangential intake of air. The intake air has about 1 lb of rock wool fibers per 107 cu. ft. of air sometimes at about 100% relative humidity. The fibers are doffed from the drum by suction nozzle which are adjacent to the drum at the bottom of the filter housing. The drum screen is cleaned by periodically jetting hot dry air at 120 psig through the screen into the suction nozzles.

  5. Providing the Basis for Innovative Improvements in Advanced LWR Reactor Passive Safety Systems Design: An Educational R&D Project

    SciTech Connect (OSTI)

    Brian G. Williams; Jim C. P. Liou; Hiral Kadakia; Bill Phoenix; Richard R. Schultz

    2007-02-27

    This project characterizes typical two-phase stratified flow conditions in advanced water reactor horizontal pipe sections, following activation of passive cooling systems. It provides (1) a means to educate nuclear engineering students regarding the importance of two-phase stratified flow in passive cooling systems to the safety of advanced reactor systems and (2) describes the experimental apparatus and process to measure key parameters essential to consider when designing passive emergency core cooling flow paths that may encounter this flow regime. Based on data collected, the state of analysis capabilities can be determined regarding stratified flow in advanced reactor systems and the best paths forward can be identified to ensure that the nuclear industry can properly characterize two-phase stratified flow in passive emergency core cooling systems.

  6. Clean Air Act | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Services » Environment » Environmental Policy and Assistance » Clean Air Act Clean Air Act The primary law governing the Department of Energy (DOE) air pollution control activities is the Clean Air Act (CAA). This law defines the role of the U.S. Environmental Protection Agency (EPA) and state, local and tribal air programs in protecting and improving the nation's air quality and stratospheric ozone layer by regulating emissions from mobile and stationary sources. The CAA contains titles

  7. Maui Smart Grid Demonstration Project Managing Distribution System Resources for Improved Service Quality and Reliability, Transmission Congestion Relief, and Grid Support Functions

    SciTech Connect (OSTI)

    none,

    2014-09-30

    The Maui Smart Grid Project (MSGP) is under the leadership of the Hawaii Natural Energy Institute (HNEI) of the University of Hawaii at Manoa. The project team includes Maui Electric Company, Ltd. (MECO), Hawaiian Electric Company, Inc. (HECO), Sentech (a division of SRA International, Inc.), Silver Spring Networks (SSN), Alstom Grid, Maui Economic Development Board (MEDB), University of Hawaii-Maui College (UHMC), and the County of Maui. MSGP was supported by the U.S. Department of Energy (DOE) under Cooperative Agreement Number DE-FC26-08NT02871, with approximately 50% co-funding supplied by MECO. The project was designed to develop and demonstrate an integrated monitoring, communications, database, applications, and decision support solution that aggregates renewable energy (RE), other distributed generation (DG), energy storage, and demand response technologies in a distribution system to achieve both distribution and transmission-level benefits. The application of these new technologies and procedures will increase MECO’s visibility into system conditions, with the expected benefits of enabling more renewable energy resources to be integrated into the grid, improving service quality, increasing overall reliability of the power system, and ultimately reducing costs to both MECO and its customers.

  8. Techni-Cast: Foundry Saves Energy with Compressed Air System Retrofit

    SciTech Connect (OSTI)

    none,

    2004-03-01

    In 2002, Techni-Cast improved its compressed air system at its foundry in Southgate, California. The project allowed the foundry to reduce its compressor capacity by 50%, which greatly reduced the foundry's energy and maintenance costs. The annual energy and maintenance savings from the project implementation are 242,000 kWh and $24,200, and the project's cost was $38,000. Because the plant received a $10,000 incentive payment from the California Public Utilities Commission, the total project cost was reduced to $28,000, yielding a 14-month simple payback.

  9. Techni-Cast: Foundry Saves Energy with Compressed Air System Retrofit

    SciTech Connect (OSTI)

    Not Available

    2001-03-01

    In 2002, Techni-Cast improved its compressed air system at its foundry in Southgate, California. The project allowed the foundry to reduce its compressor capacity by 50%, which greatly reduced the foundry's energy and maintenance costs. The annual energy and maintenance savings from the project implementation are 242,000 kWh and $24,200, and the projects cost was $38,000. Because the plant received a $10,000 incentive payment from the California Public Utilities Commission, the total project cost was reduced to $28,000, yielding a 14-month simple payback.

  10. CSP Tower Air Brayton Combustor

    Energy.gov [DOE]

    This fact sheet describes a concentrating solar power tower air Brayton combustor project awarded under the DOE's 2012 SunShot CSP R&D award program. The team, led by the Southwest Research Institute, is working to develop an external combustor that allows for the mixing of CSP-heated air with natural gas in hybridized power plants. This project aims to increase the temperature capabilities of the CSP tower air receiver and gas turbine to 1,000ºC and achieve energy conversion efficiencies greater than 50%.

  11. Miniaturized Air to Refrigerant Heat Exchangers

    Energy.gov [DOE]

    This project is developing a miniaturized air-to-refrigerant heat exchanger that is more compact and more energy efficient than current market designs. The heat exchanger will feature at least 20% less volume, material volume, and approach temperature compared to current multiport flat tube designs, and it will be in production within five years. The heat exchanger, which acts as both an evaporator and a condenser, can be applied to commercial and residential air-conditioning or heat pump systems with various capacity scales. Prototype 1-kilowatt (kW) and 10 kW designs will be tested and then improved as necessary for final tests and demonstration in a 3-ton heat pump.

  12. Air-to-air turbocharged air cooling versus air-to-water turbocharged air cooling

    SciTech Connect (OSTI)

    Moranne, J.-P.; Lukas, J.J.

    1984-01-01

    In Europe, turbocharged air in diesel engines used in on-road vehicles is cooled only by air. It is expected that by 1990, ten to twelve percent of European heavy trucks with diesel engines will cool turbocharged air by water. Air-to-air turbocharges air cooling is reviewed and the evolution of air-to-water turbocharged air cooling presented before the two systems are compared.

  13. Compressed Air System Control Strategies | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    System Control Strategies Compressed Air System Control Strategies This tip sheet briefly discusses compressed air system control strategies as a means to improving and maintaining system performance. COMPRESSED AIR TIP SHEET #7 Compressed Air System Control Strategies (August 2004) (242.65 KB) More Documents & Publications Compressed Air Storage Strategies Analyzing Your Compressed Air System Stabilizing System Pressure

  14. air force

    National Nuclear Security Administration (NNSA)

    en NNSA, Air Force Complete Successful B61-12 Life Extension Program Development Flight Test at Tonopah Test Range http:nnsa.energy.govmediaroompressreleases...

  15. The Wind Forecast Improvement Project (WFIP): A Public/Private Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations. The Southern Study Area, Final Report

    SciTech Connect (OSTI)

    Freedman, Jeffrey M.; Manobianco, John; Schroeder, John; Ancell, Brian; Brewster, Keith; Basu, Sukanta; Banunarayanan, Venkat; Hodge, Bri-Mathias; Flores, Isabel

    2014-04-30

    This Final Report presents a comprehensive description, findings, and conclusions for the Wind Forecast Improvement Project (WFIP) -- Southern Study Area (SSA) work led by AWS Truepower (AWST). This multi-year effort, sponsored by the Department of Energy (DOE) and National Oceanographic and Atmospheric Administration (NOAA), focused on improving short-term (15-minute - 6 hour) wind power production forecasts through the deployment of an enhanced observation network of surface and remote sensing instrumentation and the use of a state-of-the-art forecast modeling system. Key findings from the SSA modeling and forecast effort include: 1. The AWST WFIP modeling system produced an overall 10 - 20% improvement in wind power production forecasts over the existing Baseline system, especially during the first three forecast hours; 2. Improvements in ramp forecast skill, particularly for larger up and down ramps; 3. The AWST WFIP data denial experiments showed mixed results in the forecasts incorporating the experimental network instrumentation; however, ramp forecasts showed significant benefit from the additional observations, indicating that the enhanced observations were key to the model systems’ ability to capture phenomena responsible for producing large short-term excursions in power production; 4. The OU CAPS ARPS simulations showed that the additional WFIP instrument data had a small impact on their 3-km forecasts that lasted for the first 5-6 hours, and increasing the vertical model resolution in the boundary layer had a greater impact, also in the first 5 hours; and 5. The TTU simulations were inconclusive as to which assimilation scheme (3DVAR versus EnKF) provided better forecasts, and the additional observations resulted in some improvement to the forecasts in the first 1 - 3 hours.

  16. MHK Technologies/AirWEC | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    the MHK database homepage AirWEC.jpg Technology Profile Primary Organization Resolute Marine Energy Inc Project(s) where this technology is utilized *MHK ProjectsOcean Trials Ver...

  17. Technology Maturation Plan (TMP) Wet Air Oxidation (WAO) Technology for

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Tank 48H Treatment Project (TTP) | Department of Energy Wet Air Oxidation (WAO) Technology for Tank 48H Treatment Project (TTP) Technology Maturation Plan (TMP) Wet Air Oxidation (WAO) Technology for Tank 48H Treatment Project (TTP) This assessment determines the technology maturity level of the candidate Tank 48H treatment technologies that are being considered for implementation at DOE's SRS - specifically Wet Air Oxidation. Technology Maturation Plan (TMP) Wet Air Oxidation (WAO)

  18. Renewables and air quality

    SciTech Connect (OSTI)

    Wooley, D.R.

    2000-08-01

    The US heavy reliance on fossil fuels is a central obstacle to improving air quality and preventing catastrophic climate change. To solve this problem will require a combination of financial incentives and market rules that strongly encourage development of renewable energy resources to meet electric power demand. One promising policy option is to allow renewable energy resources to directly participate in air pollution emission trading mechanisms. Currently, the clean air benefits of renewable energy generally go unrecognized by regulators, under-appreciated by consumers and uncompensated by markets. Renewable energy is a key clean air alternative to conventional electricity generation, and the development of renewables could be stimulated by changes to the Clean Air Act's emissions trading programs. As Congress revisits clean air issues over the next several years, renewable energy representatives could push for statutory changes that reward the renewable energy industry for the air quality benefits it provides. By also becoming involved in key US Environmental Protection Agency (EPA) and state rule-making cases, the renewables industry could influence the structure of emissions trading programs and strengthen one of the most persuasive arguments for wind, solar and biomass energy development.

  19. HVAC Cabinet Air Leakage Test Method - Building America Top Innovation...

    Energy Savers

    HVAC Cabinet Air Leakage Test Method - Building America Top Innovation HVAC Cabinet Air Leakage Test Method - Building America Top Innovation While HVAC installers have improved ...

  20. ARM - Science Project Ideas

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    TeachersScience Project Ideas Outreach Home Room News Publications Traditional Knowledge Kiosks Barrow, Alaska Tropical Western Pacific Site Tours Contacts Students Study Hall About ARM Global Warming FAQ Just for Fun Meet our Friends Cool Sites Teachers Teachers' Toolbox Lesson Plans Science Project Ideas Do changes in air pressure affect the weather? What is the relationship between air pressure and temperature? Monitor the weather forecast data from the web to find the answer. How does the

  1. Assessing UST corrective action technologies: Lessons learned about in situ air sparging at the Denison Avenue Site, Cleveland, Ohio. Project report

    SciTech Connect (OSTI)

    Clark, T.R.; Chaudet, R.E.; Johnson, R.L.

    1994-12-01

    In situ air sparging (IAS) has been used at an increasing number of sites to address groundwater contamination. Because of the lack of substantive performance data, however, the actual effectiveness of the system is not known. The EPA Office of Research and Development Risk reduction Engineering Laboratory (ORD RREL) with the EPA Region 5 Office of Underground Storage Tanks, the Ohio State Fire Marshal, and BP Exploration & Oil, Inc. (BP) participated in a field evaluation of an IAS system at a petroleum leaking UST site in Cleveland, Ohio. The purpose of the study was to provide performance data that will be independently evaluated by EPA to better understand IAS effectiveness. The report presents the site and monitoring data provided by BP over a 2-year period. The chemical data indicated an overall decrease of BTEX concentrations in groundwater to nondetectable levels shortly after startup of the IAS system. Variability in the chemical and process data also precludes making any definitive link between the decrease in contaminant concentrations and IAS performance at this site.

  2. Hybrid and Advanced Air Cooling | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    and Advanced Air Cooling Hybrid and Advanced Air Cooling DOE Geothermal Program Peer Review 2010 - Presentation. This project will identify and analyze advanced air cooling strategies thatallow air-cooled geothermal power plants to maintain a high electric power output during periods of high air dry bulb temperatures while minimizing water consumption. specialized_bharathan_advanced_cooling.pdf (507.83 KB) More Documents & Publications Hybird Geothemal-Solar Air-Cooled Condensers for Next

  3. Interstate Grid Electrification Improvement Project

    Energy.gov [DOE]

    2011 DOE Hydrogen and Fuel Cells Program, and Vehicle Technologies Program Annual Merit Review and Peer Evaluation

  4. Interstate Grid Electrification Improvement Project

    Energy.gov [DOE]

    2013 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting

  5. Using Ecosystem Experiments to Improve Vegetation Models

    SciTech Connect (OSTI)

    Medlyn, Belinda; Zaehle, S; DeKauwe, Martin G.; Walker, Anthony P.; Dietze, Michael; Hanson, Paul J.; Hickler, Thomas; Jain, Atul; Luo, Yiqi; Parton, William; Prentice, I. Collin; Thornton, Peter E.; Wang, Shusen; Wang, Yingping; Weng, Ensheng; Iversen, Colleen M.; McCarthy, Heather R.; Warren, Jeffrey; Oren, Ram; Norby, Richard J

    2015-05-21

    Ecosystem responses to rising CO2 concentrations are a major source of uncertainty in climate change projections. Data from ecosystem-scale Free-Air CO2 Enrichment (FACE) experiments provide a unique opportunity to reduce this uncertainty. The recent FACE Model–Data Synthesis project aimed to use the information gathered in two forest FACE experiments to assess and improve land ecosystem models. A new 'assumption-centred' model intercomparison approach was used, in which participating models were evaluated against experimental data based on the ways in which they represent key ecological processes. Identifying and evaluating the main assumptions caused differences among models, and the assumption-centered approach produced a clear roadmap for reducing model uncertainty. We explain this approach and summarize the resulting research agenda. We encourage the application of this approach in other model intercomparison projects to fundamentally improve predictive understanding of the Earth system.

  6. Using Ecosystem Experiments to Improve Vegetation Models

    SciTech Connect (OSTI)

    Medlyn, Belinda; Zaehle, S; DeKauwe, Martin G.; Walker, Anthony P.; Dietze, Michael; Hanson, Paul J.; Hickler, Thomas; Jain, Atul; Luo, Yiqi; Parton, William; Prentice, I. Collin; Thornton, Peter E.; Wang, Shusen; Wang, Yingping; Weng, Ensheng; Iversen, Colleen M.; McCarthy, Heather R.; Warren, Jeffrey; Oren, Ram; Norby, Richard J

    2015-05-21

    Ecosystem responses to rising CO2 concentrations are a major source of uncertainty in climate change projections. Data from ecosystem-scale Free-Air CO2 Enrichment (FACE) experiments provide a unique opportunity to reduce this uncertainty. The recent FACE ModelData Synthesis project aimed to use the information gathered in two forest FACE experiments to assess and improve land ecosystem models. A new 'assumption-centred' model intercomparison approach was used, in which participating models were evaluated against experimental data based on the ways in which they represent key ecological processes. Identifying and evaluating the main assumptions caused differences among models, and the assumption-centered approach produced a clear roadmap for reducing model uncertainty. We explain this approach and summarize the resulting research agenda. We encourage the application of this approach in other model intercomparison projects to fundamentally improve predictive understanding of the Earth system.

  7. Using Ecosystem Experiments to Improve Vegetation Models

    DOE PAGES-Beta [OSTI]

    Medlyn, Belinda; Zaehle, S; DeKauwe, Martin G.; Walker, Anthony P.; Dietze, Michael; Hanson, Paul J.; Hickler, Thomas; Jain, Atul; Luo, Yiqi; Parton, William; et al

    2015-05-21

    Ecosystem responses to rising CO2 concentrations are a major source of uncertainty in climate change projections. Data from ecosystem-scale Free-Air CO2 Enrichment (FACE) experiments provide a unique opportunity to reduce this uncertainty. The recent FACE Model–Data Synthesis project aimed to use the information gathered in two forest FACE experiments to assess and improve land ecosystem models. A new 'assumption-centred' model intercomparison approach was used, in which participating models were evaluated against experimental data based on the ways in which they represent key ecological processes. Identifying and evaluating the main assumptions caused differences among models, and the assumption-centered approach produced amore » clear roadmap for reducing model uncertainty. We explain this approach and summarize the resulting research agenda. We encourage the application of this approach in other model intercomparison projects to fundamentally improve predictive understanding of the Earth system.« less

  8. Radioactive air emissions notice of construction for installation and operation of a waste retrieval system and tanks 241-AP-102 and 241-AP-104 project

    SciTech Connect (OSTI)

    DEXTER, M.L.

    1999-11-15

    This document serves as a notice of construction (NOC) pursuant to the requirements of Washington Administrative Code (WAC) 246 247-060, and as a request for approval to modify pursuant to 40 Code of Federal Regulations (CFR) 61 07 for the installation and operation of one waste retrieval system in the 24 1 AP-102 Tank and one waste retrieval system in the 241 AP 104 Tank Pursuant to 40 CFR 61 09 (a)( 1) this application is also intended to provide anticipated initial start up notification Its is requested that EPA approval of this application will also constitute EPA acceptance of the initial start up notification Project W 211 Initial Tank Retrieval Systems (ITRS) is scoped to install a waste retrieval system in the following double-shell tanks 241-AP 102-AP 104 AN 102, AN 103, AN-104, AN 105, AY 102 AZ 102 and SY-102 between now and the year 2011. Because of the extended installation schedules and unknowns about specific activities/designs at each tank, it was decided to submit NOCs as that information became available This NOC covers the installation and operation of a waste retrieval system in tanks 241 AP-102 and 241 AP 104 Generally this includes removal of existing equipment installation of new equipment and construction of new ancillary equipment and buildings Tanks 241 AP 102 and 241 AP 104 will provide waste feed for immobilization into a low activity waste (LAW) product (i.e. glass logs) The total effective dose equivalent (TEDE) to the offsite maximally exposed individual (MEI) from the construction activities is 0 045 millirem per year The unabated TEDE to the offsite ME1 from operation of the mixer pumps is 0 042 millirem per year.

  9. NNSA project receives DOE Secretary's Award for Project Management...

    National Nuclear Security Administration (NNSA)

    receives DOE Secretary's Award for Project Management Improvement Monday, April 13, 2015 - 3:28pm The NNSA Nuclear Materials Safeguards and Security Upgrade Project (NMSSUP) ...

  10. Vehicle Technologies Office 2013 Merit Review: A MultiAir / MultiFuel Approach to Enhancing Engine System Efficiency

    Energy.gov [DOE]

    A presentation given by Chrysler at the 2013 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting on its project to research a multi-air and multi-fuel approach to improving engine efficiency.

  11. Y-12 Steam Plant Project Received National Recognition for Project

    National Nuclear Security Administration (NNSA)

    Management Excellence | National Nuclear Security Administration | (NNSA) Steam Plant Project Received National Recognition for Project Management Excellence March 23, 2011 Y-12 steam plant project receives national recognition for project management excellence. Y-12's Steam Plant Life Extension Project (SPLE) has received the Secretary of Energy's Project Management Improvement Award. Microsoft Office document icon NR-03-28

  12. HVAC Cabinet Air Leakage Test Method - Building America Top Innovation |

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Department of Energy Cabinet Air Leakage Test Method - Building America Top Innovation HVAC Cabinet Air Leakage Test Method - Building America Top Innovation While HVAC installers have improved their air sealing practices to reduce the amount of air leaking at ducts and duct boots, testing showed that distribution systems still leaked at air handlers and furnace HVAC Air Leakage Fig 1 Air handler furnace cabinet with pressure taps.jpg cabinets. This has hampered the ability of HVAC

  13. DEMO Project Goals | National Nuclear Security Administration...

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    DEMO Project Goals The goals of this demonstration project are to Improve hiring by ... The demonstration project will modify the General Schedule (GS) classification and pay ...

  14. Project Management Policies & Principles Memo

    Energy.gov [DOE]

    Memo enhances and clarifies departmental policy related to project management as a result of the Improving Project Management Study and subsequent Secretarial Memo dated December 2014.

  15. Boardman to Hemingway Transmission Project

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Projects Expand Projects Skip navigation links Ancillary and Control Area Services (ACS) Practices Forum Attachment K Commercial Business Process Improvement (CBPI) Customer...

  16. Cold air systems: Sleeping giant

    SciTech Connect (OSTI)

    MacCracken, C.D. )

    1994-04-01

    This article describes how cold air systems help owners increase the profits from their buildings by reducing electric costs and improving indoor air quality through lower relative humidity levels. Cold air distribution involves energy savings, cost savings, space savings, greater comfort, cleaner air, thermal storage, tighter ducting, coil redesign, lower relative humidities, retrofitting, and improved indoor air quality (IAQ). It opens a door for architects, engineers, owners, builders, environmentalists, retrofitters, designers, occupants, and manufacturers. Three things have held up cold air's usage: multiple fan-powered boxes that ate up the energy savings of primary fans. Cold air room diffusers that provided inadequate comfort. Condensation from ducts, boxes, and diffusers. Such problems have been largely eliminated through research and development by utilities and manufacturers. New cold air diffusers no longer need fan powered boxes. It has also been found that condensation is not a concern so long as the ducts are located in air conditioned space, such as drop ceilings or central risers, where relative humidity falls quickly during morning startup.

  17. Rechargeable Lithium-Air Batteries: Development of Ultra High Specific Energy Rechargeable Lithium-Air Batteries Based on Protected Lithium Metal Electrodes

    SciTech Connect (OSTI)

    2010-07-01

    BEEST Project: PolyPlus is developing the worlds first commercially available rechargeable lithium-air (Li-Air) battery. Li-Air batteries are better than the Li-Ion batteries used in most EVs today because they breathe in air from the atmosphere for use as an active material in the battery, which greatly decreases its weight. Li-Air batteries also store nearly 700% as much energy as traditional Li-Ion batteries. A lighter battery would improve the range of EVs dramatically. Polyplus is on track to making a critical breakthrough: the first manufacturable protective membrane between its lithiumbased negative electrode and the reaction chamber where it reacts with oxygen from the air. This gives the battery the unique ability to recharge by moving lithium in and out of the batterys reaction chamber for storage until the battery needs to discharge once again. Until now, engineers had been unable to create the complex packaging and air-breathing components required to turn Li-Air batteries into rechargeable systems.

  18. MHK Projects/Ocean Trials Ver 2 | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    Project Technology *MHK TechnologiesSurgeWEC *MHK TechnologiesAirWEC Project Licensing Environmental Monitoring and Mitigation Efforts See Tethys << Return to the MHK database...

  19. History of Air Conditioning | Department of Energy

    Energy Savers

    Efficiency Standards Drive Improvements As air conditioning use soared in the 1970s, the energy crisis hit. In response, lawmakers passed laws to reduce energy consumption across...

  20. Top Low- or No-Cost Improvements | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Top Low- or No-Cost Improvements Top Low- or No-Cost Improvements This presentation describes the top low- or no-cost projects to improve energy efficiency as identified in energy assessments performed by DOE and by the Industrial Assessment Centers. Top Low- or No-Cost Improvements (April 2, 2009) (1.94 MB) More Documents & Publications Energy Assessments FUJIFILM Hunt Chemicals U.S.A. Achieves Compressed Air System Energy-Reduction Goals with a Three-Phased Strategy Save Energy Now in Your

  1. Energy Department Honors Savannah River Site Project Team with...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    contractor Parsons to improve project relationships, enhancing the project metrics, and ... of the changes were improved project performance and increased trust and confidence. ...

  2. Hybrid and Advanced Air Cooling

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    and Advanced Air Cooling Desikan Bharathan National Renewable Energy Laboratory 15013 Denver West Parkway Golden, CO 80401 ARRA funded Project Officer: Tim Reinhardt Total Project Funding: $1079K April 22-25, 2013 This presentation does not contain any proprietary confidential, or otherwise restricted information. Do not include any proprietary or confidential information. Your presentation is public and will be posted to the DOE Geothermal Technologies Office website. You must include the

  3. Air Leakage and Air Transfer Between Garage and Living Space

    SciTech Connect (OSTI)

    Rudd, A.

    2014-09-01

    This research project focused on evaluation of air transfer between the garage and living space in a single-family detached home constructed by a production homebuilder in compliance with the 2009 International Residential Code and the 2009 International Energy Conservation Code. The project gathered important information about the performance of whole-building ventilation systems and garage ventilation systems as they relate to minimizing flow of contaminated air from garage to living space. A series of 25 multi-point fan pressurization tests and additional zone pressure diagnostic testing characterized the garage and house air leakage, the garage-to-house air leakage, and garage and house pressure relationships to each other and to outdoors using automated fan pressurization and pressure monitoring techniques. While the relative characteristics of this house may not represent the entire population of new construction configurations and air tightness levels (house and garage) throughout the country, the technical approach was conservative and should reasonably extend the usefulness of the results to a large spectrum of house configurations from this set of parametric tests in this one house. Based on the results of this testing, the two-step garage-to-house air leakage test protocol described above is recommended where whole-house exhaust ventilation is employed. For houses employing whole-house supply ventilation (positive pressure) or balanced ventilation (same pressure effect as the Baseline condition), adherence to the EPA Indoor airPLUS house-to-garage air sealing requirements should be sufficient to expect little to no garage-to-house air transfer.

  4. Air Leakage and Air Transfer Between Garage and Living Space

    SciTech Connect (OSTI)

    Rudd, Armin

    2014-09-01

    This research project focused on evaluation of air transfer between the garage and living space in a single-family detached home constructed by a production homebuilder in compliance with the 2009 International Residential Code and the 2009 International Energy Conservation Code. The project gathered important information about the performance of whole-building ventilation systems and garage ventilation systems as they relate to minimizing flow of contaminated air from garage to living space. A series of 25 multi-point fan pressurization tests and additional zone pressure diagnostic testing characterized the garage and house air leakage, the garage-to-house air leakage, and garage and house pressure relationships to each other and to outdoors using automated fan pressurization and pressure monitoring techniques. While the relative characteristics of this house may not represent the entire population of new construction configurations and air tightness levels (house and garage) throughout the country, the technical approach was conservative and should reasonably extend the usefulness of the results to a large spectrum of house configurations from this set of parametric tests in this one house. Based on the results of this testing, the two-step garage-to-house air leakage test protocol described above is recommended where whole-house exhaust ventilation is employed.

  5. Air-To-Water Heat Pumps with Radiant Delivery in Low Load Homes...

    Energy Savers

    Air-to-Water Heat Pumps With Radiant Delivery in Low Load Homes Tucson, Arizona and Chico, California PROJECT INFORMATION Project Name: Field testing of air-to-water heat pump ...

  6. 13-Energy Efficiency Ratio Window Air Conditioner | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    -Energy Efficiency Ratio Window Air Conditioner 13-Energy Efficiency Ratio Window Air Conditioner Credit: Oak Ridge National Lab Credit: Oak Ridge National Lab Lead Performer: Oak Ridge National Laboratory - Oak Ridge, TN Partners: General Electric - Fairfield, CT DOE Funding: $1,540,000 Cost Share: Provided by CRADA partners Project Term: October 1, 2011 - September 30, 2015 Project Objective This project is designing and developing a high-efficiency 13 energy-efficiecy-ratio (EER) window air

  7. Increased oil production and reserves from improved completion techniques in the Bluebell Field, Uinta Basin, Utah. Quarterly technical progress report, April 1, 1996--June 30, 1996, 11th Quarter of the project

    SciTech Connect (OSTI)

    Allison, E.; Morgan, C.D.

    1996-07-30

    The objective of this project is to increase oil production and reserves in the Uinta Basin by demonstrating improved completion techniques. Low productivity of Uinta Basin wells is caused by gross production intervals of several thousand feet that contain perforated thief zones, water-bearing zones, and unperforated oil-bearing intervals. Geologic and engineering characterization and computer simulation of the Green River and Wasatch formations in the Bluebell field will determine reservoir heterogeneities related to fractures and depositional trends. This will be followed by drilling and recompletion of several wells to demonstrate improved completion techniques based on the reservoir characterization. Transfer of the project results will be an ongoing component of the project.

  8. History of Air Conditioning | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    History of Air Conditioning History of Air Conditioning July 20, 2015 - 3:15pm Addthis Paul Lester Paul Lester Digital Content Specialist, Office of Public Affairs MORE ON AIR CONDITIONING Check out our Energy Saver 101 infographic to learn how air conditioners work. Go to Energy Saver for more tips and advice on home cooling. Stay up-to-date on how the Energy Department is working to improve air conditioning technology. We take the air conditioner for granted, but imagine what life would be

  9. Final Report for the portion performed in the University of Illinois on the project entitled "Optimizing the Cloud-Aerosol-Radiation Ensemble Modeling System to Improve Future Climate Change Projections at Regional to Local Scales"

    SciTech Connect (OSTI)

    Liang, Xin-Zhong

    2011-01-31

    This is the final report for the closure of the research tasks on the project that have performed during the entire reporting period in the University of Illinois. It contains a summary of the achievements and details of key results as well as the future plan for this project to be continued in the University of Maryland.

  10. Upcoming Funding Opportunity for Wind Forecasting Improvement...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Wind Forecasting Improvement Project in Complex Terrain Upcoming Funding Opportunity for Wind Forecasting Improvement Project in Complex Terrain February 12, 2014 - 10:47am ...

  11. AltAir Fuels | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    Renewable Energy Product: Seattle-based developer of projects for the production of jet fuel from renewable and sustainable oils. References: AltAir Fuels1 This article is a...

  12. Clean Air Trade Inc | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    a company specialising in CER purchase as well as project development and investment in clean energy. References: Clean Air Trade Inc1 This article is a stub. You can help OpenEI...

  13. Advanced Variable Speed Air-Source Integrated Heat Pump 2013...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Pump 2013 Peer Review Advanced Variable Speed Air-Source Integrated Heat Pump 2013 Peer Review Emerging Technologies Project for the 2013 Building Technologies Office's Program ...

  14. Comprehensive Energy Program at Patrick Air Force Base Set to...

    Office of Environmental Management (EM)

    Download the Patrick Air Force Base case study. (709.94 KB) More Documents & Publications FPL Energy Services ESCO Qualification Sheet UESC Project Overview: NASA Ames Research ...

  15. Air-cooled Condensers in Next-generation Conversion Systems

    Office of Energy Efficiency and Renewable Energy (EERE)

    DOE Geothermal Program Peer Review 2010 - Presentation. Project objective: to reduce the costs associated with the generation of electrical power from air-cooled binary plants.

  16. EnEV AIR GmbH | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    Germany Zip: 78056 Product: Specialises in project planning of centrally designed ventilation systems with integral heat recovery. References: EnEV-AIR GmbH1 This article...

  17. Compressed Air Systems | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Technical Assistance » Compressed Air Systems Compressed Air Systems Applying best energy management practices and purchasing energy-efficient equipment can lead to significant savings in compressed air systems. Use the software tools, training, and publications listed below to improve performance and save energy. Compressed Air Tools Tools to Assess Your Energy System AIRMaster+ Tool AIRMaster+ LogTool Qualified Specialists Qualified Specialists have passed a rigorous competency examination on

  18. Lithium-Air Battery: High Performance Cathodes for Lithium-Air Batteries

    SciTech Connect (OSTI)

    2010-08-01

    BEEST Project: Researchers at Missouri S&T are developing an affordable lithium-air (Li-Air) battery that could enable an EV to travel up to 350 miles on a single charge. Todays EVs run on Li-Ion batteries, which are expensive and suffer from low energy density compared with gasoline. This new Li-Air battery could perform as well as gasoline and store 3 times more energy than current Li-Ion batteries. A Li-Air battery uses an air cathode to breathe oxygen into the battery from the surrounding air, like a human lung. The oxygen and lithium react in the battery to produce electricity. Current Li-Air batteries are limited by the rate at which they can draw oxygen from the air. The team is designing a battery using hierarchical electrode structures to enhance air breathing and effective catalysts to accelerate electricity production.

  19. Building America Technology Solutions for New and Existing Homes: Air

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Leakage and Air Transfer Between Garage and Living Space | Department of Energy Building America Technology Solutions for New and Existing Homes: Air Leakage and Air Transfer Between Garage and Living Space Building America Technology Solutions for New and Existing Homes: Air Leakage and Air Transfer Between Garage and Living Space In this project, Building Science Corporation worked with production home builder K. Hovnanian to conduct testing at a single-family home in Waldorf, Maryland,

  20. Heating, Ventilation, and Air Conditioning Projects | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    MI -- Optimized Thermal Systems - College Park, MD Purdue prototype system Residential Cold Climate Heat Pump with Variable-Speed Technology Lead Performer: Unico Systems - St....

  1. West Hackberry Tertiary Project. Quarterly technical progress report, January 1, 1996--March 31, 1996

    SciTech Connect (OSTI)

    Gillham, T.; Cerveny, B.; Turek, E.

    1996-04-10

    The goal of the West Hackberry Tertiary Project is to demonstrate the technical and economic feasibility of combining air injection with the Double Displacement Process for tertiary oil recovery. The Double Displacement Process is the gas displacement of a water invaded oil column for the purpose of recovering oil through gravity drainage. The novel aspect of this project is the use of air as the injection fluid. The target reservoir for the project is the Camerina C-1,2,3 sand located on the West Flank of West Hackberry Field in Cameron Parish, Louisiana. If successful, this project will demonstrate that the use of air injection in the Double Displacement Process can economically recover oil in reservoirs where tertiary oil recovery is presently uneconomic. The first quarter of 1996 was outstanding both in terms of volume of air injected and low cost operations. More air was injected during this quarter than in any preceding quarter. The compressors experienced much improved run time with minimal repairs. Low operating costs resulted from no repairs required for injection or production wells. A discussion of the following topics are contained herein: (1) performance summary for the injection and production wells, (2) air compressor operations, (3) updated bottom hole pressure data, (4) technology transfer activities and (5) plans for the upcoming quarter.

  2. Pure Air`s Bailly scrubber: A four-year retrospective

    SciTech Connect (OSTI)

    Manavi, G.B.; Vymazal, D.C.; Sarkus, T.A.

    1997-12-31

    Pure Air`s Advanced Flue Gas Desulfurization (AFGD) Clean Coal Project has completed four highly successful years of operation at NIPSCO`s Bailly Station. As part of their program, Pure Air has concluded a six-part study of system performance. This paper summarizes the results of the demonstration program, including AFGD performance on coals ranging from 2.0--2.4% sulfur. The paper highlights novel aspects of the Bailly facility, including pulverized limestone injection, air rotary sparger for oxidation, wastewater evaporation system and the production of PowerChip{reg_sign} gypsum. Operations and maintenance which have led to the facility`s notable 99.47% availability record are also discussed. A project company, Pure Air on the Lake Limited Partnership, owns the AFGD facility. Pure Air was the turn key contractor and Air Products and Chemicals, Inc. is the operator of the AFGD system.

  3. High-Performance Sorbents for Carbon Dioxide Capture from Air

    SciTech Connect (OSTI)

    Sholl, David; Jones, Christopher

    2013-03-13

    This project has focused on capture of CO{sub 2} from ambient air (“air capture”). If this process is technically and economically feasible, it could potentially contribute to net reduction of CO{sub 2} emissions in ways that are complementary to better developed techniques for CO{sub 2} from concentrated point sources. We focused on cyclic adsorption processes for CO{sub 2} capture from air in which the entire cycle is performed at moderate temperatures. The project involved both experimental studies of sorbent materials and process level modeling of cyclic air capture processes. In our experimental work, a series of amine-functionalized silica adsorbents were prepared and characterized to determine the impact of molecular architecture on CO{sub 2} capture. Some key findings were: • Amine functionalized silicas can be prepared with high enough CO{sub 2} capacities under ambient conditions to merit consideration for use in air capture processes. • Primary amines are better candidates for CO{sub 2} capture than secondary or tertiary amines, both in terms of amine efficiency for CO{sub 2} adsorption and enhanced water affinity. • Mechanistic understanding of degradation of these materials can enable control of molecular architecture to significantly improve material stability. Our process modeling work provided the first publically available cost and energy estimates for cyclic adsorption processes for air capture of CO{sub 2}. Some key findings were: • Cycles based on diurnal ambient heating and cooling cannot yield useful purities or amounts of captured CO{sub 2}. • Cycles based on steam desorption at 110 oC can yield CO{sub 2} purities of ~88%. • The energy requirements for cycles using steam desorption are dominated by needs for thermal input, which results in lower costs than energy input in the form of electricity. Cyclic processes with operational costs of less than $100 tCO{sub 2}-net were described, and these results point to process and

  4. Technology Solutions Case Study: Overcoming Comfort Issues Due to Reduced Flow Room Air Mixing

    SciTech Connect (OSTI)

    2015-03-01

    Energy efficiency upgrades reduce heating and cooling loads on a house. With enough load reduction and if the HVAC system warrants replacement, the HVAC system is often upgraded with a more efficient, lower capacity system that meets the loads of the upgraded house. In this project, IBACOS studied when HVAC equipment is downsized and ducts are unaltered to determine conditions that could cause a supply air delivery problem and to evaluate the feasibility of modifying the duct systems using minimally invasive strategies to improve air distribution.

  5. High Efficiency Room Air Conditioner

    SciTech Connect (OSTI)

    Bansal, Pradeep

    2015-01-01

    This project was undertaken as a CRADA project between UT-Battelle and Geberal Electric Company and was funded by Department of Energy to design and develop of a high efficiency room air conditioner. A number of novel elements were investigated to improve the energy efficiency of a state-of-the-art WAC with base capacity of 10,000 BTU/h. One of the major modifications was made by downgrading its capacity from 10,000 BTU/hr to 8,000 BTU/hr by replacing the original compressor with a lower capacity (8,000 BTU/hr) but high efficiency compressor having an EER of 9.7 as compared with 9.3 of the original compressor. However, all heat exchangers from the original unit were retained to provide higher EER. The other subsequent major modifications included- (i) the AC fan motor was replaced by a brushless high efficiency ECM motor along with its fan housing, (ii) the capillary tube was replaced with a needle valve to better control the refrigerant flow and refrigerant set points, and (iii) the unit was tested with a drop-in environmentally friendly binary mixture of R32 (90% molar concentration)/R125 (10% molar concentration). The WAC was tested in the environmental chambers at ORNL as per the design rating conditions of AHAM/ASHRAE (Outdoor- 95F and 40%RH, Indoor- 80F, 51.5%RH). All these modifications resulted in enhancing the EER of the WAC by up to 25%.

  6. Improved catalyst can clear the air

    SciTech Connect (OSTI)

    Pritchard, S.

    2006-05-15

    Catalyst technology can make clean coal plants look as clean as they are. This article examines the need and available methods for SO{sub 2} control with a specific focus on a catalyst technology developed by Cormetech. It also presents the results of commercial operating experience. 1 fig., 2 tabs.

  7. Maintaining System Air Quality

    Office of Energy Efficiency and Renewable Energy (EERE)

    This tip sheet discusses how to maintain air quality in compressed air systems through proper use of equipment.

  8. Tips: Air Conditioners

    Energy.gov [DOE]

    How to operate your air conditioner efficiently, or consider alternatives to air conditioning that can cool effectively in many climates.

  9. Hallmark Project

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Hallmark Project Commercialization of the Secure SCADA Communications Protocol, a cryptographic security solution for device-to-device communication Increased connectivity and automation in the control systems that manage the nation's energy infrastructure have improved system functionality, but left systems more vulnerable to cyber attack. Intruders could severely disrupt control system operation by sending fabricated information or commands to control system devices. To ensure message

  10. Air cathode structure manufacture

    DOE Patents [OSTI]

    Momyer, William R.; Littauer, Ernest L.

    1985-01-01

    An improved air cathode structure for use in primary batteries and the like. The cathode structure includes a matrix active layer, a current collector grid on one face of the matrix active layer, and a porous, nonelectrically conductive separator on the opposite face of the matrix active layer, the collector grid and separator being permanently bonded to the matrix active layer. The separator has a preselected porosity providing low IR losses and high resistance to air flow through the matrix active layer to maintain high bubble pressure during operation of the battery. In the illustrated embodiment, the separator was formed of porous polypropylene. A thin hydrophobic film is provided, in the preferred embodiment, on the current collecting metal grid.

  11. INEEL AIR MODELING PROTOCOL ext

    SciTech Connect (OSTI)

    C. S. Staley; M. L. Abbott; P. D. Ritter

    2004-12-01

    Various laws stemming from the Clean Air Act of 1970 and the Clean Air Act amendments of 1990 require air emissions modeling. Modeling is used to ensure that air emissions from new projects and from modifications to existing facilities do not exceed certain standards. For radionuclides, any new airborne release must be modeled to show that downwind receptors do not receive exposures exceeding the dose limits and to determine the requirements for emissions monitoring. For criteria and toxic pollutants, emissions usually must first exceed threshold values before modeling of downwind concentrations is required. This document was prepared to provide guidance for performing environmental compliance-driven air modeling of emissions from Idaho National Engineering and Environmental Laboratory facilities. This document assumes that the user has experience in air modeling and dose and risk assessment. It is not intended to be a "cookbook," nor should all recommendations herein be construed as requirements. However, there are certain procedures that are required by law, and these are pointed out. It is also important to understand that air emissions modeling is a constantly evolving process. This document should, therefore, be reviewed periodically and revised as needed. The document is divided into two parts. Part A is the protocol for radiological assessments, and Part B is for nonradiological assessments. This document is an update of and supersedes document INEEL/INT-98-00236, Rev. 0, INEEL Air Modeling Protocol. This updated document incorporates changes in some of the rules, procedures, and air modeling codes that have occurred since the protocol was first published in 1998.

  12. LABORATORY EVALUATION OF AIR FLOW MEASUREMENT METHODS FOR RESIDENTIAL HVAC RETURNS

    SciTech Connect (OSTI)

    Walker, Iain; Stratton, Chris

    2015-02-01

    This project improved the accuracy of air flow measurements used in commissioning California heating and air conditioning systems in Title 24 (Building and Appliance Efficiency Standards), thereby improving system performance and efficiency of California residences. The research team at Lawrence Berkeley National Laboratory addressed the issue that typical tools used by contractors in the field to test air flows may not be accurate enough to measure return flows used in Title 24 applications. The team developed guidance on performance of current diagnostics as well as a draft test method for use in future evaluations. The series of tests performed measured air flow using a range of techniques and devices. The measured air flows were compared to reference air flow measurements using inline air flow meters built into the test apparatus. The experimental results showed that some devices had reasonable results (typical errors of 5 percent or less) but others had much bigger errors (up to 25 percent). Because manufacturers’ accuracy estimates for their equipment do not include many of the sources of error found in actual field measurements (and replicated in the laboratory testing in this study) it is essential for a test method that could be used to determine the actual uncertainty in this specific application. The study team prepared a draft test method through ASTM International to determine the uncertainty of air flow measurements at residential heating ventilation and air conditioning returns and other terminals. This test method, when finalized, can be used by the Energy Commission and other entities to specify required accuracy of measurement devices used to show compliance with standards.

  13. Strategy Guideline. Compact Air Distribution Systems

    SciTech Connect (OSTI)

    Burdick, Arlan

    2013-06-01

    This guideline discusses the benefits and challenges of using a compact air distribution system to handle the reduced loads and reduced air volume needed to condition the space within an energy efficient home. The decision criteria for a compact air distribution system must be determined early in the whole-house design process, considering both supply and return air design. However, careful installation of a compact air distribution system can result in lower material costs from smaller equipment, shorter duct runs, and fewer outlets; increased installation efficiencies, including ease of fitting the system into conditioned space; lower loads on a better balanced HVAC system, and overall improved energy efficiency of the home.

  14. Air Sealing Your Home | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Your Home Air Sealing Your Home Save on heating and cooling costs by checking for air leaks in common trouble spots in your home. Save on heating and cooling costs by checking for air leaks in common trouble spots in your home. Reducing the amount of air that leaks in and out of your home is a cost-effective way to cut heating and cooling costs, improve durability, increase comfort, and create a healthier indoor environment. Caulking and weatherstripping are two simple and effective air-sealing

  15. Comparison of air and water quenching of HDS slugs

    SciTech Connect (OSTI)

    Burk, J.A.

    1988-02-03

    This memorandum recommends the use of water quenching, rather than air quenching, for pressed slugs in any future project to substantially update the Building 313-M slug manufacturing facility. At the outset of the recently canceled Project S-4092, Improved Slug Processing Facility (ISPF), 313-M, consensus of the SRP liaison team was to replace the existing water quench facility with air quenching. Principal motivations were to eliminate a liquid waste stream, reduce the quantity of process water used, and attain a more reliable mechanical system. During the ensuing years, unforeseen difficulties with air quenching have been realized. Also, effective methods of reducing and treating the waste streams generated by water quenching have been developed. Both methods the author believes will work. However, the propriety of either method of quenching is a function of the system into which it is being incorporated. Each method carried with it a lot of concealed constraint s and carefully designed additional equipment. There is today a consensus that water quenching is preferable. For future reference, some advantages and disadvantages of the two quenching methods are discussed.

  16. Air sampling in the workplace. Final report

    SciTech Connect (OSTI)

    Hickey, E.E.; Stoetzel, G.A.; Strom, D.J.; Cicotte, G.R.; Wiblin, C.M.; McGuire, S.A.

    1993-09-01

    This report provides technical information on air sampling that will be useful for facilities following the recommendations in the NRC`s Regulatory Guide 8.25, Revision 1, ``Air sampling in the Workplace.`` That guide addresses air sampling to meet the requirements in NRC`s regulations on radiation protection, 10 CFR Part 20. This report describes how to determine the need for air sampling based on the amount of material in process modified by the type of material, release potential, and confinement of the material. The purposes of air sampling and how the purposes affect the types of air sampling provided are discussed. The report discusses how to locate air samplers to accurately determine the concentrations of airborne radioactive materials that workers will be exposed to. The need for and the methods of performing airflow pattern studies to improve the accuracy of air sampling results are included. The report presents and gives examples of several techniques that can be used to evaluate whether the airborne concentrations of material are representative of the air inhaled by workers. Methods to adjust derived air concentrations for particle size are described. Methods to calibrate for volume of air sampled and estimate the uncertainty in the volume of air sampled are described. Statistical tests for determining minimum detectable concentrations are presented. How to perform an annual evaluation of the adequacy of the air sampling is also discussed.

  17. Breakthrough Video: Desiccant Enhanced Evaporative Air Conditioning

    SciTech Connect (OSTI)

    2012-01-01

    Researchers at the National Renewable Energy Laboratory (NREL) invented a breakthrough technology that improves air conditioning in a novel way—with heat. NREL combined desiccant materials, which remove moisture from the air using heat, and advanced evaporative technologies to develop a cooling unit that uses 90% less electricity and up to 80% less total energy than traditional air conditioning (AC). This solution, called the desiccant enhanced evaporative air conditioner (DEVAP), also controls humidity more effectively to improve the comfort of people in buildings.

  18. About Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    DOE Projects MicroBooNE Project Web Pages The Project Pages hold information and links for the collaboration and its Project Managers, and also hold links to project Director's and ...

  19. Improvement in understanding the deposition of ambient dust particles on ECAM (environmental continuous air monitor) filters, reduction of the alpha-particle interference of radon progeny and other radioactive aerosols in different particle size ranges on filters, and development of ECAMs with increased sensitivity under dusty outdoor conditions.

    SciTech Connect (OSTI)

    Schery, Stephen D., Wasiolek, Piotr; Rodgers, John

    1999-06-01

    Improvement in understanding the deposition of ambient dust particles on ECAM (environmental continuous air monitor) filters, reduction of the alpha-particle interference of radon progeny and other radioactive aerosols in different particle size ranges on filters, and development of ECAMs with increased sensitivity under dusty outdoor conditions.

  20. Cold Climate and Retrofit Applications for Air-to-Air Heat Pumps

    SciTech Connect (OSTI)

    Baxter, Van D

    2015-01-01

    Air source heat pumps (ASHP) including air-to-air ASHPs are easily applied to buildings almost anywhere for new construction as well as retrofits or renovations. They are widespread in milder climate regions but their use in cold regions is hampered due to low heating efficiency and capacity at cold outdoor temperatures. Retrofitting air-to-air ASHPs to existing buildings is relatively easy if the building already has an air distribution system. For buildings without such systems alternative approaches are necessary. Examples are ductless, minisplit heat pumps or central heat pumps coupled to small diameter, high velocity (SDHV) air distribution systems. This article presents two subjects: 1) a summary of R&D investigations aimed at improving the cold weather performance of ASHPs, and 2) a brief discussion of building retrofit options using air-to-air ASHP systems.

  1. Residential Forced Air System Cabinet Leakage and Blower Performance

    SciTech Connect (OSTI)

    Walker, Iain S.; Dickerhoff, Darryl J.; Delp, William W.

    2010-03-01

    This project evaluated the air leakage and electric power consumption of Residential HVAC components, with a particular focus on air leakage of furnace cabinets. Laboratory testing of HVAC components indicated that air leakage can be significant and highly variable from unit to unit ? indicating the need for a standard test method and specifying maximum allowable air leakage in California State energy codes. To further this effort, this project provided technical assistance for the development of a national standard for Residential HVAC equipment air leakage. This standard is being developed by ASHRAE and is called"ASHRAE Standard 193P - Method of test for Determining the Air Leakage Rate of HVAC Equipment". The final part of this project evaluated techniques for measurement of furnace blower power consumption. A draft test procedure for power consumption was developed in collaboration with the Canadian General Standards Board: CSA 823"Performance Standard for air handlers in residential space conditioning systems".

  2. Extension of Comment Period on Improving Performance of Federal Permitting and Review of Infrastructure Projects: Federal Register Notice Volume 78, No. 186- September 25, 2013

    Office of Energy Efficiency and Renewable Energy (EERE)

    On August 29, 2013, the U.S. Department of Energy (DOE) published a Request for Information seeking information on a draft Integrated, Interagency Pre-Application (IIP) Process for significant onshore electric transmission projects requiring Federal authorizations. This notice announces an extension of the public comment period for submitting comments regarding the IIP Process.

  3. MODELING THE TRANSPORT AND CHEMICAL EVOLUTION OF ONSHORE AND OFFSHORE EMISSIONS AND THEIR IMPACT ON LOCAL AND REGIONAL AIR QUALITY USING A VARIABLE-GRID-RESOLUTION AIR QUALITY MODEL

    SciTech Connect (OSTI)

    Kiran Alapaty

    2003-12-01

    This document, the project's first semiannual report, summarizes the research performed from 04/17/2003 through 10/16/2003. Portions of the research in several of the project's eight tasks were completed, and results obtained are briefly presented. We have tested the applicability of two different atmospheric boundary layer schemes for use in air quality model simulations. Preliminary analysis indicates that a scheme that uses sophisticated atmospheric boundary physics resulted in better simulation of atmospheric circulations. We have further developed and tested a new surface data assimilation technique to improve meteorological simulations, which will also result in improved air quality model simulations. Preliminary analysis of results indicates that using the new data assimilation technique results in reduced modeling errors in temperature and moisture. Ingestion of satellite-derived sea surface temperatures into the mesoscale meteorological model led to significant improvements in simulated clouds and precipitation compared to that obtained using traditional analyzed sea surface temperatures. To enhance the capabilities of an emissions processing system so that it can be used with our variable-grid-resolution air quality model, we have identified potential areas for improvements. Also for use in the variable-grid-resolution air quality model, we have tested a cloud module offline for its functionality, and have implemented and tested an efficient horizontal diffusion algorithm within the model.

  4. Combustion air preheating

    SciTech Connect (OSTI)

    Wells, T.A.; Petterson, W.C.

    1986-10-14

    This patent describes a process for steam cracking hydrocarbons to cracked gases in a tubular furnace heated by burning a mixture of fuel and combustion air and subsequently quenching the cracked gases. Waste heat is recovered in the form of high pressure steam and the combustion air is preheated prior to introduction into the furnace. The improvement described here comprises: (a) superheating the high pressure steam and expanding at least a portion of the superheated high pressure steam through a first turbine to produce shaft work and superheated medium pressure steam at a temperature between 260/sup 0/ and 465/sup 0/ C.; (b) expanding at least a portion of the superheated medium pressure steam through a second turbine to produce shaft work and low pressure steam at a temperature between 120/sup 0/ and 325/sup 0/ C.; and (c) preheating the combustion air by indirect heat exchange with at least a portion of the superheated medium pressure stream and at least a portion of the low pressure steam.

  5. Metal-Air Batteries

    SciTech Connect (OSTI)

    Zhang, Jiguang; Bruce, Peter G.; Zhang, Gregory

    2011-08-01

    Metal-air batteries have much higher specific energies than most currently available primary and rechargeable batteries. Recent advances in electrode materials and electrolytes, as well as new designs on metal-air batteries, have attracted intensive effort in recent years, especially in the development of lithium-air batteries. The general principle in metal-air batteries will be reviewed in this chapter. The materials, preparation methods, and performances of metal-air batteries will be discussed. Two main metal-air batteries, Zn-air and Li-air batteries will be discussed in detail. Other type of metal-air batteries will also be described.

  6. Technology Base Research Project for electrochemical energy storage

    SciTech Connect (OSTI)

    Kinoshita, Kim

    1991-06-01

    The US DOE's Office of Propulsion Systems provides support for an electrochemical energy storage program, which includes R D on advanced rechargeable batteries and fuel cells. A major goal of this program is to develop electrochemical power sources suitable for application in electric vehicles (EVs). The program centers on advanced systems that offer the potential for high performance and low life-cycle costs, both of which are necessary to permit significant penetration into commercial markets. The general R D areas addressed by the project include identification of new electrochemical couples for advanced batteries, determination of technical feasibility of the new couples, improvements in battery components and materials, establishment of engineering principles applicable to electrochemical energy storage and conversion, and the development of air-system (fuel cell, metal/air) technology for transportation applications. Major emphasis is given to applied research which will lead to superior performance and lower life-cycle costs. The TBR Project is divided into three major project elements: Exploratory Research, Applied Science Research, and Air Systems Research. Highlights of each project element are summarized according to the appropriate battery system or electrochemical research area. 16 figs., 4 tabs.

  7. Clean Air Initiative for Asian Cities | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    "The Clean Air Initiative for Asian Cities (CAI-Asia) promotes innovative ways to improve air quality in Asian cities by sharing experiences and building partnerships. CAI-Asia was...

  8. TECHNOLOGIES TO ENHANCE THE OPERATION OF EXISTING NATURAL GAS COMPRESSION INFRASTRUCTURE - MANIFOLD DESIGN FOR CONTROLLING ENGINE AIR BALANCE

    SciTech Connect (OSTI)

    Gary D. Bourn; Ford A. Phillips; Ralph E. Harris

    2005-12-01

    This document provides results and conclusions for Task 15.0--Detailed Analysis of Air Balance & Conceptual Design of Improved Air Manifolds in the ''Technologies to Enhance the Operation of Existing Natural Gas Compression Infrastructure'' project. SwRI{reg_sign} is conducting this project for DOE in conjunction with Pipeline Research Council International, Gas Machinery Research Council, El Paso Pipeline, Cooper Compression, and Southern Star, under DOE contract number DE-FC26-02NT41646. The objective of Task 15.0 was to investigate the perceived imbalance in airflow between power cylinders in two-stroke integral compressor engines and develop solutions via manifold redesign. The overall project objective is to develop and substantiate methods for operating integral engine/compressors in gas pipeline service, which reduce fuel consumption, increase capacity, and enhance mechanical integrity.

  9. project management | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    project management NNSA continues improvements in best practices for acquisition and project management In July, NNSA's Office of Acquisition and Project Management hosted the third annual Federal Project Director and Project Integrator Training Session in Albuquerque, N.M. This training is one of several initiatives undertaken by NNSA to continually improve contracting and project management... NNSA projects win Secretary's Achievement Awards for cost savings and efficiency NNSA was presented

  10. Modeling the Transport and Chemical Evolution of Onshore and Offshore Emissions and their Impact on Local and Regional Air Quality Using a Variable-Grid-Resolution Air Quality Model

    SciTech Connect (OSTI)

    Kiran Alapaty; Adel Hanna

    2006-10-16

    This research project has two primary objectives: (1) to further develop and refine the Multiscale Air Quality Simulation Platform-Variable Grid Resolution (MAQSIP-VGR) model, an advanced variable-grid-resolution air quality model, to provide detailed, accurate representation of the dynamical and chemical processes governing the fate of anthropogenic emissions in coastal environments; and (2) to improve current understanding of the potential impact of onshore and offshore oil and gas exploration and production (E&P) emissions on O{sub 3} and particulate matter nonattainment in the Gulf of Mexico and surrounding states.

  11. Photo of the Week: Air Supply | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Air Supply Photo of the Week: Air Supply February 6, 2014 - 11:02am Addthis In this 1972 photo, two scientists worked in improved supplied-air suits, which protected workers from toxic environments and protected controlled atmospheric areas from exposure to human emissions. The suits were developed at the Oak Ridge Y-12 Plant in Tennessee. | Photo courtesy of the Energy Department. In this 1972 photo, two scientists worked in improved supplied-air suits, which protected workers from toxic

  12. Mountain States Transmission Intertie (MSTI) Project

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Projects Expand Projects Skip navigation links Ancillary and Control Area Services (ACS) Practices Forum Attachment K Commercial Business Process Improvement (CBPI) Customer...

  13. Secretarial Memorandum on Integrating Project Management with...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Secretarial Memorandum on Integrating Project Management with NEPA Compliance to Improve Decision Making Secretarial Memorandum on Integrating Project Management with NEPA ...

  14. Carbon Dioxide and Ionic Liquid Refrigerants: Compact, Efficient Air Conditioning with Ionic Liquid-Based Refrigerants

    SciTech Connect (OSTI)

    2010-10-01

    BEETIT Project: Notre Dame is developing an air-conditioning system with a new ionic liquid and CO2 as the working fluid. Synthetic refrigerants used in air conditioning and refrigeration systems are potent GHGs and can trap 1,000 times more heat in the atmosphere than CO2 alone—making CO2 an attractive alternative for synthetic refrigerants in cooling systems. However, operating cooling systems with pure CO2 requires prohibitively high pressures and expensive hardware. Notre Dame is creating a new fluid made of CO2 and ionic liquid that enables the use of CO2 at low pressures and requires minimal changes to existing hardware and production lines. This new fluid also produces no harmful emissions and can improve the efficiency of air conditioning systems— enabling new use of CO2 as a refrigerant in cooling systems.

  15. Primary zone air proportioner

    DOE Patents [OSTI]

    Cleary, Edward N. G.

    1982-10-12

    An air proportioner is provided for a liquid hydrocarbon fueled gas turbine of the type which is convertible to oil gas fuel and to coal gas fuel. The turbine includes a shell for enclosing the turbine, an air duct for venting air in said shell to a gasifier, and a fuel injector for injecting gasified fuel into the turbine. The air proportioner comprises a second air duct for venting air from the air duct for mixing with fuel from the gasifier. The air can be directly injected into the gas combustion basket along with the fuel from the injector or premixed with fuel from the gasifier prior to injection by the fuel injector.

  16. Biological Air Emissions Control

    Office of Energy Efficiency and Renewable Energy (EERE)

    Air quality standards are becoming more stringent for the U.S. wood products industry. Emissions of volatile organic compounds (VOCs) and hazardous air pollutants (HAPs) (including methanol,...

  17. Projection screen having reduced ambient light scattering

    SciTech Connect (OSTI)

    Sweatt, William C.

    2010-05-11

    An apparatus and method for improving the contrast between incident projected light and ambient light reflected from a projection screen are described. The efficiency of the projection screen for reflection of the projected light remains high, while permitting the projection screen to be utilized in a brightly lighted room. Light power requirements from the projection system utilized may be reduced.

  18. Energy Savings and Economics of Advanced Control Strategies for Packaged Air-Conditioning Units with Gas Heat

    SciTech Connect (OSTI)

    Wang, Weimin; Katipamula, Srinivas; Huang, Yunzhi; Brambley, Michael R.

    2011-12-31

    Pacific Northwest National Laboratory (PNNL) with funding from the U.S. Department of Energy's Building Technologies Program (BTP) evaluated a number of control strategies that can be implemented in a controller, to improve the operational efficiency of the packaged air conditioning units. The two primary objectives of this research project are: (1) determine the magnitude of energy savings achievable by retrofitting existing packaged air conditioning units with advanced control strategies not ordinarily used for packaged units and (2) estimating what the installed cost of a replacement control with the desired features should be in various regions of the U.S. This document reports results of the study.

  19. High Energy Efficiency Air Conditioning

    SciTech Connect (OSTI)

    Edward McCullough; Patrick Dhooge; Jonathan Nimitz

    2003-12-31

    This project determined the performance of a new high efficiency refrigerant, Ikon B, in a residential air conditioner designed to use R-22. The refrigerant R-22, used in residential and small commercial air conditioners, is being phased out of production in developed countries beginning this year because of concerns regarding its ozone depletion potential. Although a replacement refrigerant, R-410A, is available, it operates at much higher pressure than R-22 and requires new equipment. R-22 air conditioners will continue to be in use for many years to come. Air conditioning is a large part of expensive summer peak power use in many parts of the U.S. Previous testing and computer simulations of Ikon B indicated that it would have 20 - 25% higher coefficient of performance (COP, the amount of cooling obtained per energy used) than R-22 in an air-cooled air conditioner. In this project, a typical new R-22 residential air conditioner was obtained, installed in a large environmental chamber, instrumented, and run both with its original charge of R-22 and then with Ikon B. In the environmental chamber, controlled temperature and humidity could be maintained to obtain repeatable and comparable energy use results. Tests with Ikon B included runs with and without a power controller, and an extended run for several months with subsequent analyses to check compatibility of Ikon B with the air conditioner materials and lubricant. Baseline energy use of the air conditioner with its original R-22 charge was measured at 90 deg F and 100 deg F. After changeover to Ikon B and a larger expansion orifice, energy use was measured at 90 deg F and 100 deg F. Ikon B proved to have about 19% higher COP at 90 deg F and about 26% higher COP at 100 deg F versus R-22. Ikon B had about 20% lower cooling capacity at 90 deg F and about 17% lower cooling capacity at 100 deg F versus R-22 in this system. All results over multiple runs were within 1% relative standard deviation (RSD). All of these

  20. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Second Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- & Post-CAP Forecast Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 84% Line Item 78% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC

  1. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- & Post-CAP Forecast Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 84% Line Item 78% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC is

  2. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Actual FY 2011 Pre- & Post-CAP Actual Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 84% Line Item 77% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC is

  3. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    First Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 84% Construction 83% Cleanup 85% 77% Pre-CAP 86% Post- CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  4. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Second Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 88% Construction 87% Cleanup 89% 77% Pre-CAP 92% Post- CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  5. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 87% Construction 87% Cleanup 87% 77% Pre-CAP 90% Post- CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  6. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Final FY 2012 Pre- & Post-CAP Final Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 86% Construction 87% Cleanup 84% 77% Pre-CAP 89% Post-CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  7. PROJECT PROFILE: An Integrated Tool for Improving Grid Performance and Reliability of Combined Transmission-Distribution with High Solar Penetration (SuNLaMP)

    Energy.gov [DOE]

    High penetration of solar photovoltaics (PV) in electric power grids has created a need for changes to power system planning and operations analysis. Important technical issues such as two-way power flow, coordination of protection devices, transmission-distribution interaction, and reduction in inertia need to be resolved to enable a greater deployment of solar generation. To overcome these technical barriers, this project will develop a suite of software tools that creates a holistic understanding of the steady-state and transient behavior of transmission-distribution networks’ interaction under high PV penetration levels, along with the capability of real-time monitoring of the distribution systems and integration of system protection.

  8. PROJECT PROFILE: Frequency Response Assessment and Improvement of Three Major North American Interconnections due to High Penetrations of Photovoltaic Generation (SuNLaMP)

    Energy.gov [DOE]

    As the number of solar photovoltaic (PV) installations continues to grow exponentially, one of the major challenges to grid stability will be mitigating decreasing system inertia and deteriorating frequency response. Preliminary independent studies on two North American interconnections have already demonstrated that the overall frequency response will deteriorate significantly with increasing renewable generation. This project will investigate the frequency response and system inertia impacts with high PV penetration levels for all three major interconnections, namely the Eastern Interconnection, Western Interconnection, and the Electric Reliability Council of Texas.

  9. Advanced Flue Gas Desulfurization (AFGD) demonstration project: Volume 2, Project performance and economics. Final technical report

    SciTech Connect (OSTI)

    1996-04-30

    The project objective is to demonstrate removal of 90--95% or more of the SO{sub 2} at approximately one-half the cost of conventional scrubbing technology; and to demonstrate significant reduction of space requirements. In this project, Pure Air has built a single SO{sub 2} absorber for a 528-MWe power plant. The absorber performs three functions in a single vessel: prequencher, absorber, and oxidation of sludge to gypsum. Additionally, the absorber is of a co- current design, in which the flue gas and scrubbing slurry move in the same direction and at a relatively high velocity compared to conventional scrubbers. These features all combine to yield a state- of-the-art SO{sub 2} absorber that is more compact and less expensive than conventional scrubbers. The project incorporated a number of technical features including the injection of pulverized limestone directly into the absorber, a device called an air rotary sparger located within the base of the absorber, and a novel wastewater evaporation system. The air rotary sparger combines the functions of agitation and air distribution into one piece of equipment to facilitate the oxidation of calcium sulfite to gypsum. Additionally, wastewater treatment is being demonstrated to minimize water disposal problems inherent in many high-chloride coals. Bituminous coals primarily from the Indiana, Illinois coal basin containing 2--4.5% sulfur were tested during the demonstration. The Advanced Flue Gas Desulfurization (AFGD) process has demonstrated removal of 95% or more of the SO{sub 2} while providing a commercial gypsum by-product in lieu of solid waste. A portion of the commercial gypsum is being agglomerated into a product known as PowerChip{reg_sign} gypsum which exhibits improved physical properties, easier flowability and more user friendly handling characteristics to enhance its transportation and marketability to gypsum end-users.

  10. EA-1912: Midway-Benton No. 1 Rebuild Project, near town of Desert...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Midway-Benton No. 1 Rebuild Project, near town of Desert Aire, Benton County, WA EA-1912: Midway-Benton No. 1 Rebuild Project, near town of Desert Aire, Benton County, WA...

  11. EM Employees Engage in Interactive Workshop on Contract, Project...

    Office of Environmental Management (EM)

    Employees Engage in Interactive Workshop on Contract, Project Management Improvements EM Employees Engage in Interactive Workshop on Contract, Project Management Improvements June ...

  12. COUNTERCURRENT FLOW LIMITATION EXPERIMENTS AND MODELING FOR IMPROVED REACTOR SAFETY

    SciTech Connect (OSTI)

    Vierow, Karen

    2008-09-26

    This project is investigating countercurrent flow and “flooding” phenomena in light water reactor systems to improve reactor safety of current and future reactors. To better understand the occurrence of flooding in the surge line geometry of a PWR, two experimental programs were performed. In the first, a test facility with an acrylic test section provided visual data on flooding for air-water systems in large diameter tubes. This test section also allowed for development of techniques to form an annular liquid film along the inner surface of the “surge line” and other techniques which would be difficult to verify in an opaque test section. Based on experiences in the air-water testing and the improved understanding of flooding phenomena, two series of tests were conducted in a large-diameter, stainless steel test section. Air-water test results and steam-water test results were directly compared to note the effect of condensation. Results indicate that, as for smaller diameter tubes, the flooding phenomena is predominantly driven by the hydrodynamics. Tests with the test sections inclined were attempted but the annular film was easily disrupted. A theoretical model for steam venting from inclined tubes is proposed herein and validated against air-water data. Empirical correlations were proposed for air-water and steam-water data. Methods for developing analytical models of the air-water and steam-water systems are discussed, as is the applicability of the current data to the surge line conditions. This report documents the project results from July 1, 2005 through June 30, 2008.

  13. Membrane Based Air Conditioning | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Membrane Based Air Conditioning Membrane Based Air Conditioning Image courtesy of Dais Analytic Corporation and BTO Peer Review. Image courtesy of Dais Analytic Corporation and BTO Peer Review. Lead Performer: Dais Analytic Corporation - Odessa, FL Partners: -- Oak Ridge National Laboratory - Oak Ridge, TN -- Xergy Inc. - Seaford, DE DOE Total Funding: $1,500,000 Cost Share: $300,000 Project Term: October 1, 2015 - September 30, 2016 Funding Opportunity: Building Energy Efficiency Frontiers and

  14. Preheated Combustion Air; Industrial Technologies Program (ITP...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    fuel-fired industrial heating processes, one of the most potent ways to improve efficiency and productivity is to preheat the combustion air going to the burners. The source of ...

  15. 2012 National Tribal Forum on Air Quality

    Energy.gov [DOE]

    This forum on improving air quality will take place May 22-24, 2012, in Tulsa, Oklahoma. It is co-sponsored by the Institute for Tribal Environmental Professionals (ITEP) and the National Tribal...

  16. Northern Cheyenne Tribe - Wind Power Project

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Northern Cheyenne Tribe Wind Power Project Program Review 2006 Ingrid Gardner Project Overview * Project began in 2002 * Sole decision maker and final authority » NORTHERN CHEYENNE TRIBE * Technical Participant » Distributed Generation Systems, Inc. * Tribal Participant » TRIBAL EDA COMMITTEE » TRIBAL EDA PLANNER Project Design * Development Phase Approach - Long Term Wind Data Collected »RAWS SITE »AIR QUALITY SITES »ON-SITE MET TOWERS 50 meter tower 20 meter tower Project Design Cont. *

  17. Assessing the potential visibility benefits of Clean Air Act Title IV emission reductions

    SciTech Connect (OSTI)

    Trexler, E.C. Jr.; Shannon, J.D.

    1995-06-01

    Assessments are made of the benefits of the 1990 Clean Air Act Title IV (COVE), Phase 2, SO2 and NOX reduction provisions, to the visibility in typical eastern and western Class 1 areas. Probable bands of visibility impairment distribution curves are developed for Shenandoah National Park, Smoky Mountain National Park and the Grand Canyon National Park, based on the existing emissions, ``Base Case``, and for the COVE emission reductions, ``CAAA Case``. Emission projections for 2010 are developed with improved versions of the National Acid Precipitation Assessment Program emission projection models. Source-receptor transfer matrices created with the Advanced Statistical Trajectory Regional Air Pollution (ASTRAP) model are used with existing emission inventories and with the emission projections to calculate atmospheric concentrations of sulfate and nitrate at the receptors of interest for existing and projected emission scenarios. The Visibility Assessment Scoping Model (VASM) is then used to develop distributions of visibility impairment. VASM combines statistics of observed concentrations of particulate species and relative humidity with ASTRAP calculations of the relative changes in atmospheric sulfate and nitrate particulate concentrations in a Monte Carlo approach to produce expected distributions of hourly particulate concentrations and RH. Light extinction relationships developed in theoretical and field studies are then used to calculate the resulting distribution of visibility impairment. Successive Monte Carlo studies are carried out to develop sets of visibility impairment distributions with and without the COVE emission reductions to gain insight into the detectability of expected visibility improvements.

  18. Cromer Cycle Air Conditioner

    Energy.gov [DOE]

    New Air Conditioning System Uses Desiccant to Transfer Moisture and Increase Efficiency and Capacity

  19. Evaluation of permanent die coatings to improve the wear resistance of die casting dies. Final project report, January 1, 1995--April 30, 1997

    SciTech Connect (OSTI)

    Shivpuri, R.

    1997-09-18

    Die Casting dies are subject to severe service conditions during the die casting operation. While these severe conditions are necessary to achieve high production rates, they cause the dies which are commonly made of H13 die steel, to suffer frequent failures. The major die failure mechanisms are erosion or washout, Heat checking, soldering and corrosion. Due to their geometrical complexity, die casting dies are very expensive (some dies cost over a million dollars), and thus a large number of parts have to be produced by a die, to justify this cost and leverage the advantages of the die casting process (high production rates, low manpower costs). A potential increase in the die service life, thus has a significant impact on the economics of the die; casting operation. There are many ways to extend die life: developing new wear resistant die materials, developing new surface treatments including coatings, improving heat treatment of existing H13 dies, using better lubricants that can protect the die material, or modifying the die geometry and process parameters to reduce the intensity of wear. Of these the use of coatings to improve the wear resistance of the die surface has shown a lot of promise. Consequently, use of coatings in the die casting industry and their wide use to decrease die wear can improve significantly the productivity of shop operations resulting in large savings in material and energy usage.

  20. Project Reports for Coeur d'Alene Tribe- 2011 Project

    Office of Energy Efficiency and Renewable Energy (EERE)

    The purpose of this proposed project is to assess and determine the technical and economic feasibility of energy efficiency improvements to existing tribally owned buildings.

  1. The Wind Forecast Improvement Project (WFIP). A Public/Private Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations -- the Northern Study Area

    SciTech Connect (OSTI)

    Finley, Cathy

    2014-04-30

    This report contains the results from research aimed at improving short-range (0-6 hour) hub-height wind forecasts in the NOAA weather forecast models through additional data assimilation and model physics improvements for use in wind energy forecasting. Additional meteorological observing platforms including wind profilers, sodars, and surface stations were deployed for this study by NOAA and DOE, and additional meteorological data at or near wind turbine hub height were provided by South Dakota State University and WindLogics/NextEra Energy Resources over a large geographical area in the U.S. Northern Plains for assimilation into NOAA research weather forecast models. The resulting improvements in wind energy forecasts based on the research weather forecast models (with the additional data assimilation and model physics improvements) were examined in many different ways and compared with wind energy forecasts based on the current operational weather forecast models to quantify the forecast improvements important to power grid system operators and wind plant owners/operators participating in energy markets. Two operational weather forecast models (OP_RUC, OP_RAP) and two research weather forecast models (ESRL_RAP, HRRR) were used as the base wind forecasts for generating several different wind power forecasts for the NextEra Energy wind plants in the study area. Power forecasts were generated from the wind forecasts in a variety of ways, from very simple to quite sophisticated, as they might be used by a wide range of both general users and commercial wind energy forecast vendors. The error characteristics of each of these types of forecasts were examined and quantified using bulk error statistics for both the local wind plant and the system aggregate forecasts. The wind power forecast accuracy was also evaluated separately for high-impact wind energy ramp events. The overall bulk error statistics calculated over the first six hours of the forecasts at both the

  2. Energy Efficiency in Buildings as an Air Quality Compliance Approach: Opportunities for the U.S. Department of Energy

    SciTech Connect (OSTI)

    Vine, Edward

    2002-05-01

    Increasing the energy efficiency of end-use equipment in the residential, commercial, and industrial sectors can reduce air pollution emissions and greenhouse gases significantly. Because energy efficiency is an effective means of reducing multi-pollutant emissions, it is important to ensure that energy efficiency is a fully engaged component of emission-reduction programs. However, while energy-efficiency measures are perceived by many stakeholders to be important options for improving air quality, some members in the air quality community are concerned about the ability of these measures to fit in a regulatory framework-in particular, the ability of emissions reductions from energy-efficiency measures to be real, quantifiable, certifiable, and enforceable. Hence, there are few air quality programs that include energy efficiency as a tool for complying with air quality regulations. This paper describes the connection between energy consumption and air quality, the potential role of energy-efficiency measures to meet air quality regulations, the barriers and challenges to the use of these measures in the air quality regulatory environment, and the potential role that the U.S. Department of Energy's (USDOE) Energy Efficiency and Renewable Energy's Building Technology, State and Community Programs (EERE-Buildings) could play in this area. EERE-Buildings can play a very important role in promoting energy efficiency in the air quality community, in ways that are fully consistent with its overall mission. EERE-Buildings will need to work with other stakeholders to aggressively promote energy efficiency via multiple means: publications, analytical tools, pilot programs, demonstrations, and program and policy analysis and evaluation. EERE-Buildings and state energy officials have considerable experience in implementing and monitoring energy-savings projects, as well as in designing documentation and verification requirements of energy-efficiency improvements. The

  3. Improved Battery Pack Thermal Management to Reduce Cost and Increase Energy Density: Cooperative Research and Development Final Report, CRADA Number CRD-12-499

    SciTech Connect (OSTI)

    Smith, K.

    2013-10-01

    Under this CRADA NREL will support Creare's project for the Department of Energy entitled 'Improved Battery Pack Thermal Management to Reduce Cost and Increase Energy Density' which involves the development of an air-flow based cooling product that increases energy density, safety, and reliability of hybrid electric vehicle battery packs.

  4. Laboratory Evaluation of Air Flow Measurement Methods for Residential...

    Office of Scientific and Technical Information (OSTI)

    used in commissioning California heating and air conditioning systems in Title 24 (Building and Appliance Efficiency Standards), thereby improving system performance and...

  5. NREL: Transmission Grid Integration - Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Researchers are exploring the potential impacts of higher penetrations of solar and wind power on system operations. Our projects provide insights that enable improved and ...

  6. Fuel Cell Forklift Project Final Report

    SciTech Connect (OSTI)

    Cummings, Clifton C

    2013-10-23

    This project addresses the DOE’s priorities related to acquiring data from real-world fuel cell operation, eliminating non-technical barriers, and increasing opportunities for market expansion of hydrogen fuel cell technologies. The project involves replacing the batteries in a complete fleet of class-1 electric lift trucks at FedEx Freight’s Springfield, MO parcel distribution center with 35 Plug Power GenDrive fuel cell power units. Fuel for the power units involves on-site hydrogen handling and dispensing equipment and liquid hydrogen delivery by Air Products. The project builds on FedEx Freight’s previous field trial experience with a handful of Plug Power’s GenDrive power units. Those trials demonstrated productivity gains and improved performance compared to battery-powered lift trucks. Full lift truck conversion at our Springfield location allows us to improve the competitiveness of our operations and helps the environment by reducing greenhouse gas emissions and toxic battery material use. Success at this distribution center may lead to further fleet conversions at some of our distribution centers.

  7. Bradys EGS Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Bradys EGS Project Bradys EGS Project Geothermal Technologies Program 2010 Peer Review Bradys Engineered Geothermal Systems Project for Engineered Geothermal Systems Demonstration Projects Track and Innovative Exploration Technologies. Objective to stimulate permeability in tight well 15-12 and improve connection to rest of the field, improve overall productivity or injectivity. egs_drakos_bradys.pdf (1.91 MB) More Documents & Publications Desert Peak EGS Project Bradys EGS Project Desert

  8. Improved aethalometer

    DOE Patents [OSTI]

    Hansen, A.D.

    1988-01-25

    An improved aethalometer having a single light source and a single light detector and two light paths from the light source to the light detector. A quartz fiber filter is inserted in the device, the filter having a collection area in one light path and a reference area in the other light path. A gas flow path through the aethalometer housing allows ambient air to flow through the collection area of the filter so that aerosol particles can be collected on the filter. A rotating disk with an opening therethrough allows light for the light source to pass alternately through the two light paths. The voltage output of the detector is applied to a VCO and the VCO pulses for light transmission separately through the two light paths, are counted and compared to determine the absorption coefficient of the collected aerosol particles. 5 figs.

  9. Isokinetic air sampler

    DOE Patents [OSTI]

    Sehmel, George A.

    1979-01-01

    An isokinetic air sampler includes a filter, a holder for the filter, an air pump for drawing air through the filter at a fixed, predetermined rate, an inlet assembly for the sampler having an inlet opening therein of a size such that isokinetic air sampling is obtained at a particular wind speed, a closure for the inlet opening and means for simultaneously opening the closure and turning on the air pump when the wind speed is such that isokinetic air sampling is obtained. A system incorporating a plurality of such samplers provided with air pumps set to draw air through the filter at the same fixed, predetermined rate and having different inlet opening sizes for use at different wind speeds is included within the ambit of the present invention as is a method of sampling air to measure airborne concentrations of particulate pollutants as a function of wind speed.

  10. Emission Inventories and Projections (Book) | SciTech Connect

    Office of Scientific and Technical Information (OSTI)

    Title: Emission Inventories and Projections When the Executive Body to the Convention on Long-range Transboundary Air Pollution took the decision to establish the Task Force on ...

  11. Alternative Fuels Data Center: Natural Gas Street Sweepers Improve...

    Alternative Fuels and Advanced Vehicles Data Center

    Natural Gas Street Sweepers Improve Air Quality in New York to someone by E-mail Share Alternative Fuels Data Center: Natural Gas Street Sweepers Improve Air Quality in New York on ...

  12. Research Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    LaboratoryNational Security Education Center Menu NSEC Educational Programs Los Alamos Dynamics Summer School Science of Signatures Advanced Studies Institute Judicial Science School SHM Data Sets and Software Research Projects Current Projects Past Projects Publications NSEC » Engineering Institute » Research Projects » Joint Los Alamos National Laboratory/UCSD research projects Past Research Projects Previous collaborations between Los Alamos National Laboratory and the University of

  13. Evaluation Framework and Analyses for Thermal Energy Storage Integrated with Packaged Air Conditioning

    SciTech Connect (OSTI)

    Kung, F.; Deru, M.; Bonnema, E.

    2013-10-01

    Few third-party guidance documents or tools are available for evaluating thermal energy storage (TES) integrated with packaged air conditioning (AC), as this type of TES is relatively new compared to TES integrated with chillers or hot water systems. To address this gap, researchers at the National Renewable Energy Laboratory conducted a project to improve the ability of potential technology adopters to evaluate TES technologies. Major project outcomes included: development of an evaluation framework to describe key metrics, methodologies, and issues to consider when assessing the performance of TES systems integrated with packaged AC; application of multiple concepts from the evaluation framework to analyze performance data from four demonstration sites; and production of a new simulation capability that enables modeling of TES integrated with packaged AC in EnergyPlus. This report includes the evaluation framework and analysis results from the project.

  14. Previously Funded Projects | The Ames Laboratory

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Previously Funded Projects Analyzing Environmental Contaminants Improvements in Inductively Coupled Plasma - Mass Spectrometry Augmenting an already effective analytical technique,...

  15. HTS Cable Projects

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Superconductivity Partnerships with Industry ANL Air Liquide DOE Golden LANL AEP ORNL Nexans Niagara Mohawk Super Power American Superconductor NYSERDA BOC Praxair W ? tion systems. This is the most the nation. W superconductivity? HTS Cable Projects www.oe.energy.gov Phone: 202 \ 586-1411 Office of Electricity Delivery and Energy Reliability, OE-1 U.S. Department of Energy - 1000 Independence Avenue, SW - Washington, DC 20585. Plugging America Into the Future of Power "A National Effort to

  16. Research Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Current Research Projects Joint Los Alamos National LaboratoryUCSD Research Projects Collaborations between Los Alamos National Laboratory and the University of California at San...

  17. Project Accounts

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Project Accounts Project Accounts A redirector page has been set up without anywhere to redirect to. Last edited: 2016-04-29 11:34:50

  18. Project Financing

    Office of Environmental Management (EM)

    evaluate a Federal Energy Efficiency Project across three broad risk categories: - Contract Risk - Project Risk - Participant Risk * Ultimately, pricing and terms are set by ...

  19. Project Gnome

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Project Gnome Double Beta Decay Dark Matter Biology Repository Science Renewable Energy The first underground physics experiment near Carlsbad was Project Gnome, December 10, 1961 ...

  20. Industrial end-use forecasting that incorporates DSM and air quality

    SciTech Connect (OSTI)

    Tutt, T.; Flory, J.

    1995-05-01

    The California Energy Commission (CEC) and major enregy utilities in California have generally depended on simple aggregate intensity or economic models to forecast energy use in the process industry sector (which covers large industries employing basic processes to transform raw materials, such as paper mills, glass plants, and cement plants). Two recent trends suggests that the time has come to develop a more disaggregate process industry forecasting model. First, recent efforts to improve air quality, especially by the South Coast Air Quality Management District (SCAQMD), could significantly affect energy use by the process industry by altering the technologies and processes employed in order to reduce emissions. Second, there is a renewed interest in Demand-Side Management (DSM), not only for utility least-cost planning, but also for improving the economic competitiveness and environmental compliance of the pro{minus}cess industries. A disaggregate forecasting model is critical to help the CEC and utilities evaluate both the air quality and DSM impacts on energy use. A crucial obstacle to the development and use of these detailed process industry forecasting models is the lack of good data about disaggregate energy use in the sector. The CEC is nearing completion of a project to begin to overcome this lack of data. The project is testing methds of developing detailed energy use data, collecting an initial database for a large portion of southern California, and providing recommendations and direction for further data collection efforts.

  1. Project Controls Fellowship Program | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Project Controls Fellowship Program Project Controls Fellowship Program Project Controls Fellowship Program (466.96 KB) Key Resources Internal DOE Tools PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications Project Controls Fellowship Program Improving DOE's Project Controls Integration with Project Management Please click here to read the latest interactive edition of DOE Project Management News. This month's edition includes the Director's

  2. Improving Steam System Performance: A Sourcebook for Industry, Second Edition (Book) (Revised)

    SciTech Connect (OSTI)

    Not Available

    2012-10-01

    Improving Steam System Performance: A Sourcebook for Industry was developed for the U.S. Department of Energy's (DOE) Advanced Manufacturing Office (AMO), formerly the Industrial Technologies Program. AMO undertook this project as a series of sourcebook publications. Other topics in this series include: compressed air systems, pumping systems, fan systems, process heating and motor and drive systems. For more information about program resources, see AMO in the Where to Find Help section of this publication.

  3. Simple Interactive Models for better air quality (SIM-air) |...

    Open Energy Information (Open El) [EERE & EIA]

    Interactive Models for better air quality (SIM-air) Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Simple Interactive Models (SIM-air) AgencyCompany Organization:...

  4. Low excess air operations of oil boilers

    SciTech Connect (OSTI)

    Butcher, T.A.; Celebi, Y.; Litzke, Wai Lin

    1997-09-01

    To quantify the benefits which operation at very low excess air operation may have on heat exchanger fouling BNL has recently started a test project. The test allows simultaneous measurement of fouling rate, flue gas filterable soot, flue gas sulfuric acid content, and flue gas sulfur dioxide.

  5. Observing Emissions of Air Pollutants from Space | Argonne National...

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    to study the future turnover of vehicle fleets around the world and the likely effects on air pollution and climate. This project has used satellite data to monitor CO, CO2,...

  6. Brazil-World Bank Climate Projects | Open Energy Information

    Open Energy Information (Open El) [EERE & EIA]

    1.1 Sao Paulo Metro Line 5 Project 1.2 BR-GEF Sustainable Transport and Air Quality Project (STAQ) 1.3 First Programmatic Development Policy Loan for Sustainable...

  7. California Clean Air Act: A compliance strategy for the City of San Diego`s non-emergency fleet

    SciTech Connect (OSTI)

    Not Available

    1992-12-31

    Historically, parts of California have had the worst air quality in the nation. The California Energy Commission began experimenting with alternate fuels in the 1970`s in an effort to reduce harmful automobile emissions and hence, improve air quality. It is recognized that the costs to California which result from our air quality problems are immense. Ten to twenty billion dollars each year is the estimated damage in terms of health impacts, materials damages, lost agricultural crop output and forest damages. As the California population increases and health care costs escalate, the total monetary damages from air pollution will increase. The California Energy Commission goal to improve air quality became a mandate in 1988 with the passage of the California Clean Air Act (CCAA). The CCAA requires a revised air quality strategy for the San Diego district since we do not meet State air quality standards for smog, carbon monoxide and nitrogen dioxide. Smog remains San Diego`s major air quality problem, even though the annual number of days each year over the Federal standard has been reduced by 55 percent in the past ten years. Ten years ago about two-thirds of San Diego`s smog was transported from Los Angeles. Today more than 60 per cent of the days San Diego exceeds the State standard are from locally generated smog. It is estimated that 57% of the reactive hydrocarbon emissions (which react with nitrogen dioxide in the presence of sunlight to form smog) is from cars, trucks and buses. The Air Pollution Control District (part of the County of San Diego) is the office that the Air Resources Board has put in charge of creating regulations and designing strategy to reduce polluting emissions. The purpose of this project is to determine the full cost of acquiring and operating a municipal fleet which meets the mandates of the California Clean Air Act. With that information, a plan to meet the Clear Air Act (CCAA) requirements can be formulated by local government.

  8. ACCESS Project: Final Report

    SciTech Connect (OSTI)

    Weller, Heiko

    2015-04-01

    The ACCESS project addressed the development, testing, and demonstration of the proposed advanced technologies and the associated emission and fuel economy improvement at an engine dynamometer and on a full-scale vehicle. Improve fuel economy by 25% with minimum performance penalties Achieve SULEV level emissions with gasoline Demonstrate multi-mode combustion engine management system

  9. Air Cooling Technology for Advanced Power Electronics and Electric Machines (Presentation)

    SciTech Connect (OSTI)

    Bharathan, D.

    2009-05-01

    This presentation gives an overview of the status and FY09 accomplishments for the NREL thermal management research project 'Air Cooling for Power Electronics'.

  10. Compressed Air System Upgrade Generates Significant Energy Savings at a Steel Mill

    SciTech Connect (OSTI)

    2010-06-25

    In 1996, U.S. Steel completed a project in which the main compressed air system at their Edgar Thomson plant in Braddock, Pennsylvania was overhauled.

  11. Check Burner Air to Fuel Ratios | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Burner Air to Fuel Ratios Check Burner Air to Fuel Ratios This tip sheet discusses when to check and reset burner air to fuel ratios as well as why it's a simply way to maximize the efficiency of process heating equipment. PROCESS HEATING TIP SHEET #2 Check Burner Air to Fuel Ratios (November 2007) (260.29 KB) More Documents & Publications Waste Heat Reduction and Recovery for Improving Furnace Efficiency, Productivity and Emissions Performance: A BestPractices Process Heating Technical

  12. Maintaining Your Air Conditioner

    Energy.gov [DOE]

    Regular maintenance extends the life of your air conditioner and helps it run as efficiently as possible.

  13. Minimize Compressed Air Leaks

    Office of Energy Efficiency and Renewable Energy (EERE)

    This tip sheet outlines a strategy for compressed air leak detection and provides a formula for cost savings calculations.

  14. Air-Cooled Stack Freeze Tolerance Freeze Failure Modes and Freeze Tolerance Strategies for GenDriveTM Material Handling Application Systems and Stacks Final Scientific Report

    SciTech Connect (OSTI)

    Hancock, David, W.

    2012-02-14

    Air-cooled stack technology offers the potential for a simpler system architecture (versus liquid-cooled) for applications below 4 kilowatts. The combined cooling and cathode air allows for a reduction in part count and hence a lower cost solution. However, efficient heat rejection challenges escalate as power and ambient temperature increase. For applications in ambient temperatures below freezing, the air-cooled approach has additional challenges associated with not overcooling the fuel cell stack. The focus of this project was freeze tolerance while maintaining all other stack and system requirements. Through this project, Plug Power advanced the state of the art in technology for air-cooled PEM fuel cell stacks and related GenDrive material handling application fuel cell systems. This was accomplished through a collaborative work plan to improve freeze tolerance and mitigate freeze-thaw effect failure modes within innovative material handling equipment fuel cell systems designed for use in freezer forklift applications. Freeze tolerance remains an area where additional research and understanding can help fuel cells to become commercially viable. This project evaluated both stack level and system level solutions to improve fuel cell stack freeze tolerance. At this time, the most cost effective solutions are at the system level. The freeze mitigation strategies developed over the course of this project could be used to drive fuel cell commercialization. The fuel cell system studied in this project was Plug Power's commercially available GenDrive platform providing battery replacement for equipment in the material handling industry. The fuel cell stacks were Ballard's commercially available FCvelocity 9SSL (9SSL) liquid-cooled PEM fuel cell stack and FCvelocity 1020ACS (Mk1020) air-cooled PEM fuel cell stack.

  15. Project Controls

    Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Project controls are systems used to plan, schedule, budget, and measure the performance of a project/program. The cost estimation package is one of the documents that is used to establish the baseline for project controls. This chapter gives a brief description of project controls and the role the cost estimation package plays.

  16. Cleaner Vehicles, Cleaner Fuel & Cleaner Air | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Cleaner Vehicles, Cleaner Fuel & Cleaner Air Cleaner Vehicles, Cleaner Fuel & Cleaner Air 2002 DEER Conference Presentation: U.S. Environmental Protection Agency 2002_deer_mcdonald.pdf (2.16 MB) More Documents & Publications Use of a Diesel Fuel Processor for Rapid and Efficient Regeneration of Single Leg NOx Adsorber Systems NOx Adsorbers for Heavy Duty Truck Engines - Testing and Simulation APBF-DEC Heavy Duty NOx Adsorber/DPF Project: Heavy Duty Linehaul Platform Project Up

  17. Renewable Hydrogen Production at Hickam Air Force Base | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Energy at Hickam Air Force Base Renewable Hydrogen Production at Hickam Air Force Base Presented at the Renewable Hydrogen Workshop, Nov. 16, 2009, in Palm Springs, CA renewable_hydrogen_workshop_nov16_quinn.pdf (920.39 KB) More Documents & Publications Hickam Air Force Base Fuel Cell Vehicles: Early Implementation Experience Fuel Cell Hybrid Bus Lands at Hickam AFB: Hydrogen Fuel Cell & Infrastructure Technologies Program, Fuel Cell Bus Demonstration Project (Fact Sheet) Hawaii

  18. Fuel-Free Compressed-Air Energy Storage: Fuel-Free, Ubiquitous Compressed-Air Energy Storage and Power Conditioning

    SciTech Connect (OSTI)

    2010-09-13

    GRIDS Project: General Compression has developed a transformative, near-isothermal compressed air energy storage system (GCAES) that prevents air from heating up during compression and cooling down during expansion. When integrated with renewable generation, such as a wind farm, intermittent energy can be stored in compressed air in salt caverns or pressurized tanks. When electricity is needed, the process is reversed and the compressed air is expanded to produce electricity. Unlike conventional compressed air energy storage (CAES) projects, no gas is burned to convert the stored high-pressure air back into electricity. The result of this breakthrough is an ultra-efficient, fully shapeable, 100% renewable and carbon-free power product. The GCAES™ system can provide high quality electricity and ancillary services by effectively integrating renewables onto the grid at a cost that is competitive with gas, coal and nuclear generation.

  19. Iron-Air Rechargeable Battery: A Robust and Inexpensive Iron-Air Rechargeable Battery for Grid-Scale Energy Storage

    SciTech Connect (OSTI)

    2010-10-01

    GRIDS Project: USC is developing an iron-air rechargeable battery for large-scale energy storage that could help integrate renewable energy sources into the electric grid. Iron-air batteries have the potential to store large amounts of energy at low cost—iron is inexpensive and abundant, while oxygen is freely obtained from the air we breathe. However, current iron-air battery technologies have suffered from low efficiency and short life spans. USC is working to dramatically increase the efficiency of the battery by placing chemical additives on the battery’s iron-based electrode and restructuring the catalysts at the molecular level on the battery’s air-based electrode. This can help the battery resist degradation and increase life span. The goal of the project is to develop a prototype iron-air battery at significantly cost lower than today’s best commercial batteries.

  20. Stirling Air Conditioner for Compact Cooling (Program Document) | SciTech

    Office of Scientific and Technical Information (OSTI)

    Connect Program Document: Stirling Air Conditioner for Compact Cooling Citation Details In-Document Search Title: Stirling Air Conditioner for Compact Cooling BEETIT Project: Infinia is developing a compact air conditioner that uses an unconventional high efficient Stirling cycle system (vs. conventional vapor compression systems) to produce cool air that is energy efficient and does not rely on polluting refrigerants. The Stirling cycle system is a type of air conditioning system that uses

  1. Biochemical Process Improvements & Synthetic Biology Validation...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Process Improvements & Synthetic Biology Validation Projects This presentation ... Develop efficient, inexpensive synthetic biology methods and tools to convert biomass into ...

  2. Project Information

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Project Information Slider award map The REE Program funds projects focused on developing economically feasible and environmentally benign technologies for recovering REEs from coal and/or coal by-products. Project Information The listed projects represent the current REE program portfolio. Agreement Number Project Title Performer Name FWP-RIC REE FY2016-2020 Rare Earth Elements (REE) from Coal and Coal By-Products National Energy Technology Laboratory FE0027167 High Yield and Economical

  3. Improve Your Boiler's Combustion Efficiency, Energy Tips: STEAM...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    Improve Your Boiler's Combustion Efficiency Combustion Efficiency Operating your boiler with an optimum amount of excess air will minimize heat loss up the stack and improve ...

  4. Air Sparging Decision Tool

    Energy Science and Technology Software Center (OSTI)

    1996-06-10

    The Air Sparging Decision Tool is a computer decision aid to help environmental managers and field practitioners in evaluating the applicability of air sparging to a wide range of sites and for refining the operation of air sparging systems. The program provides tools for the practitioner to develop the conceptual design for an air sparging system suitable for the identified site. The Tool provides a model of the decision making process, not a detailed designmore » of air sparging systems. The Tool will quickly and cost effectively assist the practitioner in screening for applicability of the technology at a proposed site.« less

  5. Determining the Right Air Quality for Your Compressed Air System

    Energy.gov [DOE]

    This tip sheet outlines the main factors for determining the right air quality for compressed air systems.

  6. Improvements to the Rocky Flats Metrology Laboratories Velocity Meter Calibration System

    SciTech Connect (OSTI)

    Abercrombie, K.R.

    1992-03-12

    The Rocky Flats Standards Laboratory has undertaken a project to improve calibration of air velocity meters by reducing the uncertainty of the Velocity Meter Calibration System. The project was accomplished by analyzing the governing equation in order to determine which areas within the system contributed most to the overall system uncertainty. Then, based upon this new analysis, new components were selected to replace the components identified in the analysis. Finally, the system was re-evaluated to determine the new systematic uncertainty for the system.

  7. Development and testing of an air quality model for Mexico City

    SciTech Connect (OSTI)

    Williams, M.D.; Streit, G. ); Cruz, X.; Ruiz, M.; Sosa, G. ); Russell, A.G.; McNair, L.A. . Dept. of Mechanical Engineering)

    1992-03-02

    Los Alamos National Laboratory and Instituto Mexicano del Petroleo have embarked on a joint study of options for improving air quality in Mexico City. The intent is to develop a modeling system which can address the behavior of pollutants in the region so that option for improving Mexico City air quality can be properly evaluated. In February of 1991, the project conducted a field program which yielded a variety of data which is being used to evaluate and improve the models. Normally the worst air quality for both primary and photochemical pollutants occurs in the winter Mexico City. During the field program, measurements included: (1) lidar measurements of aerosol transport and dispersion, (2) aircraft measurements of winds, turbulence, and chemical species aloft, (3) aircraft measurements of earth surface skin temperatures, and (4) tethersonde measurements of wind, temperature and ozone vertical profiles. A three-dimensional, prognostic, higher order turbulence meteorological model (HOTMAC) was modified to include an urban canopy and urban heat sources. HOTMAC is used to drive an Monte-Carlo kernel dispersion code (RAPTAD). HOTMAC also provides winds and mixing heights for the CIT photochemical model which was developed by investigators at the California Institute of Technology and Carnegie Mellon University.

  8. Line Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Grand Coulee Transmission Line Replacement Project Hooper Springs McNary-John Day Montana-to-Washington Transmission System Upgrade Project - M2W Olympia-Grand Coulee No. 1...

  9. Project Benefits

    Energy.gov [DOE]

    Benefits of the Guidelines for Home Energy Professionals project including reducing energy upgrade costs for consumers, employers, and program administrators.

  10. Hydropower Projects

    Energy.gov [DOE]

    This report covers the Wind and Water Power Technologies Office's hydropower project funding from fiscal years 2008 to 2014.

  11. NAVAJO ELECTRIFICATION DEMONSTRATION PROJECT

    SciTech Connect (OSTI)

    Terry W. Battiest

    2008-06-11

    The Navajo Electrification Demonstration Project (NEDP) is a multi-year project which addresses the electricity needs of the unserved and underserved Navajo Nation, the largest American Indian tribe in the United States. The program serves to cumulatively provide off-grid electricty for families living away from the electricty infrastructure, line extensions for unserved families living nearby (less than 1/2 mile away from) the electricity, and, under the current project called NEDP-4, the construction of a substation to increase the capacity and improve the quality of service into the central core region of the Navajo Nation.

  12. Parameters used in the environmental pathways (DESCARTES) and radiological dose (CIDER) modules of the Hanford Environmental Dose Reconstruction Integrated Codes (HEDRIC) for the air pathway. Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Snyder, S.F.; Farris, W.T.; Napier, B.A.; Ikenberry, T.A.; Gilbert, R.O.

    1992-09-01

    This letter report is a description of work performed for the Hanford Environmental Dose Reconstruction (HEDR) Project. The HEDR Project was established to estimate the radiation doses to individuals resulting from releases of radionuclides from the Hanford Site since 1944. This work is being done by staff at Battelle, Pacific Northwest Laboratories (Battelle) under a contract with the Centers for Disease Control (CDC) with technical direction provided by an independent Technical Steering Panel (TSP). The objective of this report is to-document the environmental accumulation and dose-assessment parameters that will be used to estimate the impacts of past Hanford Site airborne releases. During 1993, dose estimates made by staff at Battelle will be used by the Fred Hutchinson Cancer Research Center as part of the Hanford Thyroid Disease Study (HTDS). This document contains information on parameters that are specific to the airborne release of the radionuclide iodine-131. Future versions of this document will include parameter information pertinent to other pathways and radionuclides.

  13. Ergonomic Improvements for Foundries

    SciTech Connect (OSTI)

    Frank Peters; Patrick Patterson

    2002-06-18

    The goal of this project was to make improvements to the production systems of the steel casting industry through ergonomic improvements. Because of the wide variety of products, the wide range of product sizes, and the relatively small quantities of any particular product, manual operations remain a vital part of the production systems of the steel casting companies. Ergonomic improvements will assist the operators to more efficiently and consistently produce quality products.

  14. Determining the Right Air Quality for Your Compressed Air System - Compressed Air Tip Sheet #5

    SciTech Connect (OSTI)

    2004-08-01

    BestPractices Program tip sheet discussing how to determine the right air quality for compressed air systems.

  15. Distributed Wind Competitiveness Improvement Project Fact Sheet...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    its National Renewable Energy Laboratory (NREL). Manufacturers of small and medium wind turbines are awarded cost-shared grants via a competitive process to optimize their ...

  16. Class 8 Truck Freight Efficiency Improvement Project

    Energy.gov [DOE]

    2011 DOE Hydrogen and Fuel Cells Program, and Vehicle Technologies Program Annual Merit Review and Peer Evaluation

  17. Project Profile: Improved Large Aperture Collector Manufacturing...

    Energy.gov (indexed) [DOE]

    costs, resulting in a savings of 30m2. Publications, Patents, and Awards Final Report Learn about other DOE competitive awards for concentrating solar power research that ...

  18. PROJECT PROFILE: Frequency Response Assessment and Improvement...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    TN SunShot Award Amount: 2,200,000 Awardee Cost Share: 107,853 As the number of solar photovoltaic (PV) installations continues to grow exponentially, one of the major challenges ...

  19. Class 8 Truck Freight Efficiency Improvement Project

    Energy.gov (indexed) [DOE]

    ... HEV Engine controls Integration SAE Hybrid Committee Standards development for ... testing on-going HV-LV DCDC Inverter Junction Box HV-MV DCDC HV Battery eAC Comp. ...

  20. Improving Capital Assets Project Documentation | Department of...

    Energy.gov (indexed) [DOE]

    PARS II Data Quality Memorandum from Deputy Secretary Poneman (June 19, 2012) Smith Electric Vehicles: Advanced Vehicle Electrification + Transportation Sector...

  1. 2010 Quality Assurance Improvement Project Plan

    Office of Environmental Management (EM)

    Energy 9 Tribal Energy Program Review Meeting Presentations 2009 Tribal Energy Program Review Meeting Presentations Find presentations from the November 2009 Tribal Energy Program Review held in Denver, Colorado, below. Sort by topic, tribe, presenter, or presentation title. Topic Tribe Presenter Presentation Federal Programs and DOE Laboratories Lizana Pierce Tribal Energy Program Overview Federal Programs and DOE Laboratories Roger Taylor National Renewable Energy Laboratory Federal

  2. Connecticut Weatherization Project Improves Lives, Receives National...

    Energy Savers

    The upgrade to the facility also captured a residential energy efficiency award and is an example for other states. With support from the Energy Department's Weatherization ...

  3. Improving Capital Assets Project Documentation | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) (indexed site)

    PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications Smith Electric Vehicles: Advanced Vehicle Electrification + Transportation Sector ...

  4. Common Air Conditioner Problems

    Energy.gov [DOE]

    When your air conditioner is not operating properly, there are a few things you can check before calling a service professional.

  5. Personal continuous air monitor

    DOE Patents [OSTI]

    Morgan, Ronald G.; Salazar, Samuel A.

    2000-01-01

    A personal continuous air monitor capable of giving immediate warning of the presence of radioactivity has a filter/detector head to be worn in the breathing zone of a user, containing a filter mounted adjacent to radiation detectors, and a preamplifier. The filter/detector head is connected to a belt pack to be worn at the waist or on the back of a user. The belt pack contains a signal processor, batteries, a multichannel analyzer, a logic circuit, and an alarm. An air pump also is provided in the belt pack for pulling air through the filter/detector head by way of an air tube.

  6. Adsorption air conditioner

    DOE Patents [OSTI]

    Rousseau, Jean L. I.

    1979-01-01

    A solar powered air conditioner using the adsorption process is constructed with its components in a nested cylindrical array for compactness and ease of operation.

  7. Hill Air Force Base

    Energy.gov [DOE]

    Energy savings performance contracting at Hill Air Force Base generated much interest during a recent training session on energy management that downlinked 12 Department of Defense sites. Energy...

  8. Technology Solutions Case Study: Air Leakage and Air Transfer Between Garage and Living Space, Waldorf, Maryland

    SciTech Connect (OSTI)

    2014-11-01

    In this project, Building Science Corporation worked with production homebuilder K. Hovnanian to evaluate air transfer between the garage and living space in a single-family detached home constructed by a production homebuilder in compliance with the 2009 International Residential Code and the 2009 International Energy Conservation Code. The project gathered important information about the performance of whole-building ventilation systems and garage ventilation systems as they relate to minimizing flow of contaminated air from garage to living space. A series of 25 multipoint fan pressurization tests and additional zone pressure diagnostic testing measured the garage and house air leakage, the garage-to-house air leakage, and garage and house pressure relationships to each other and to outdoors using automated fan pressurization and pressure monitoring techniques. While the relative characteristics of this house may not represent the entire population of new construction configurations and air tightness levels (house and garage) throughout the country, the technical approach was conservative and should reasonably extend the usefulness of the results to a large spectrum of house configurations from this set of parametric tests in this one house. Based on the results of this testing, the two-step garage-to-house air leakage test protocol described above is recommended where whole-house exhaust ventilation is employed. For houses employing whole-house supply ventilation (positive pressure) or balanced ventilation (same pressure effect as the baseline condition), adherence to the EPA Indoor airPLUS house-to-garage air sealing requirements should be sufficient to expect little to no garage-to-house air transfer.

  9. Evaluation of a jet plate solar air heater

    SciTech Connect (OSTI)

    Choudhury, C.; Garg, H.P. )

    1991-01-01

    To achieve higher heat transfer from the absorber plate to the flowing air stream with an intention to increase the amount of the collected energy, and hence, to improve the efficiency of an air-based solar collector, a unique jet impingement concept has been advanced for evaluation in the present study. To investigate the effects of various geometrical parameters such as the hole or nozzle diameter on the jet plate, their interspacings, the nozzle height, the distance between the absorber and the jet plate and the operational parameter such as the velocity of air impinging out of the holes/nozzles on to the back side of the absorber surface on the performance parameters of the jet impingement concept air heater, a detailed theoretical parametric analysis has been made on the design for different mass flow rates of air and different lengths of air channel. A parallel study has also been carried out on a conventional parallel plate air heater in order to compare its air temperature increment and performance efficiency with those of the jet plate air heater. The gain in air temperature increment and performance efficiency of the jet-concept air heater over that of the parallel plate air heater with duct depth 10 cm and length 2 m is 15.5{degree}C to 2.5{degree}C and 26.5% to 19%, respectively, for air flow rates in the range 50 to 250 kg/hm{sup 2}.

  10. Acquisition & Project Management | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    Acquisition & Project Management NNSA continues improvements in best practices for acquisition and project management In July, NNSA's Office of Acquisition and Project Management hosted the third annual Federal Project Director and Project Integrator Training Session in Albuquerque, N.M. This training is one of several initiatives undertaken by NNSA to continually improve contracting and project management... NNSA Office of Acquisition Management improves customer satisfaction (Click to view

  11. SU-D-207-01: Markerless Respiratory Motion Tracking with Contrast Enhanced Thoracic Cone Beam CT Projections

    SciTech Connect (OSTI)

    Chao, M; Yuan, Y; Rosenzweig, K; Lo, Y; Brousmiche, S

    2015-06-15

    Purpose: To develop a novel technique to enhance the image contrast of clinical cone beam CT projections and extract respiratory signals based on anatomical motion using the modified Amsterdam Shroud (AS) method to benefit image guided radiation therapy. Methods: Thoracic cone beam CT projections acquired prior to treatment were preprocessed to increase their contrast for better respiratory signal extraction. Air intensity on raw images was firstly estimated and then applied to correct the projections to generate new attenuation images that were subsequently improved with deeper anatomy feature enhancement through taking logarithm operation, derivative along superior-inferior direction, respectively. All pixels on individual post-processed two dimensional images were horizontally summed to one column and all projections were combined side by side to create an AS image from which patient’s respiratory signal was extracted. The impact of gantry rotation on the breathing signal rendering was also investigated. Ten projection image sets from five lung cancer patients acquired with the Varian Onboard Imager on 21iX Clinac (Varian Medical Systems, Palo Alto, CA) were employed to assess the proposed technique. Results: Application of the air correction on raw projections showed that more than an order of magnitude of contrast enhancement was achievable. The typical contrast on the raw projections is around 0.02 while that on attenuation images could greater than 0.5. Clear and stable breathing signal can be reliably extracted from the new images while the uncorrected projection sets failed to yield clear signals most of the time. Conclusion: Anatomy feature plays a key role in yielding breathing signal from the projection images using the AS technique. The air correction process facilitated the contrast enhancement significantly and attenuation images thus obtained provides a practical solution to obtaining markerless breathing motion tracking.

  12. The search for extended air showers at the Jicamarca Radio Observatory

    SciTech Connect (OSTI)

    Wahl, D.; Chau, J.; Galindo, F.; Huaman, A.; Solano, C. J.

    2009-04-30

    This paper presents the status of the project to detect extended air showers at the Jicamarca Radio Observatory. We report on detected anomalous signals and present a toy model to estimate at what altitudes we might expect to see air shower signals. According to this model, a significant number of high altitude horizontal air showers could be observed by radar techniques.

  13. Tribal Renewable Energy Webinar: Project Regulatory Considerations

    Energy.gov [DOE]

    Learn about the many permitting and project regulatory issues that need to be addressed when developing energy projects. Considerations include the Helping Expedite and Advance Responsible Tribal Home Ownership (HEARTH) Act, land use, noise, birds, and other biological resources; visual impact; soil erosion and water quality; public health and safety; cultural and paleontological resources; solid and hazardous wastes; air quality; and climate.

  14. Developing Government Renewable Energy Projects

    SciTech Connect (OSTI)

    Kurt S. Myers; Thomas L. Baldwin; Jason W. Bush; Jake P. Gentle

    2012-07-01

    The US Army Corps of Engineers has retained Idaho National Laboratory (INL) to conduct a study of past INL experiences and complete a report that identifies the processes that are needed for the development of renewable energy projects on government properties. The INL has always maintained expertise in power systems and applied engineering and INL’s renewable energy experiences date back to the 1980’s when our engineers began performing US Air Force wind energy feasibility studies and development projects. Over the last 20+ years of working with Department of Defense and other government agencies to study, design, and build government renewable projects, INL has experienced the do’s and don’ts for being successful with a project. These compiled guidelines for government renewable energy projects could include wind, hydro, geothermal, solar, biomass, or a variety of hybrid systems; however, for the purpose of narrowing the focus of this report, wind projects are the main topic discussed throughout this report. It is our thought that a lot of what is discussed could be applied, possibly with some modifications, to other areas of renewable energy. It is also important to note that individual projects (regardless the type) vary to some degree depending on location, size, and need but in general these concepts and directions can be carried over to the majority of government renewable energy projects. This report focuses on the initial development that needs to occur for any project to be a successful government renewable energy project.

  15. Research Projects

    U.S. Department of Energy (DOE) all webpages (Extended Search)

    Francois Hemez (X-1-MV: METHODS AND VERIFICATION) Dr. Gyuhae Park (INST-OFF: INSTITUTES) Dr. Irene Beyerlein (T-03: FLUID DYNAMICS) Unmanned Air Vehicles (UAV's) are being used by ...

  16. Linear air-fuel sensor development

    SciTech Connect (OSTI)

    Garzon, F.; Miller, C.

    1996-12-14

    The electrochemical zirconia solid electrolyte oxygen sensor, is extensively used for monitoring oxygen concentrations in various fields. They are currently utilized in automobiles to monitor the exhaust gas composition and control the air-to-fuel ratio, thus reducing harmful emission components and improving fuel economy. Zirconia oxygen sensors, are divided into two classes of devices: (1) potentiometric or logarithmic air/fuel sensors; and (2) amperometric or linear air/fuel sensors. The potentiometric sensors are ideally suited to monitor the air-to-fuel ratio close to the complete combustion stoichiometry; a value of about 14.8 to 1 parts by volume. This occurs because the oxygen concentration changes by many orders of magnitude as the air/fuel ratio is varied through the stoichiometric value. However, the potentiometric sensor is not very sensitive to changes in oxygen partial pressure away from the stoichiometric point due to the logarithmic dependence of the output voltage signal on the oxygen partial pressure. It is often advantageous to operate gasoline power piston engines with excess combustion air; this improves fuel economy and reduces hydrocarbon emissions. To maintain stable combustion away from stoichiometry, and enable engines to operate in the excess oxygen (lean burn) region several limiting-current amperometric sensors have been reported. These sensors are based on the electrochemical oxygen ion pumping of a zirconia electrolyte. They typically show reproducible limiting current plateaus with an applied voltage caused by the gas diffusion overpotential at the cathode.

  17. Portable oven air circulator

    DOE Patents [OSTI]

    Jorgensen, Jorgen A.; Nygren, Donald W.

    1983-01-01

    A portable air circulating apparatus for use in cooking ovens which is used to create air currents in the oven which transfer heat to cooking foodstuffs to promote more rapid and more uniform cooking or baking, the apparatus including a motor, fan blade and housing of metallic materials selected from a class of heat resistant materials.

  18. AIR RADIOACTIVITY MONITOR

    DOE Patents [OSTI]

    Bradshaw, R.L.; Thomas, J.W.

    1961-04-11

    The monitor is designed to minimize undesirable background buildup. It consists of an elongated column containing peripheral electrodes in a central portion of the column, and conduits directing an axial flow of radioactively contaminated air through the center of the column and pure air through the annular portion of the column about the electrodes. (AEC)

  19. Protective air lock

    DOE Patents [OSTI]

    Evans, Herbert W.

    1976-03-30

    A device suitable for preventing escape and subsequent circulation of toxic gases comprising an enclosure which is sealed by a surrounding air lock, automatic means for partially evacuating said enclosure and said air lock and for ventilating said enclosure and means for disconnecting said enclosure ventilating means, whereby a relatively undisturbed atmosphere is created in said enclosure.

  20. Recirculating electric air filter

    DOE Patents [OSTI]

    Bergman, Werner

    1986-01-01

    An electric air filter cartridge has a cylindrical inner high voltage eleode, a layer of filter material, and an outer ground electrode formed of a plurality of segments moveably connected together. The outer electrode can be easily opened to remove or insert filter material. Air flows through the two electrodes and the filter material and is exhausted from the center of the inner electrode.