Abstract
Canada's largest fully integrated primary natural- gas processing and sulfur recovery plant is heading for physical completion by mid-summer of 1971. The Ralph M. Parsons Construction Co. of Canada Ltd., contractor for the S. Kaybob Beaverhill Lake Unit No. 3 gas-processing plant, to be operated by Chevron Standard Ltd., estimates completion by June 30. After that the $80 million complex will have tests and running in time. With any reasonable luck, it should be fully on stream by late summer. Preliminary construction on the 200-acre site started in Jan. 1969 with clearing and contouring of the main plant and sulfur storage sites. Initial rough grading started in the early summer, after spring breakup was over. Delivery of most of the big items was made by rail because the local secondary roads were inadequate for them. Concrete has been a large item. The contractor has its own batch plant on the site for the estimated 28,000 cu yd which will be needed for the whole job. Dominating the construction site from the start has been the high sulfur plant stack, first of the major items to be finished. It will serve to dispose of effluent from the largest sulfur recovery unit
More>>
Citation Formats
None.
Kabob report. Pt. 3. Chevron plant largest in Canada.
Canada: N. p.,
1971.
Web.
None.
Kabob report. Pt. 3. Chevron plant largest in Canada.
Canada.
None.
1971.
"Kabob report. Pt. 3. Chevron plant largest in Canada."
Canada.
@misc{etde_5963929,
title = {Kabob report. Pt. 3. Chevron plant largest in Canada}
author = {None}
abstractNote = {Canada's largest fully integrated primary natural- gas processing and sulfur recovery plant is heading for physical completion by mid-summer of 1971. The Ralph M. Parsons Construction Co. of Canada Ltd., contractor for the S. Kaybob Beaverhill Lake Unit No. 3 gas-processing plant, to be operated by Chevron Standard Ltd., estimates completion by June 30. After that the $80 million complex will have tests and running in time. With any reasonable luck, it should be fully on stream by late summer. Preliminary construction on the 200-acre site started in Jan. 1969 with clearing and contouring of the main plant and sulfur storage sites. Initial rough grading started in the early summer, after spring breakup was over. Delivery of most of the big items was made by rail because the local secondary roads were inadequate for them. Concrete has been a large item. The contractor has its own batch plant on the site for the estimated 28,000 cu yd which will be needed for the whole job. Dominating the construction site from the start has been the high sulfur plant stack, first of the major items to be finished. It will serve to dispose of effluent from the largest sulfur recovery unit in Canada. It is 465 ft high, one of the largest in Alberta, and a significant contribution to pollution control and environmental protection.}
journal = []
volume = {21:48}
journal type = {AC}
place = {Canada}
year = {1971}
month = {Jan}
}
title = {Kabob report. Pt. 3. Chevron plant largest in Canada}
author = {None}
abstractNote = {Canada's largest fully integrated primary natural- gas processing and sulfur recovery plant is heading for physical completion by mid-summer of 1971. The Ralph M. Parsons Construction Co. of Canada Ltd., contractor for the S. Kaybob Beaverhill Lake Unit No. 3 gas-processing plant, to be operated by Chevron Standard Ltd., estimates completion by June 30. After that the $80 million complex will have tests and running in time. With any reasonable luck, it should be fully on stream by late summer. Preliminary construction on the 200-acre site started in Jan. 1969 with clearing and contouring of the main plant and sulfur storage sites. Initial rough grading started in the early summer, after spring breakup was over. Delivery of most of the big items was made by rail because the local secondary roads were inadequate for them. Concrete has been a large item. The contractor has its own batch plant on the site for the estimated 28,000 cu yd which will be needed for the whole job. Dominating the construction site from the start has been the high sulfur plant stack, first of the major items to be finished. It will serve to dispose of effluent from the largest sulfur recovery unit in Canada. It is 465 ft high, one of the largest in Alberta, and a significant contribution to pollution control and environmental protection.}
journal = []
volume = {21:48}
journal type = {AC}
place = {Canada}
year = {1971}
month = {Jan}
}