Replacement of the old hydropower plant Ruppoldingen by new construction: More power in harmony with nature. Ersatz des alten Kraftwerkes Ruppoldingen durch Neubau: Mehr Strom im Einklang mit der Natur

Abstract

The Aare-Tessin AG fuer Elektrizitaet (Atel) at Olten intend to construct a new run-of-river power plant at Ruppoldingen above the Aareblick restaurant. The new plant will replace the present hydroelectric power plant, which is new nearly 100 years old and whose operating permit will run out in 1994. The article gives an outline of the power plant project. The new plant will have three times the power of the old plant; protection of nature will be ensured by a number of measures.(orig.).
Authors:
Aemmer, F; Zimmermann, C; Inderbitzin, R [1] 
  1. Atel, Aare-Tessin AG fuer Elektrizitaet, Olten (Switzerland)
Publication Date:
Feb 21, 1992
Product Type:
Journal Article
Reference Number:
CHF-92-0F0928; EDB-92-101664
Resource Relation:
Journal Name: Bulletin des Schweizerischen Elektrotechnischen Vereins (und) des Verbandes Schweizerischer Elektrizitaetswerke; (Switzerland); Journal Volume: 83:4
Subject:
13 HYDRO ENERGY; HYDROELECTRIC POWER PLANTS; CONSTRUCTION; DAMS; ENVIRONMENT; FLOW RATE; PLANNING; POWER GENERATION; RIVERS; SCHEDULES; SWITZERLAND; DEVELOPED COUNTRIES; EUROPE; POWER PLANTS; STREAMS; SURFACE WATERS; 130300* - Hydro Energy- Plant Design & Operation; 130700 - Hydro Energy- Power-Conversion Systems
OSTI ID:
5248270
Country of Origin:
Switzerland
Language:
German
Other Identifying Numbers:
Journal ID: CODEN: BEVED
Submitting Site:
HEDB
Size:
Pages: 27-33
Announcement Date:
Jul 15, 1992

Citation Formats

Aemmer, F, Zimmermann, C, and Inderbitzin, R. Replacement of the old hydropower plant Ruppoldingen by new construction: More power in harmony with nature. Ersatz des alten Kraftwerkes Ruppoldingen durch Neubau: Mehr Strom im Einklang mit der Natur. Switzerland: N. p., 1992. Web.
Aemmer, F, Zimmermann, C, & Inderbitzin, R. Replacement of the old hydropower plant Ruppoldingen by new construction: More power in harmony with nature. Ersatz des alten Kraftwerkes Ruppoldingen durch Neubau: Mehr Strom im Einklang mit der Natur. Switzerland.
Aemmer, F, Zimmermann, C, and Inderbitzin, R. 1992. "Replacement of the old hydropower plant Ruppoldingen by new construction: More power in harmony with nature. Ersatz des alten Kraftwerkes Ruppoldingen durch Neubau: Mehr Strom im Einklang mit der Natur." Switzerland.
@misc{etde_5248270,
title = {Replacement of the old hydropower plant Ruppoldingen by new construction: More power in harmony with nature. Ersatz des alten Kraftwerkes Ruppoldingen durch Neubau: Mehr Strom im Einklang mit der Natur}
author = {Aemmer, F, Zimmermann, C, and Inderbitzin, R}
abstractNote = {The Aare-Tessin AG fuer Elektrizitaet (Atel) at Olten intend to construct a new run-of-river power plant at Ruppoldingen above the Aareblick restaurant. The new plant will replace the present hydroelectric power plant, which is new nearly 100 years old and whose operating permit will run out in 1994. The article gives an outline of the power plant project. The new plant will have three times the power of the old plant; protection of nature will be ensured by a number of measures.(orig.).}
journal = []
volume = {83:4}
journal type = {AC}
place = {Switzerland}
year = {1992}
month = {Feb}
}