Planning and realization of river diversions for the construction of reservoirs and river power stations; Planung und Ausfuehrung von Flussumleitungen im Talsperren- und Flusskraftwerksbau

Miscellaneous:

Abstract

River diversions are necessary measures in reservoir and river power station construction in order to be able to construct the planned buildings in dry building ground. These diversion measures are only temporary as only in the construction phase of the retaining works the flow is led through the site. As in the recent past large hydraulic engineering plants have reached new dimensions also river diversions have gained importance with regard to the flow to be controlled. With this work the author wants to contribute to an improvement in river diversion with regard to safety, economy and environmental compatibility. (orig.) [Deutsch] Flussumleitungen sind im Talsperren- und Flusskraftwerksbau notwendige Massnahmen, um die projektierten Bauwerke in trockenen Baugruben errichten zu koennen. Diese Umleitungsmassnahmen besitzen einen temporaeren Charakter, da mit ihrer Hilfe der Abfluss ausschliesslich in der Bauphase des Sperrprojekts durch die Baustelle gewaehrleistet wird. Da in juengster Vergangenheit die wasserbaulichen Grossanlagen in neue Dimensionen vorgestossen sind, haben auch die Flussumleitungen hinsichtlich der Abfluesse, die es zu beherrschen gilt, an Bedeutung gewonnen. Mit der vorliegenden Arbeit moechte ich einen Beitrag leisten zur Verbesserung von Flussumleitungen im Hinblick auf Sicherheit, Wirtschaftlichkeit und Umweltvertraeglichkeit. (orig.)
Authors:
Publication Date:
Mar 19, 1992
Product Type:
Miscellaneous
Reference Number:
SCA: 130300; 130700; PA: DE-95:0G9626; EDB-95:069181; SN: 95001388993
Resource Relation:
Other Information: DN: Dissertation also published in: Mitteilungen des Instituts fuer Wasserbau und Wasserwirtschaft (TU Aachen), v. 84; TH: Diss. (Dr.-Ing.); PBD: 19 Mar 1992
Subject:
13 HYDRO ENERGY; HYDROELECTRIC POWER; RIVERS; DAMS; PENSTOCKS; HYDROLOGY; PLANNING; SCHEDULES; EROSION; FLOW RATE; SPILLWAYS
OSTI ID:
44185
Research Organizations:
Technische Hochschule Aachen (Germany). Fakultaet fuer Bauingenieur- und Vermessungswesen
Country of Origin:
Germany
Language:
German
Other Identifying Numbers:
TRN: DE95G9626
Availability:
Available from TIB Hannover: RA 3265(84)
Submitting Site:
DE
Size:
205 p.
Announcement Date:

Miscellaneous:

Citation Formats

Patt, M. Planning and realization of river diversions for the construction of reservoirs and river power stations; Planung und Ausfuehrung von Flussumleitungen im Talsperren- und Flusskraftwerksbau. Germany: N. p., 1992. Web.
Patt, M. Planning and realization of river diversions for the construction of reservoirs and river power stations; Planung und Ausfuehrung von Flussumleitungen im Talsperren- und Flusskraftwerksbau. Germany.
Patt, M. 1992. "Planning and realization of river diversions for the construction of reservoirs and river power stations; Planung und Ausfuehrung von Flussumleitungen im Talsperren- und Flusskraftwerksbau." Germany.
@misc{etde_44185,
title = {Planning and realization of river diversions for the construction of reservoirs and river power stations; Planung und Ausfuehrung von Flussumleitungen im Talsperren- und Flusskraftwerksbau}
author = {Patt, M}
abstractNote = {River diversions are necessary measures in reservoir and river power station construction in order to be able to construct the planned buildings in dry building ground. These diversion measures are only temporary as only in the construction phase of the retaining works the flow is led through the site. As in the recent past large hydraulic engineering plants have reached new dimensions also river diversions have gained importance with regard to the flow to be controlled. With this work the author wants to contribute to an improvement in river diversion with regard to safety, economy and environmental compatibility. (orig.) [Deutsch] Flussumleitungen sind im Talsperren- und Flusskraftwerksbau notwendige Massnahmen, um die projektierten Bauwerke in trockenen Baugruben errichten zu koennen. Diese Umleitungsmassnahmen besitzen einen temporaeren Charakter, da mit ihrer Hilfe der Abfluss ausschliesslich in der Bauphase des Sperrprojekts durch die Baustelle gewaehrleistet wird. Da in juengster Vergangenheit die wasserbaulichen Grossanlagen in neue Dimensionen vorgestossen sind, haben auch die Flussumleitungen hinsichtlich der Abfluesse, die es zu beherrschen gilt, an Bedeutung gewonnen. Mit der vorliegenden Arbeit moechte ich einen Beitrag leisten zur Verbesserung von Flussumleitungen im Hinblick auf Sicherheit, Wirtschaftlichkeit und Umweltvertraeglichkeit. (orig.)}
place = {Germany}
year = {1992}
month = {Mar}
}