You need JavaScript to view this

An integrated automatic system for the eddy-current testing of the steam generator tubes

Abstract

This research project was focused on automation of steam generator tubes inspection for nuclear power plants. ECT (Eddy Current Testing) inspection process in nuclear power plants is classified into 3 subprocesses such as signal acquisition process, signal evaluation process, and inspection planning and data management process. Having been automated individually, these processes were effectively integrated into an automatic inspection system, which was implemented in HP workstation with expert system developed (author). 25 refs., 80 figs.
Authors:
Woo, Hee Gon; Choi, Seong Su [1] 
  1. Korea Electric Power Corp. (KEPCO), Taejon (Korea, Republic of). Research Center
Publication Date:
Dec 31, 1995
Product Type:
Technical Report
Report Number:
KRC-93A-J02
Reference Number:
SCA: 990200; PA: KR-96:000361; EDB-96:124729; NTS-97:004284; SN: 96001629589
Resource Relation:
Other Information: PBD: 1995
Subject:
99 MATHEMATICS, COMPUTERS, INFORMATION SCIENCE, MANAGEMENT, LAW, MISCELLANEOUS; STEAM GENERATORS; NONDESTRUCTIVE TESTING; EDDY CURRENT TESTING; AUTOMATION
OSTI ID:
267503
Research Organizations:
Korea Electric Power Corp. (KEPCO), Taejon (Korea, Republic of). Research Center
Country of Origin:
Korea, Republic of
Language:
Korean
Other Identifying Numbers:
Other: ON: DE96768137; TRN: KR9600361
Availability:
OSTI as DE96768137
Submitting Site:
KR
Size:
152 p.
Announcement Date:
Aug 23, 1996

Citation Formats

Woo, Hee Gon, and Choi, Seong Su. An integrated automatic system for the eddy-current testing of the steam generator tubes. Korea, Republic of: N. p., 1995. Web.
Woo, Hee Gon, & Choi, Seong Su. An integrated automatic system for the eddy-current testing of the steam generator tubes. Korea, Republic of.
Woo, Hee Gon, and Choi, Seong Su. 1995. "An integrated automatic system for the eddy-current testing of the steam generator tubes." Korea, Republic of.
@misc{etde_267503,
title = {An integrated automatic system for the eddy-current testing of the steam generator tubes}
author = {Woo, Hee Gon, and Choi, Seong Su}
abstractNote = {This research project was focused on automation of steam generator tubes inspection for nuclear power plants. ECT (Eddy Current Testing) inspection process in nuclear power plants is classified into 3 subprocesses such as signal acquisition process, signal evaluation process, and inspection planning and data management process. Having been automated individually, these processes were effectively integrated into an automatic inspection system, which was implemented in HP workstation with expert system developed (author). 25 refs., 80 figs.}
place = {Korea, Republic of}
year = {1995}
month = {Dec}
}