Abstract
In the RA reactor action plan for 1977 it is foreseen that the reactor would be operated for 181 days, mostly at nominal power of 6.5 MW. It is planned to produce 28236 MWh in total. Five reactor core exchanges (refuelling) are planned. The plan includes time for repair of components as well as for cooling. [Serbo-Croat] Plan rada reaktora RA predvidja rad tokom 181 dana, vecim delom na nominalnoj snazi od 6,5 MW tokom 1977. godine. Planirano je da ukupni rad iznosi 28236 MWh. Planom je predvidjeno i pet izmena goriva kao i vreme potrebno za remont opreme i hladjenje.
Citation Formats
None.
RA reactor action plan for 1977 - Annex VI; Prilog VI - Plan rada reaktora RA za 1977. godinu.
Serbia and Montenegro: N. p.,
1976.
Web.
None.
RA reactor action plan for 1977 - Annex VI; Prilog VI - Plan rada reaktora RA za 1977. godinu.
Serbia and Montenegro.
None.
1976.
"RA reactor action plan for 1977 - Annex VI; Prilog VI - Plan rada reaktora RA za 1977. godinu."
Serbia and Montenegro.
@misc{etde_20734975,
title = {RA reactor action plan for 1977 - Annex VI; Prilog VI - Plan rada reaktora RA za 1977. godinu}
author = {None}
abstractNote = {In the RA reactor action plan for 1977 it is foreseen that the reactor would be operated for 181 days, mostly at nominal power of 6.5 MW. It is planned to produce 28236 MWh in total. Five reactor core exchanges (refuelling) are planned. The plan includes time for repair of components as well as for cooling. [Serbo-Croat] Plan rada reaktora RA predvidja rad tokom 181 dana, vecim delom na nominalnoj snazi od 6,5 MW tokom 1977. godine. Planirano je da ukupni rad iznosi 28236 MWh. Planom je predvidjeno i pet izmena goriva kao i vreme potrebno za remont opreme i hladjenje.}
place = {Serbia and Montenegro}
year = {1976}
month = {Dec}
}
title = {RA reactor action plan for 1977 - Annex VI; Prilog VI - Plan rada reaktora RA za 1977. godinu}
author = {None}
abstractNote = {In the RA reactor action plan for 1977 it is foreseen that the reactor would be operated for 181 days, mostly at nominal power of 6.5 MW. It is planned to produce 28236 MWh in total. Five reactor core exchanges (refuelling) are planned. The plan includes time for repair of components as well as for cooling. [Serbo-Croat] Plan rada reaktora RA predvidja rad tokom 181 dana, vecim delom na nominalnoj snazi od 6,5 MW tokom 1977. godine. Planirano je da ukupni rad iznosi 28236 MWh. Planom je predvidjeno i pet izmena goriva kao i vreme potrebno za remont opreme i hladjenje.}
place = {Serbia and Montenegro}
year = {1976}
month = {Dec}
}