RA reactor operation and maintenance, Annual report 1974; Pogon i odrzavanje reaktora RA - Izvestaj o radu u 1974. godini

Abstract

During 1974, RA reactor was operated at nominal power for 194 days and 13 days at lower power levels. The total production was 30711 MWh which is 2.4% higher than planned. Practically there were no discrepancies from the plan. The reactor was used for irradiation and experiments according to the demand of 437 users. This report contains detailed data about reactor power and experiments performed in 1974. Total number of afety shutdowns was 11, of which 8 were caused by power cuts, and 3 due to human error. Maximum individual personnel exposure dose was 50% of the maximum permissible dose. There were no accidents during this year. Decontamination of surfaces was less than during previous years. About 805 m{sup 2} of surfaces and 178 objects were decontaminated. It was concluded that the successful operation in 1974 has a special significance taking into account the financial problems. [Serbo-Croat] Reaktor RA je u 1974. godini radio na nominalnoj snazi 194 dana i 13 dana na manjim snagama. Ukupni rad iznosio je 30711 MWh odnosno 1,4% vise od planiranog. Prakticno nije bilo odstupanja od plana rada. Reaktor je koriscen za ozracivanja i eksperimente za 437 korisnika. Ovaj izvestaj sadrzi detaljne podatke o radu  More>>
Authors:
Milosevic, D et al [1] 
  1. Institute of Nuclear Sciences Boris Kidric, Vinca, Beograd (Serbia and Montenegro)
Publication Date:
Dec 15, 1974
Product Type:
Miscellaneous
Report Number:
INIS-CS-0059; RA-214/R3/P3/35
Resource Relation:
Other Information: 30 tabs
Subject:
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS; DECONTAMINATION; ELECTRON TUBES; ELECTRONIC EQUIPMENT; EXCURSIONS; FINANCING; R-A REACTOR; RADIATION PROTECTION; REACTOR COMPONENTS; REACTOR INSTRUMENTATION; REACTOR KINETICS; REACTOR MAINTENANCE; REACTOR OPERATION; REACTOR SAFETY; REACTOR SHUTDOWN; SCRAM
OSTI ID:
20733528
Research Organizations:
Institute of Nuclear Sciences Boris Kidric, Vinca, Beograd (Serbia and Montenegro)
Country of Origin:
Serbia and Montenegro
Language:
English
Other Identifying Numbers:
TRN: CS06RA362043601
Availability:
Available from INIS in electronic form; Also available from the Institute of nuclear sciences Vinca
Submitting Site:
INIS
Size:
57 pages
Announcement Date:
Jun 19, 2006

Citation Formats

Milosevic, D et al. RA reactor operation and maintenance, Annual report 1974; Pogon i odrzavanje reaktora RA - Izvestaj o radu u 1974. godini. Serbia and Montenegro: N. p., 1974. Web.
Milosevic, D et al. RA reactor operation and maintenance, Annual report 1974; Pogon i odrzavanje reaktora RA - Izvestaj o radu u 1974. godini. Serbia and Montenegro.
Milosevic, D et al. 1974. "RA reactor operation and maintenance, Annual report 1974; Pogon i odrzavanje reaktora RA - Izvestaj o radu u 1974. godini." Serbia and Montenegro.
@misc{etde_20733528,
title = {RA reactor operation and maintenance, Annual report 1974; Pogon i odrzavanje reaktora RA - Izvestaj o radu u 1974. godini}
author = {Milosevic, D et al}
abstractNote = {During 1974, RA reactor was operated at nominal power for 194 days and 13 days at lower power levels. The total production was 30711 MWh which is 2.4% higher than planned. Practically there were no discrepancies from the plan. The reactor was used for irradiation and experiments according to the demand of 437 users. This report contains detailed data about reactor power and experiments performed in 1974. Total number of afety shutdowns was 11, of which 8 were caused by power cuts, and 3 due to human error. Maximum individual personnel exposure dose was 50% of the maximum permissible dose. There were no accidents during this year. Decontamination of surfaces was less than during previous years. About 805 m{sup 2} of surfaces and 178 objects were decontaminated. It was concluded that the successful operation in 1974 has a special significance taking into account the financial problems. [Serbo-Croat] Reaktor RA je u 1974. godini radio na nominalnoj snazi 194 dana i 13 dana na manjim snagama. Ukupni rad iznosio je 30711 MWh odnosno 1,4% vise od planiranog. Prakticno nije bilo odstupanja od plana rada. Reaktor je koriscen za ozracivanja i eksperimente za 437 korisnika. Ovaj izvestaj sadrzi detaljne podatke o radu i eksperimentima koji su obavljani. U toku godine bilo je 11 sigurnosnih zaustavljanja, od cega 8 zbog elektricnog napona i 3 usled greske osoblja. Ukupna doza ozracivanja ljudstva bila je manja nego prethodnih godina. Maksimalna doza po oveku bila je 50% manja od maksimalno dozvoljene doze. Nije bilo ni jednog akcidenta. Dekontaminirano je znatno manje povrsina nego ranijih godina, i sakupljeno manje otpada nego prethodnih godina, dok tecnih efluenata nije bilo. Zakljuceno je da uspesan rad reaktora u 1974. godini ima poseban znacaj kada se imaju na umu problemi finansiranja reaktora.}
place = {Serbia and Montenegro}
year = {1974}
month = {Dec}
}