The contract for the replacement of two steam generators at NPP Krsko was awarded in February 1998 to the Consortium SIEMENS AG FRAMATOME S.A.. The time frame for the replacement outage was scheduled from April to June 2000. The replacement itself started with the plant shut down on 15{sup th} of April 2000 and the plant was back on line on 15{sup th} of June, so that after an intensive engineering period of more than two years the plant was off line only 62 days, as scheduled. This document deals with the various aspects of the replacement phase itself and the techniques used. During the last years conference the engineering and licensing phase of the project have been presented. (author)
Holz, R;
Stach, U;
[1]
Gloaguen, C
[2]
- Siemens AG, Erlangen, Offenbach (Germany)
- Framatome, Paris (France)
Citation Formats
Holz, R, Stach, U, and Gloaguen, C.
Modernization of the Nuclear Power Plant Krsko with new steam generators.
Slovenia: N. p.,
2000.
Web.
Holz, R, Stach, U, & Gloaguen, C.
Modernization of the Nuclear Power Plant Krsko with new steam generators.
Slovenia.
Holz, R, Stach, U, and Gloaguen, C.
2000.
"Modernization of the Nuclear Power Plant Krsko with new steam generators."
Slovenia.
@misc{etde_20413847,
title = {Modernization of the Nuclear Power Plant Krsko with new steam generators}
author = {Holz, R, Stach, U, and Gloaguen, C}
abstractNote = {The contract for the replacement of two steam generators at NPP Krsko was awarded in February 1998 to the Consortium SIEMENS AG FRAMATOME S.A.. The time frame for the replacement outage was scheduled from April to June 2000. The replacement itself started with the plant shut down on 15{sup th} of April 2000 and the plant was back on line on 15{sup th} of June, so that after an intensive engineering period of more than two years the plant was off line only 62 days, as scheduled. This document deals with the various aspects of the replacement phase itself and the techniques used. During the last years conference the engineering and licensing phase of the project have been presented. (author)}
place = {Slovenia}
year = {2000}
month = {Jul}
}
title = {Modernization of the Nuclear Power Plant Krsko with new steam generators}
author = {Holz, R, Stach, U, and Gloaguen, C}
abstractNote = {The contract for the replacement of two steam generators at NPP Krsko was awarded in February 1998 to the Consortium SIEMENS AG FRAMATOME S.A.. The time frame for the replacement outage was scheduled from April to June 2000. The replacement itself started with the plant shut down on 15{sup th} of April 2000 and the plant was back on line on 15{sup th} of June, so that after an intensive engineering period of more than two years the plant was off line only 62 days, as scheduled. This document deals with the various aspects of the replacement phase itself and the techniques used. During the last years conference the engineering and licensing phase of the project have been presented. (author)}
place = {Slovenia}
year = {2000}
month = {Jul}
}