Fiscal 1996 achievement report. Coal liquefaction technology development - Bituminous coal liquefaction technology development - Study for supporting pilot plant - Study using 1t/d PSU (Study of operation using PSU); 1996 nendo seika hokokusho. Sekitan ekika gijutsu kaihatsu - Rekiseitan ekika gijutsu no kaihatsu - Pilot plant no shien kenkyu - 1t/d process support unit (PSU) ni yoru kenkyu (PSU ni yoru unten kenkyu)

Abstract

The operation of a 1t/d PSU (process support unit) was studied for the NEDOL coal liquefaction process. In the modification of facilities, detailed designs were prepared for product oil reforming facilities and some equipment and devices were procured. In addition, the 3rd liquefaction reactor cone section and the neutron attenuation-aided measuring device were refurbished. In the injection of coal, a 62-day and 23-day slurry injection operations were accomplished using Tanito Harum coal, when the impact imposed on the yield of the product, etc., by the change of liquefaction catalysts and by gas phase hydrogen concentration enriching conditions was investigated, and the unit was examined for operationality. During a 42-day operation for maintenance, the unit was operated using only the slurry heater for the investigation of the initial reaction in liquefaction, and studies were conducted about the heater exit temperature, G/L (gas-liquid ratio), and the effect to ensue from the use of a different solvent. In the effort to develop and evaluate new materials, implantation tests were conducted for metallic materials and the 3rd liquefaction reactor was subjected to a non-destructive inspection. Wastewater from the process was examined for quality, and environment-related measurements were performed for the atmosphere. (NEDO)
Publication Date:
Mar 01, 1997
Product Type:
Technical Report
Report Number:
JP-NEDO-010019610
Resource Relation:
Other Information: PBD: Mar 1997
Subject:
01 COAL, LIGNITE, AND PEAT; COAL LIQUEFACTION; BITUMINOUS COAL; PILOT PLANTS; OPERATION; COAL LIQUIDS; REFORMER PROCESSES; MEASURING INSTRUMENTS; SLURRIES; CATALYSTS; CHEMICAL REACTION YIELD; NONDESTRUCTIVE TESTING; WASTE WATER; AIR POLLUTION MONITORING
OSTI ID:
20270987
Research Organizations:
New Energy and Industrial Technology Development Organization, Tokyo (Japan)
Country of Origin:
Japan
Language:
Japanese
Other Identifying Numbers:
TRN: JN0240015
Availability:
Available to ETDE participating countries only(see www.etde.org); commercial reproduction prohibited; OSTI as DE20270987
Submitting Site:
NEDO
Size:
498 pages
Announcement Date:
Apr 17, 2003

Citation Formats

None. Fiscal 1996 achievement report. Coal liquefaction technology development - Bituminous coal liquefaction technology development - Study for supporting pilot plant - Study using 1t/d PSU (Study of operation using PSU); 1996 nendo seika hokokusho. Sekitan ekika gijutsu kaihatsu - Rekiseitan ekika gijutsu no kaihatsu - Pilot plant no shien kenkyu - 1t/d process support unit (PSU) ni yoru kenkyu (PSU ni yoru unten kenkyu). Japan: N. p., 1997. Web.
None. Fiscal 1996 achievement report. Coal liquefaction technology development - Bituminous coal liquefaction technology development - Study for supporting pilot plant - Study using 1t/d PSU (Study of operation using PSU); 1996 nendo seika hokokusho. Sekitan ekika gijutsu kaihatsu - Rekiseitan ekika gijutsu no kaihatsu - Pilot plant no shien kenkyu - 1t/d process support unit (PSU) ni yoru kenkyu (PSU ni yoru unten kenkyu). Japan.
None. 1997. "Fiscal 1996 achievement report. Coal liquefaction technology development - Bituminous coal liquefaction technology development - Study for supporting pilot plant - Study using 1t/d PSU (Study of operation using PSU); 1996 nendo seika hokokusho. Sekitan ekika gijutsu kaihatsu - Rekiseitan ekika gijutsu no kaihatsu - Pilot plant no shien kenkyu - 1t/d process support unit (PSU) ni yoru kenkyu (PSU ni yoru unten kenkyu)." Japan.
@misc{etde_20270987,
title = {Fiscal 1996 achievement report. Coal liquefaction technology development - Bituminous coal liquefaction technology development - Study for supporting pilot plant - Study using 1t/d PSU (Study of operation using PSU); 1996 nendo seika hokokusho. Sekitan ekika gijutsu kaihatsu - Rekiseitan ekika gijutsu no kaihatsu - Pilot plant no shien kenkyu - 1t/d process support unit (PSU) ni yoru kenkyu (PSU ni yoru unten kenkyu)}
author = {None}
abstractNote = {The operation of a 1t/d PSU (process support unit) was studied for the NEDOL coal liquefaction process. In the modification of facilities, detailed designs were prepared for product oil reforming facilities and some equipment and devices were procured. In addition, the 3rd liquefaction reactor cone section and the neutron attenuation-aided measuring device were refurbished. In the injection of coal, a 62-day and 23-day slurry injection operations were accomplished using Tanito Harum coal, when the impact imposed on the yield of the product, etc., by the change of liquefaction catalysts and by gas phase hydrogen concentration enriching conditions was investigated, and the unit was examined for operationality. During a 42-day operation for maintenance, the unit was operated using only the slurry heater for the investigation of the initial reaction in liquefaction, and studies were conducted about the heater exit temperature, G/L (gas-liquid ratio), and the effect to ensue from the use of a different solvent. In the effort to develop and evaluate new materials, implantation tests were conducted for metallic materials and the 3rd liquefaction reactor was subjected to a non-destructive inspection. Wastewater from the process was examined for quality, and environment-related measurements were performed for the atmosphere. (NEDO)}
place = {Japan}
year = {1997}
month = {Mar}
}