You need JavaScript to view this

Achievement report for fiscal 1981 on Sunshine Program-assisted project. Part 1. Research and development of coal liquefaction technology (Development of direct coal hydroliquefaction plant; development of 2.4T/day-capable research plant); 1981 nendo sekitan ekika gijutsu no kenkyu kaihatsu / chokusetsu suiten ekika plant no kaihatsu seika hokokusho. 1. 2.4t/nichi jikken plant no kaihatsu

Abstract

The above-named plant is constructed, and studies are conducted on its operation. Before the construction of this 2.4T/day-capable research plant, its details were designed in fiscal 1979 when the plan placed the plant at the Chiba establishment of the Mitsui Engineering and Shipbuilding Co., Ltd. The plan was altered in July of fiscal 1980 for the plant to be built at the Keihin steelworks site of the NKK Corporation, and then partial modification was implemented for the basic and detailed designs of the plant for the second year running. Furthermore, a review was made so that the results of the element studies that followed the designing of the details would be embodied, and the changes were reflected on orders placed for equipment and construction work. These processes culminated in the 2.4T/day-capable research plant, now complete and subjected to inspections by the relevant Government offices. In a study of the operation of the plant, an operating procedure is worked out, and water-handling tests are conducted for each of the stages of operation. The plant will be subjected to a full test operation, improved as required, studied for proper operation, and will undergo additional construction work as required, all these in preparation  More>>
Publication Date:
Mar 01, 1982
Product Type:
Technical Report
Report Number:
JP-NEDO-010017628
Resource Relation:
Other Information: PBD: Mar 1982
Subject:
01 COAL, LIGNITE, AND PEAT; SUNSHINE PROJECT; COAL LIQUEFACTION; HYDROGENATION; PILOT PLANTS; CONSTRUCTION; OPERATION; DESIGN; INSPECTION
OSTI ID:
20123679
Research Organizations:
New Energy and Industrial Technology Development Organization, Tokyo (Japan)
Country of Origin:
Japan
Language:
Japanese
Other Identifying Numbers:
TRN: JN0040791
Availability:
Available to ETDE participating countries only(see www.etde.org); commercial reproduction prohibited; OSTI as DE20123679
Submitting Site:
NEDO
Size:
[300] pages
Announcement Date:
May 24, 2002

Citation Formats

None. Achievement report for fiscal 1981 on Sunshine Program-assisted project. Part 1. Research and development of coal liquefaction technology (Development of direct coal hydroliquefaction plant; development of 2.4T/day-capable research plant); 1981 nendo sekitan ekika gijutsu no kenkyu kaihatsu / chokusetsu suiten ekika plant no kaihatsu seika hokokusho. 1. 2.4t/nichi jikken plant no kaihatsu. Japan: N. p., 1982. Web.
None. Achievement report for fiscal 1981 on Sunshine Program-assisted project. Part 1. Research and development of coal liquefaction technology (Development of direct coal hydroliquefaction plant; development of 2.4T/day-capable research plant); 1981 nendo sekitan ekika gijutsu no kenkyu kaihatsu / chokusetsu suiten ekika plant no kaihatsu seika hokokusho. 1. 2.4t/nichi jikken plant no kaihatsu. Japan.
None. 1982. "Achievement report for fiscal 1981 on Sunshine Program-assisted project. Part 1. Research and development of coal liquefaction technology (Development of direct coal hydroliquefaction plant; development of 2.4T/day-capable research plant); 1981 nendo sekitan ekika gijutsu no kenkyu kaihatsu / chokusetsu suiten ekika plant no kaihatsu seika hokokusho. 1. 2.4t/nichi jikken plant no kaihatsu." Japan.
@misc{etde_20123679,
title = {Achievement report for fiscal 1981 on Sunshine Program-assisted project. Part 1. Research and development of coal liquefaction technology (Development of direct coal hydroliquefaction plant; development of 2.4T/day-capable research plant); 1981 nendo sekitan ekika gijutsu no kenkyu kaihatsu / chokusetsu suiten ekika plant no kaihatsu seika hokokusho. 1. 2.4t/nichi jikken plant no kaihatsu}
author = {None}
abstractNote = {The above-named plant is constructed, and studies are conducted on its operation. Before the construction of this 2.4T/day-capable research plant, its details were designed in fiscal 1979 when the plan placed the plant at the Chiba establishment of the Mitsui Engineering and Shipbuilding Co., Ltd. The plan was altered in July of fiscal 1980 for the plant to be built at the Keihin steelworks site of the NKK Corporation, and then partial modification was implemented for the basic and detailed designs of the plant for the second year running. Furthermore, a review was made so that the results of the element studies that followed the designing of the details would be embodied, and the changes were reflected on orders placed for equipment and construction work. These processes culminated in the 2.4T/day-capable research plant, now complete and subjected to inspections by the relevant Government offices. In a study of the operation of the plant, an operating procedure is worked out, and water-handling tests are conducted for each of the stages of operation. The plant will be subjected to a full test operation, improved as required, studied for proper operation, and will undergo additional construction work as required, all these in preparation for a continuous operation in the future. (NEDO)}
place = {Japan}
year = {1982}
month = {Mar}
}