Measurement of the power transient and valve closing time, for the zone control system, during a programmed shutdown in August 1989 and its relation with the class IV partial loss event occurred on 27/12/88 in CNE (Embalse nuclear power plant); Medicion del transitorio de potencia y del tiempo de cierre de valvulas del sistema de control zonal durante la parada programada de agosto de 1989 y relacion con el evento de perdida parcial de clase IV ocurrido el 27/12/88 en CNE (Central Nuclear Embalse)

Abstract

A description is made of a number of measurements performed during the programmed shutdown on Embalse nuclear power plant (CNE) (August 1989) to validate the existance of a reactivity insertion owing to the emptying of the liquid zone control system. In the event occurred on 27/12/88 when there was a partial loss Cl IV. Once the existance of this contribution was confirmed, the pertinent corrective measures were taken and the test was repeated to verify the effectiveness of the latter. The temporal evolution of a number of neutronic variables and process variables of the liquid zone system were stored in an IBM-PC XT equipped with analog-to-digital converters, for later analysis. (Author). [Espanol] En el presente trabajo se describen una serie de mediciones realizadas durante la parada programada de la Central Nuclear Embalse (CNE) (agosto 1989) para validar la existencia de una insercion de reactividad debida al vaciamiento del sistema de control zonal liquido durante el evento ocurrido el 27-12-88 de perdida parcial de Cl IV. Una vez confirmada la existencia de esta contribucion se procedio a tomar acciones correctivas correspondientes y repetir la prueba en cuestion para determinar la efectividad de las mismas. Por medio de una PC-IBM tipo XT  More>>
Publication Date:
Dec 31, 1990
Product Type:
Conference
Report Number:
INIS-mf-13243; CONF-9010363-
Reference Number:
SCA: 210400; PA: AIX-23:054402; EDB-92:107198; SN: 92000774994
Resource Relation:
Conference: 18. annual meeting of the Argentine Association of Nuclear Technology (AANT),18. Reunion anual de la Asociacion Argentina de Tecnologia Nuclear,Buenos Aires (Argentina),22-26 Oct 1990; Other Information: DN: Pre-conference paper.; PBD: 1990
Subject:
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS; REACTOR SHUTDOWN; REACTIVITY INSERTIONS; TRANSIENTS; ARGENTINA; CANDU TYPE REACTORS; CLOSURES; HELIUM COOLED REACTORS; LOSS OF COOLANT; NEUTRON DETECTION; PUMPS; REACTOR CONTROL SYSTEMS; VALVES; 210400; POWER REACTORS, NONBREEDING, OTHERWISE MODERATED OR UNMODERATED
OSTI ID:
10156635
Research Organizations:
Comision Nacional de Energia Atomica, Embalse (Argentina). Central Nuclear en Embalse
Country of Origin:
Argentina
Language:
Spanish
Other Identifying Numbers:
Other: ON: DE92636594; TRN: AR9200059054402
Availability:
OSTI; NTIS (US Sales Only); INIS
Submitting Site:
INIS
Size:
10 p.
Announcement Date:
Jul 06, 2005

Citation Formats

Paz, A.O. de, Moreno, C A, and Vinez, J C. Measurement of the power transient and valve closing time, for the zone control system, during a programmed shutdown in August 1989 and its relation with the class IV partial loss event occurred on 27/12/88 in CNE (Embalse nuclear power plant); Medicion del transitorio de potencia y del tiempo de cierre de valvulas del sistema de control zonal durante la parada programada de agosto de 1989 y relacion con el evento de perdida parcial de clase IV ocurrido el 27/12/88 en CNE (Central Nuclear Embalse). Argentina: N. p., 1990. Web.
Paz, A.O. de, Moreno, C A, & Vinez, J C. Measurement of the power transient and valve closing time, for the zone control system, during a programmed shutdown in August 1989 and its relation with the class IV partial loss event occurred on 27/12/88 in CNE (Embalse nuclear power plant); Medicion del transitorio de potencia y del tiempo de cierre de valvulas del sistema de control zonal durante la parada programada de agosto de 1989 y relacion con el evento de perdida parcial de clase IV ocurrido el 27/12/88 en CNE (Central Nuclear Embalse). Argentina.
Paz, A.O. de, Moreno, C A, and Vinez, J C. 1990. "Measurement of the power transient and valve closing time, for the zone control system, during a programmed shutdown in August 1989 and its relation with the class IV partial loss event occurred on 27/12/88 in CNE (Embalse nuclear power plant); Medicion del transitorio de potencia y del tiempo de cierre de valvulas del sistema de control zonal durante la parada programada de agosto de 1989 y relacion con el evento de perdida parcial de clase IV ocurrido el 27/12/88 en CNE (Central Nuclear Embalse)." Argentina.
@misc{etde_10156635,
title = {Measurement of the power transient and valve closing time, for the zone control system, during a programmed shutdown in August 1989 and its relation with the class IV partial loss event occurred on 27/12/88 in CNE (Embalse nuclear power plant); Medicion del transitorio de potencia y del tiempo de cierre de valvulas del sistema de control zonal durante la parada programada de agosto de 1989 y relacion con el evento de perdida parcial de clase IV ocurrido el 27/12/88 en CNE (Central Nuclear Embalse)}
author = {Paz, A.O. de, Moreno, C A, and Vinez, J C}
abstractNote = {A description is made of a number of measurements performed during the programmed shutdown on Embalse nuclear power plant (CNE) (August 1989) to validate the existance of a reactivity insertion owing to the emptying of the liquid zone control system. In the event occurred on 27/12/88 when there was a partial loss Cl IV. Once the existance of this contribution was confirmed, the pertinent corrective measures were taken and the test was repeated to verify the effectiveness of the latter. The temporal evolution of a number of neutronic variables and process variables of the liquid zone system were stored in an IBM-PC XT equipped with analog-to-digital converters, for later analysis. (Author). [Espanol] En el presente trabajo se describen una serie de mediciones realizadas durante la parada programada de la Central Nuclear Embalse (CNE) (agosto 1989) para validar la existencia de una insercion de reactividad debida al vaciamiento del sistema de control zonal liquido durante el evento ocurrido el 27-12-88 de perdida parcial de Cl IV. Una vez confirmada la existencia de esta contribucion se procedio a tomar acciones correctivas correspondientes y repetir la prueba en cuestion para determinar la efectividad de las mismas. Por medio de una PC-IBM tipo XT con conversores analogico-digitales se almaceno la evolucion temporal de una serie de variables neutronicas y de proceso del sistema de zonas liquidas, para posteriormente proceder a su analisis. (Autor).}
place = {Argentina}
year = {1990}
month = {Dec}
}