Abstract
In accordance with the provisions laid in the decision of the Ministry for Trade and Industry Imatran Voima Oy has revised the decommissioning plan for the Loviisa power plant, and submitted it to the authorities for review in December 1993. The plan outlines the technical measures needed to dismantle the radioactive parts of the Loviisa power plant, explains how the resulting waste will be packed and disposed of, and estimates how many people will be needed for the decommissioning waste will be. A general timetable and a cost estimate have also been drawn up on the basis of a detailed working plan. In this report the plan has been revised for cost estimate, activity inventory of the decommissioning waste and radiation dose caused by dismantling work. (orig.). (11 refs., 10 figs., 8 tabs.).
Citation Formats
Haerkoenen, H, Maekinen, P, and Palmu, J.
Decommissioning of the Loviisa power plant; Loviisan voimalaitoksen kaeytoestaepoisto.
Finland: N. p.,
1993.
Web.
Haerkoenen, H, Maekinen, P, & Palmu, J.
Decommissioning of the Loviisa power plant; Loviisan voimalaitoksen kaeytoestaepoisto.
Finland.
Haerkoenen, H, Maekinen, P, and Palmu, J.
1993.
"Decommissioning of the Loviisa power plant; Loviisan voimalaitoksen kaeytoestaepoisto."
Finland.
@misc{etde_10152758,
title = {Decommissioning of the Loviisa power plant; Loviisan voimalaitoksen kaeytoestaepoisto}
author = {Haerkoenen, H, Maekinen, P, and Palmu, J}
abstractNote = {In accordance with the provisions laid in the decision of the Ministry for Trade and Industry Imatran Voima Oy has revised the decommissioning plan for the Loviisa power plant, and submitted it to the authorities for review in December 1993. The plan outlines the technical measures needed to dismantle the radioactive parts of the Loviisa power plant, explains how the resulting waste will be packed and disposed of, and estimates how many people will be needed for the decommissioning waste will be. A general timetable and a cost estimate have also been drawn up on the basis of a detailed working plan. In this report the plan has been revised for cost estimate, activity inventory of the decommissioning waste and radiation dose caused by dismantling work. (orig.). (11 refs., 10 figs., 8 tabs.).}
place = {Finland}
year = {1993}
month = {Dec}
}
title = {Decommissioning of the Loviisa power plant; Loviisan voimalaitoksen kaeytoestaepoisto}
author = {Haerkoenen, H, Maekinen, P, and Palmu, J}
abstractNote = {In accordance with the provisions laid in the decision of the Ministry for Trade and Industry Imatran Voima Oy has revised the decommissioning plan for the Loviisa power plant, and submitted it to the authorities for review in December 1993. The plan outlines the technical measures needed to dismantle the radioactive parts of the Loviisa power plant, explains how the resulting waste will be packed and disposed of, and estimates how many people will be needed for the decommissioning waste will be. A general timetable and a cost estimate have also been drawn up on the basis of a detailed working plan. In this report the plan has been revised for cost estimate, activity inventory of the decommissioning waste and radiation dose caused by dismantling work. (orig.). (11 refs., 10 figs., 8 tabs.).}
place = {Finland}
year = {1993}
month = {Dec}
}