On-line partial discharge measurement on stator winding of large synchronous hydro-generators: Main criteria applied in management of such measurements and presentation of results

Abstract

The paper reports on work in progress at ENEL (Italian Electricity Board) the concerning on-line measurement of partial discharges in the stator windings of large synchronous hydro-generators. It is a follow-up to a paper, presented at the 1990 IEEE Symposium on Electrical Insulation, which summarized the main results of a previous work-step mainly aimed at characterizing the signals related to the partial discharges to be investigated, and designing the necessary coupling system. To date, some twenty ENEL synchronous hydro-generators have been equipped with permanent couplers, and a campaign of on-line PD measurements is being carried out. This paper describes the procedure followed in performing the above-mentioned measurement and provides an outline of the data acquisition system currently employed. Finally, the basic criteria applied in processing the data acquired and presenting the measurement results are considered, and an example of application is briefly discussed.
Publication Date:
Dec 31, 1992
Product Type:
Technical Report
Report Number:
ETDE-IT-93-36
Reference Number:
SCA: 130700; 130800; PA: ITA-93:000084; SN: 93000947306
Resource Relation:
Other Information: PBD: 1992
Subject:
13 HYDRO ENERGY; STATORS; ELECTRIC DISCHARGES; ELECTRICAL INSULATION; HYDROELECTRIC POWER PLANTS; ELECTRIC GENERATORS; DATA ACQUISITION SYSTEMS; EQUIPMENT PROTECTION DEVICES; DATA PROCESSING; MEASURING METHODS; ON-LINE CONTROL SYSTEMS; EXPERIMENTAL DATA; 130700; 130800; POWER-CONVERSION SYSTEMS; HEALTH AND SAFETY
OSTI ID:
10128902
Research Organizations:
Ente Nazionale per l`Energia Elettrica, Milan (Italy). Centro di Ricerca Elettrica; Ente Nazionale per l`Energia Elettrica, Rome (Italy)
Country of Origin:
Italy
Language:
English
Other Identifying Numbers:
Other: ON: DE93769320; TRN: 93:000084
Availability:
OSTI; NTIS (US Sales Only)
Submitting Site:
ITA
Size:
5 p.
Announcement Date:
Jul 04, 2005

Citation Formats

Colombo, E, Tontini, G, and Filie, A. On-line partial discharge measurement on stator winding of large synchronous hydro-generators: Main criteria applied in management of such measurements and presentation of results. Italy: N. p., 1992. Web.
Colombo, E, Tontini, G, & Filie, A. On-line partial discharge measurement on stator winding of large synchronous hydro-generators: Main criteria applied in management of such measurements and presentation of results. Italy.
Colombo, E, Tontini, G, and Filie, A. 1992. "On-line partial discharge measurement on stator winding of large synchronous hydro-generators: Main criteria applied in management of such measurements and presentation of results." Italy.
@misc{etde_10128902,
title = {On-line partial discharge measurement on stator winding of large synchronous hydro-generators: Main criteria applied in management of such measurements and presentation of results}
author = {Colombo, E, Tontini, G, and Filie, A}
abstractNote = {The paper reports on work in progress at ENEL (Italian Electricity Board) the concerning on-line measurement of partial discharges in the stator windings of large synchronous hydro-generators. It is a follow-up to a paper, presented at the 1990 IEEE Symposium on Electrical Insulation, which summarized the main results of a previous work-step mainly aimed at characterizing the signals related to the partial discharges to be investigated, and designing the necessary coupling system. To date, some twenty ENEL synchronous hydro-generators have been equipped with permanent couplers, and a campaign of on-line PD measurements is being carried out. This paper describes the procedure followed in performing the above-mentioned measurement and provides an outline of the data acquisition system currently employed. Finally, the basic criteria applied in processing the data acquired and presenting the measurement results are considered, and an example of application is briefly discussed.}
place = {Italy}
year = {1992}
month = {Dec}
}