AECB staff review of Bruce NGS `A` operation for the year 1988

Abstract

AECB project staff believes that overall performance of the station in 1988 was generally satisfactory and better than in 1987. However, this assessment is not supported by some of the key performance indicators, although the indicators in areas where AECB staff had specific concerns do support it. For example, the percentage of reported significant events attributable to human error, the number of operating memos beyond the review date, scheduled emergency drills completed, the number of completed reactor trips all show a significant improvement over the 1987 value. In addition, AECB staff has been encouraged by the licensee`s implementation of effective review processes for operator and maintenance call-ups, routines and deficiencies, and the establishment of supervisor inspection tours and operator rounds programs. Nevertheless, it is the opinion of AECB staff that to achieve standards of operation which would be considered fully satisfactory, the backlog of maintenance work must be reduced, the quality of work performed in the plant improved, and assurance provided that the required quality standards are being consistently achieved and maintained.
Publication Date:
May 01, 1989
Product Type:
Technical Report
Report Number:
INFO-0326
Reference Number:
SCA: 210400; PA: AIX-23:026241; SN: 92000685908
Resource Relation:
Other Information: PBD: May 1989
Subject:
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS; BRUCE-1 REACTOR; REACTOR OPERATION; CANADIAN AECB; SAFETY; ACCIDENTS; BRUCE-2 REACTOR; BRUCE-3 REACTOR; BRUCE-4 REACTOR; EDUCATION; ENVIRONMENTAL IMPACTS; LICENSING; MANAGEMENT; MODIFICATIONS; PERFORMANCE; QUALITY ASSURANCE; RADIATION PROTECTION; REACTOR MAINTENANCE; REACTOR PROTECTION SYSTEMS; REACTOR SAFETY; SECURITY; 210400; POWER REACTORS, NONBREEDING, OTHERWISE MODERATED OR UNMODERATED
OSTI ID:
10128302
Research Organizations:
Atomic Energy Control Board, Ottawa, ON (Canada)
Country of Origin:
Canada
Language:
English
Other Identifying Numbers:
Other: ON: DE92620849; TRN: CA9200012026241
Availability:
OSTI; NTIS (US Sales Only); INIS
Submitting Site:
INIS
Size:
29 p.
Announcement Date:
Jul 04, 2005

Citation Formats

None. AECB staff review of Bruce NGS `A` operation for the year 1988. Canada: N. p., 1989. Web.
None. AECB staff review of Bruce NGS `A` operation for the year 1988. Canada.
None. 1989. "AECB staff review of Bruce NGS `A` operation for the year 1988." Canada.
@misc{etde_10128302,
title = {AECB staff review of Bruce NGS `A` operation for the year 1988}
author = {None}
abstractNote = {AECB project staff believes that overall performance of the station in 1988 was generally satisfactory and better than in 1987. However, this assessment is not supported by some of the key performance indicators, although the indicators in areas where AECB staff had specific concerns do support it. For example, the percentage of reported significant events attributable to human error, the number of operating memos beyond the review date, scheduled emergency drills completed, the number of completed reactor trips all show a significant improvement over the 1987 value. In addition, AECB staff has been encouraged by the licensee`s implementation of effective review processes for operator and maintenance call-ups, routines and deficiencies, and the establishment of supervisor inspection tours and operator rounds programs. Nevertheless, it is the opinion of AECB staff that to achieve standards of operation which would be considered fully satisfactory, the backlog of maintenance work must be reduced, the quality of work performed in the plant improved, and assurance provided that the required quality standards are being consistently achieved and maintained.}
place = {Canada}
year = {1989}
month = {May}
}