Technical preparation of a 300 kWel biomass gasification plant. Report for the project: Simplification, system and operation optimization of staged gasification unit for CHP production (the Castor unit in Graested); Teknisk forberedelse af 300 kWel bioforgasningsanlaeg. En Delrapport til projektet: Forenkling, system- og driftsoptimering af trinopdelt forgasningsanlaeg til kraftvarmeproduktion (Castor anlaegget i Graested)

Abstract

In 2003/04 BioSynergi Proces ApS built a complete approx. 450 kWth Open Core staged gasification unit as a development / demonstration plant. The plant uses wet wood chips as fuel for generating electricity and heat. The facility, known as the Castor plant, is connected to the heat supply network in Graested District Heating. The daily operation is handled by BioSynergi Process. The cogeneration system, that the Castor plant represents, is the basis for this completed project. For technical preparation of the planned future up scaling of the cogeneration system, a test of the function of the gas generator core (reactor core) was performed in this sub-project. It is the central component of the total cogeneration system, and it is also the one who has the greatest influence on the overall gasification process. The experiments have demonstrated that the stage gasification principle, which is in operation at the Castor plant, is also possible to have in operation with the desired process steps in the tested reactor core with four times more capacity. Finalization of the total gas generator in the range of 300 kWel is now being developed in a new project. The simplified experiments, that were possible to perform with  More>>
Publication Date:
Sep 15, 2009
Product Type:
Technical Report
Report Number:
NEI-DK-5430
Resource Relation:
Other Information: PSO-2007
Subject:
09 BIOMASS FUELS; 20 FOSSIL-FUELED POWER PLANTS; BIOMASS; WOOD; DUAL-PURPOSE POWER PLANTS; COGENERATION; GASIFICATION; DEMONSTRATION PLANTS; GAS GENERATORS; POWER RANGE 100-1000 KW
OSTI ID:
1000219
Research Organizations:
BioSynergi Proces ApS, Hoersholm (Denmark)
Country of Origin:
Denmark
Language:
Danish
Other Identifying Numbers:
Other: Contract FORSKEL-7191; TRN: DK1001184
Availability:
Also available at http://www.risoe.dtu.dk/rispubl/NEI/NEI-DK-5430.pdf; OSTI as DE01000219
Submitting Site:
DK
Size:
25 p. pages
Announcement Date:
Dec 21, 2010

Citation Formats

Houmann Jakobsen, H. Technical preparation of a 300 kWel biomass gasification plant. Report for the project: Simplification, system and operation optimization of staged gasification unit for CHP production (the Castor unit in Graested); Teknisk forberedelse af 300 kWel bioforgasningsanlaeg. En Delrapport til projektet: Forenkling, system- og driftsoptimering af trinopdelt forgasningsanlaeg til kraftvarmeproduktion (Castor anlaegget i Graested). Denmark: N. p., 2009. Web.
Houmann Jakobsen, H. Technical preparation of a 300 kWel biomass gasification plant. Report for the project: Simplification, system and operation optimization of staged gasification unit for CHP production (the Castor unit in Graested); Teknisk forberedelse af 300 kWel bioforgasningsanlaeg. En Delrapport til projektet: Forenkling, system- og driftsoptimering af trinopdelt forgasningsanlaeg til kraftvarmeproduktion (Castor anlaegget i Graested). Denmark.
Houmann Jakobsen, H. 2009. "Technical preparation of a 300 kWel biomass gasification plant. Report for the project: Simplification, system and operation optimization of staged gasification unit for CHP production (the Castor unit in Graested); Teknisk forberedelse af 300 kWel bioforgasningsanlaeg. En Delrapport til projektet: Forenkling, system- og driftsoptimering af trinopdelt forgasningsanlaeg til kraftvarmeproduktion (Castor anlaegget i Graested)." Denmark.
@misc{etde_1000219,
title = {Technical preparation of a 300 kWel biomass gasification plant. Report for the project: Simplification, system and operation optimization of staged gasification unit for CHP production (the Castor unit in Graested); Teknisk forberedelse af 300 kWel bioforgasningsanlaeg. En Delrapport til projektet: Forenkling, system- og driftsoptimering af trinopdelt forgasningsanlaeg til kraftvarmeproduktion (Castor anlaegget i Graested)}
author = {Houmann Jakobsen, H}
abstractNote = {In 2003/04 BioSynergi Proces ApS built a complete approx. 450 kWth Open Core staged gasification unit as a development / demonstration plant. The plant uses wet wood chips as fuel for generating electricity and heat. The facility, known as the Castor plant, is connected to the heat supply network in Graested District Heating. The daily operation is handled by BioSynergi Process. The cogeneration system, that the Castor plant represents, is the basis for this completed project. For technical preparation of the planned future up scaling of the cogeneration system, a test of the function of the gas generator core (reactor core) was performed in this sub-project. It is the central component of the total cogeneration system, and it is also the one who has the greatest influence on the overall gasification process. The experiments have demonstrated that the stage gasification principle, which is in operation at the Castor plant, is also possible to have in operation with the desired process steps in the tested reactor core with four times more capacity. Finalization of the total gas generator in the range of 300 kWel is now being developed in a new project. The simplified experiments, that were possible to perform with the outdoor setup of the reactor core, were, however, not suited to qualitative assessments of the gasification process. (ln)}
place = {Denmark}
year = {2009}
month = {Sep}
}