Title: Sandy River Delta Habitat Restoration : Annual Report, January 2008 - March 2009.

Abstract

During the period 2008-2009, there were 2 contracts with BPA. One (38539) was dealing with the restoration work for 2007 and the other (26198) was an extension on the 2006 contract including the NEPA for Dam removal on the old channel of the Sandy River. For contract 38539, the Sandy River Delta Habitat Restoration project continued its focus on riparian hardwood reforestation with less emphasis on wetlands restoration. Emphasis was placed on Sundial Island again due to the potential removal of the dike and the loss of access in the near future. AshCreek Forest Management was able to leverage additional funding from grants to help finance the restoration effort; this required a mid year revision of work funded by BPA. The revised work not only continued the maintenance of restored hardwood forests, but was aimed to commence the restoration of the Columbia River Banks, an area all along the Columbia River. This would be the final restoration for Sundial Island. The grant funding would help achieve this. Thus by 2011, all major work will have been completed on Sundial Island and the need for access with vehicles would no longer be required. The restored forests continued to show excellent growthmore » and development towards true riparian gallery forests. Final inter-planting was commenced, and will continue through 2010 before the area is considered fully restored. No new wetland work was completed. The wetlands were filled by pumping in early summer to augment the water levels but due to better rainfall, no new fuel was required to augment existing. Monitoring results continued to show very good growth of the trees and the restoration at large was performing beyond expectations. Weed problems continue to be the most difficult issue. The $100,000 from BPA planned for forest restoration in 2008, was augmented by $25,000 from USFS, $120,000 from OR150 grant, $18,000 from LCREP, and the COE continued to add $250,000 for their portion. Summary of the use of these funds are displayed in Table 1 (page 5). Work on the restoration of the original Sandy River channel (dam removal, contract 26198) continued slowly. The draft EA was completed and sent out for review. The COE has decided to finish the NEPA with the intent to complete the project.« less

Authors:
 [1]
  1. USDA Forest Service, Columbia River Gorge National Scenic Area
Publication Date:
Research Org.:
Bonneville Power Administration (BPA), Portland, OR (United States)
Sponsoring Org.:
USDOE
OSTI Identifier:
966367
Report Number(s):
P113369
R&D Project: 1999-025-00; TRN: US200921%%422
DOE Contract Number:  
38539
Resource Type:
Technical Report
Resource Relation:
Related Information: document dated July 2009
Country of Publication:
United States
Language:
English
Subject:
13 HYDRO ENERGY; COLUMBIA RIVER; FORESTS; HABITAT; MAINTENANCE; MANAGEMENT; MONITORING; PUMPING; REMOVAL; RIVER DELTAS; RIVERS; TREES; WATER; WEEDS; WETLANDS

Citation Formats

Dobson, Robin. Sandy River Delta Habitat Restoration : Annual Report, January 2008 - March 2009.. United States: N. p., 2009. Web. doi:10.2172/966367.
Dobson, Robin. Sandy River Delta Habitat Restoration : Annual Report, January 2008 - March 2009.. United States. doi:10.2172/966367.
Dobson, Robin. Fri . "Sandy River Delta Habitat Restoration : Annual Report, January 2008 - March 2009.". United States. doi:10.2172/966367. https://www.osti.gov/servlets/purl/966367.
@article{osti_966367,
title = {Sandy River Delta Habitat Restoration : Annual Report, January 2008 - March 2009.},
author = {Dobson, Robin},
abstractNote = {During the period 2008-2009, there were 2 contracts with BPA. One (38539) was dealing with the restoration work for 2007 and the other (26198) was an extension on the 2006 contract including the NEPA for Dam removal on the old channel of the Sandy River. For contract 38539, the Sandy River Delta Habitat Restoration project continued its focus on riparian hardwood reforestation with less emphasis on wetlands restoration. Emphasis was placed on Sundial Island again due to the potential removal of the dike and the loss of access in the near future. AshCreek Forest Management was able to leverage additional funding from grants to help finance the restoration effort; this required a mid year revision of work funded by BPA. The revised work not only continued the maintenance of restored hardwood forests, but was aimed to commence the restoration of the Columbia River Banks, an area all along the Columbia River. This would be the final restoration for Sundial Island. The grant funding would help achieve this. Thus by 2011, all major work will have been completed on Sundial Island and the need for access with vehicles would no longer be required. The restored forests continued to show excellent growth and development towards true riparian gallery forests. Final inter-planting was commenced, and will continue through 2010 before the area is considered fully restored. No new wetland work was completed. The wetlands were filled by pumping in early summer to augment the water levels but due to better rainfall, no new fuel was required to augment existing. Monitoring results continued to show very good growth of the trees and the restoration at large was performing beyond expectations. Weed problems continue to be the most difficult issue. The $100,000 from BPA planned for forest restoration in 2008, was augmented by $25,000 from USFS, $120,000 from OR150 grant, $18,000 from LCREP, and the COE continued to add $250,000 for their portion. Summary of the use of these funds are displayed in Table 1 (page 5). Work on the restoration of the original Sandy River channel (dam removal, contract 26198) continued slowly. The draft EA was completed and sent out for review. The COE has decided to finish the NEPA with the intent to complete the project.},
doi = {10.2172/966367},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2009},
month = {9}
}

Technical Report: