Title: LCLS Undulator Tuning And Fiducialization

Conference ·
OSTI ID:918956

The LCLS project at SLAC requires 40 undulators: 33 in the beam line, 6 spares, and one reference undulator. A new facility was constructed at SLAC for tuning and fiducializing the undulators. The throughput of the facility must be approximately one undulator per week. The undulator tuning has been partially automated. Fiducialization techniques have been devised. The new facility, the tuning techniques, and the fiducialization techniques will be discussed.

Research Organization:
SLAC National Accelerator Lab., Menlo Park, CA (United States)
Sponsoring Organization:
USDOE
DOE Contract Number:
AC02-76SF00515
OSTI ID:
918956
Report Number(s):
SLAC-PUB-12947; TRN: US0806266
Resource Relation:
Conference: Prepared for Particle Accelerator Conference (PAC 07), Albuquerque, New Mexico, 25-29 Jun 2007
Country of Publication:
United States
Language:
English

Similar Records

LCLS Undulator Test Plan
Technical Report · Wed Nov 24 00:00:00 EST 2010 · OSTI ID:918956

Algorithms to Automate LCLS Undulator Tuning
Technical Report · Fri Dec 03 00:00:00 EST 2010 · OSTI ID:918956

LCLS Undulator Quadrupole Fiducialization Plan
Technical Report · Wed Nov 24 00:00:00 EST 2010 · OSTI ID:918956