Title: Achieve Continuous Injection of Solid Fuels into Advanced Combustion System Pressures

Abstract

The overall objective of this project is the development of a mechanical rotary-disk feeder, known as the Stamet Posimetric High Pressure Solids Feeder System, to demonstrate feeding of dry granular coal continuously and controllably into pressurized environments of up to 70 kg/cm2 (1,000 psi). This is the Phase III of the ongoing program. Earlier Phases 1 and II successfully demonstrated feeding into pressures up to 35 kg/cm{sup 2} (500 psi). The final report for those phases was submitted in April 2005. Based on the previous work done in Phases I & II using Powder River Basin coal provided by the PSDF facility in Wilsonville, AL, a Phase III feeder system was designed and built to accomplish the target of feeding the coal into a pressure of 70 kg/cm2 (1,000 psi) and to be capable of feed rates of up to 550 kilograms (1,200lbs) per hour. The drive motor system from Phase II was retained for use on Phase III since projected performance calculations indicated it should be capable of driving the Phase III pump to the target levels. The pump & motor system was installed in a custom built test rig comprising an inlet vessel containing an active live-wall hoppermore » mounted on weigh cells in a support frame, transition into the pump inlet, transition from pump outlet and a receiver vessel containing a receiver drum supported on weigh cells. All pressure containment on the rig was rated to105 kg/cm{sup 2} (1,500psi) to accommodate the final pressure requirement of a proposed Phase IV of the program. A screw conveyor and batch hopper were added to transfer coal at atmospheric pressure from the shop floor up into the test rig to enable continuous feeding up to the capacity of the receiving vessel. Control & monitoring systems were up-rated from the Phase II system to cover the additional features incorporated in the Phase III rig, and provide closer control and expanded monitoring of the entire system. A program of testing and modification was carried out in Stamet's facility in CA, culminating in the first successful feeding of coal into the Phase III target of 70 kg/cm{sup 2} (1,000 psi) gas pressure in March 2007. Subsequently, repeated runs at pressure were achieved, and comparison of the data with Phase II results when adjusted for scale differences showed further power reductions of 40% had been achieved from the final Phase II pressure runs. The general design layout of a commercial-scale unit was conducted, and preliminary cost estimates made.« less

Authors:
;
Publication Date:
Research Org.:
Stamet Incorporated
Sponsoring Org.:
USDOE
OSTI Identifier:
909121
DOE Contract Number:
FC26-02NT41439
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
01 COAL, LIGNITE, AND PEAT; ATMOSPHERIC PRESSURE; COAL; COMBUSTION; FEEDING; POWDER RIVER BASIN; SOLID FUELS

Citation Formats

Derek L. Aldred, and Timothy Saunders. Achieve Continuous Injection of Solid Fuels into Advanced Combustion System Pressures. United States: N. p., 2007. Web. doi:10.2172/909121.
Derek L. Aldred, & Timothy Saunders. Achieve Continuous Injection of Solid Fuels into Advanced Combustion System Pressures. United States. doi:10.2172/909121.
Derek L. Aldred, and Timothy Saunders. Sat . "Achieve Continuous Injection of Solid Fuels into Advanced Combustion System Pressures". United States. doi:10.2172/909121. https://www.osti.gov/servlets/purl/909121.
@article{osti_909121,
title = {Achieve Continuous Injection of Solid Fuels into Advanced Combustion System Pressures},
author = {Derek L. Aldred and Timothy Saunders},
abstractNote = {The overall objective of this project is the development of a mechanical rotary-disk feeder, known as the Stamet Posimetric High Pressure Solids Feeder System, to demonstrate feeding of dry granular coal continuously and controllably into pressurized environments of up to 70 kg/cm2 (1,000 psi). This is the Phase III of the ongoing program. Earlier Phases 1 and II successfully demonstrated feeding into pressures up to 35 kg/cm{sup 2} (500 psi). The final report for those phases was submitted in April 2005. Based on the previous work done in Phases I & II using Powder River Basin coal provided by the PSDF facility in Wilsonville, AL, a Phase III feeder system was designed and built to accomplish the target of feeding the coal into a pressure of 70 kg/cm2 (1,000 psi) and to be capable of feed rates of up to 550 kilograms (1,200lbs) per hour. The drive motor system from Phase II was retained for use on Phase III since projected performance calculations indicated it should be capable of driving the Phase III pump to the target levels. The pump & motor system was installed in a custom built test rig comprising an inlet vessel containing an active live-wall hopper mounted on weigh cells in a support frame, transition into the pump inlet, transition from pump outlet and a receiver vessel containing a receiver drum supported on weigh cells. All pressure containment on the rig was rated to105 kg/cm{sup 2} (1,500psi) to accommodate the final pressure requirement of a proposed Phase IV of the program. A screw conveyor and batch hopper were added to transfer coal at atmospheric pressure from the shop floor up into the test rig to enable continuous feeding up to the capacity of the receiving vessel. Control & monitoring systems were up-rated from the Phase II system to cover the additional features incorporated in the Phase III rig, and provide closer control and expanded monitoring of the entire system. A program of testing and modification was carried out in Stamet's facility in CA, culminating in the first successful feeding of coal into the Phase III target of 70 kg/cm{sup 2} (1,000 psi) gas pressure in March 2007. Subsequently, repeated runs at pressure were achieved, and comparison of the data with Phase II results when adjusted for scale differences showed further power reductions of 40% had been achieved from the final Phase II pressure runs. The general design layout of a commercial-scale unit was conducted, and preliminary cost estimates made.},
doi = {10.2172/909121},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Sat Mar 31 00:00:00 EDT 2007},
month = {Sat Mar 31 00:00:00 EDT 2007}
}

Technical Report:

Save / Share:
  • The overall objective of this project is the development of a mechanical rotary-disk feeder, known as the Stamet Posimetric High Pressure Solids Feeder System, to feed dry granular coal continuously and controllably into pressurized environments of up to 35 kg/cm{sup 2} (500 psi). This was to be accomplished in two phases. The first task was to review materials handling experience in pressurized operations as it related to the target pressures for this project, and review existing coal preparation processes and specifications currently used in advanced combustion systems. Samples of existing fuel materials were obtained and tested to evaluate flow, sealingmore » and friction properties. This provided input data for use in the design of the Stamet Feeders for the project, and ensured that the material specification used met the requirements of advanced combustion & gasification systems. Ultimately, Powder River Basin coal provided by the PSDF facility in Wilsonville, AL was used as the basis for the feeder design and test program. Based on the material property information, a Phase 1 feeder system was designed and built to accomplish feeding the coal to an intermediate pressure up to 21 kg/cm{sup 2} (300 psi) at feed rates of approximately 100 kilograms (220lbs) per hour. The pump & motor system was installed in a custom built test rig comprising an inlet vessel containing an active live-wall hopper mounted in a support frame, transition into the pump inlet, transition from pump outlet and a receiver vessel containing a receiver drum supported on weigh cells. All pressure containment on the rig was rated for the final pressure requirement of 35 kg/cm{sup 2} (500psi). A program of testing and modification was carried out in Stamet's facility in CA, culminating in successful feeding of coal into the Phase 1 target of 21 kg/cm{sup 2} (300psi) gas pressure in December 2003. Further testing was carried out at CQ Inc's facility in PA, providing longer run times and experience of handling and feeding the coal in winter conditions. Based on the data developed through the testing of the Phase I unit, a Phase II system was designed for feeding coal into pressures of up to 35 kg/cm{sup 2} (500 psi). A further program of testing and modification was then carried out in Stamet's facility, with the target pressure being achieved in January 2005. Repeated runs at pressure were achieved, and optimization of the machine resulted in power reductions of 60% from the first successful pressure runs. General design layout of a commercial-scale unit was conducted, and preliminary cost estimates for a commercial unit obtained.« less
  • The project is addressing barriers to or opportunities for increasing distributed generation (DG)/combined heat and power (CHP) use in industrial applications using renewable/opportunity fuels. This project brings together novel gas quality sensor (GQS) technology with engine management for opportunity fuels such as landfill gas, digester gas and coal bed methane. By providing the capability for near real-time monitoring of the composition of these opportunity fuels, the GQS output can be used to improve the performance, increase efficiency, raise system reliability, and provide improved project economics and reduced emissions for engines used in distributed generation and combined heat and power.
  • US Department of Energy research programs aimed at conserving petroleum, natural gas and coal through the development of more efficient combustion technologies, the substitution of synthetic and refuse-derived fuels for fossil fuels, and the improvement of vehicular engines are discussed in terms of their current status, costs, and anticipated benefits. (LCL)