Title: CONTAMINATED PROCESS EQUIPMENT REMOVAL FOR THE D&D OF THE 232-Z CONTAMINATED WASTE RECOVERY PROCESS FACILITY AT THE PLUTONIUM FINISHING PLANT (PFP)

Conference ·
OSTI ID:899765

This paper describes the unique challenges encountered and subsequent resolutions to accomplish the deactivation and decontamination of a plutonium ash contaminated building. The 232-Z Contaminated Waste Recovery Process Facility at the Plutonium Finishing Plant was used to recover plutonium from process wastes such as rags, gloves, containers and other items by incinerating the items and dissolving the resulting ash. The incineration process resulted in a light-weight plutonium ash residue that was highly mobile in air. This light-weight ash coated the incinerator's process equipment, which included gloveboxes, blowers, filters, furnaces, ducts, and filter boxes. Significant airborne contamination (over 1 million derived air concentration hours [DAC]) was found in the scrubber cell of the facility. Over 1300 grams of plutonium held up in the process equipment and attached to the walls had to be removed, packaged and disposed. This ash had to be removed before demolition of the building could take place.

Research Organization:
Hanford Site (HNF), Richland, WA (United States)
Sponsoring Organization:
USDOE - Office of Environmental Management (EM)
DOE Contract Number:
DE-AC06-96RL13200
OSTI ID:
899765
Report Number(s):
HNF-32534-FP Rev 0; TRN: US0702075
Resource Relation:
Conference: 33RD ANNUAL WASTE MANAGEMENT CONFERENCE & EXHIBITION (WM07) SYMPOSIA INC 02/25/2007 THRU 03/1/2007 TUCSON ARIZONA
Country of Publication:
United States
Language:
English