Title: FACILITY DEACTIVATION AND DECOMMISSIONING AT THE SAVANNAH RIVER SITE

Abstract

In February 2002, the U.S. Department of Energy initiated actions to expedite Cleanup, focus on significant and early risk reduction, and reduce costs at the Savannah River Site (SRS). In response SRS started on a project focused on completing the decommissioning of inactive facilities in T, D, and M Areas, areas that on the perimeter of the Site, by the end of 2006. In June 2003, the Department of Energy Savannah River Operations Office (DOE-SR), the South Carolina Department of Health and Environmental Control (SCDHEC), and the Environmental Protection Agency, Region 4 (EPA-4) endorsed a Memorandum of Agreement (MOA) concerning cleanup at the Savannah River Site (SRS). The vision of the Agreement is that SRS will reduce its operations footprint to establish a buffer zone at the perimeter if the Site, while the central core area of the Site will be reserved for continuing or future long-term operations. DOE-SR, EPA-4, and SCDHEC agreed that establishing this buffer zone and appropriately sequencing environmental restoration and decommissioning activities can lead to greater efficiency and accelerate completion of entire site areas. This vision is embodied in the concept of Area Completion--which integrated operations, deactivation and decommissioning (D&D), and soils and groundwater cleanup intomore » a time-phased approach to completing all the work necessary to address the Cold War legacy. D&D addresses the ''footprint'' of the building or structure, while the soils and groundwater project addresses any environmental remediation that may be required in the underlying and surrounding soils and groundwater. Since then, {approx}250 facilities have been decommissioned at the SRS, ranging from guard stations to nuclear fuel production facilities.« less

Authors:
; ;
Publication Date:
Research Org.:
SRS
Sponsoring Org.:
USDOE
OSTI Identifier:
899036
Report Number(s):
WSRC-MS-2007-00021
TRN: US0701730
DOE Contract Number:
DE-AC09-96SR18500
Resource Type:
Conference
Resource Relation:
Conference: AMERICAN NUCLEAR SOCIETY TOPICAL MEETING - DECOMMISSIONING/DECONTAMINATION AND REUTILIZATION
Country of Publication:
United States
Language:
English
Subject:
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; BUFFERS; DEACTIVATION; DECOMMISSIONING; EFFICIENCY; NUCLEAR FUELS; PRODUCTION; SAVANNAH RIVER PLANT; SOILS; US EPA

Citation Formats

Gilmour, J, William Austin, W, and Cathy Sizemore, C. FACILITY DEACTIVATION AND DECOMMISSIONING AT THE SAVANNAH RIVER SITE. United States: N. p., 2007. Web.
Gilmour, J, William Austin, W, & Cathy Sizemore, C. FACILITY DEACTIVATION AND DECOMMISSIONING AT THE SAVANNAH RIVER SITE. United States.
Gilmour, J, William Austin, W, and Cathy Sizemore, C. Wed . "FACILITY DEACTIVATION AND DECOMMISSIONING AT THE SAVANNAH RIVER SITE". United States. doi:. https://www.osti.gov/servlets/purl/899036.
@article{osti_899036,
title = {FACILITY DEACTIVATION AND DECOMMISSIONING AT THE SAVANNAH RIVER SITE},
author = {Gilmour, J and William Austin, W and Cathy Sizemore, C},
abstractNote = {In February 2002, the U.S. Department of Energy initiated actions to expedite Cleanup, focus on significant and early risk reduction, and reduce costs at the Savannah River Site (SRS). In response SRS started on a project focused on completing the decommissioning of inactive facilities in T, D, and M Areas, areas that on the perimeter of the Site, by the end of 2006. In June 2003, the Department of Energy Savannah River Operations Office (DOE-SR), the South Carolina Department of Health and Environmental Control (SCDHEC), and the Environmental Protection Agency, Region 4 (EPA-4) endorsed a Memorandum of Agreement (MOA) concerning cleanup at the Savannah River Site (SRS). The vision of the Agreement is that SRS will reduce its operations footprint to establish a buffer zone at the perimeter if the Site, while the central core area of the Site will be reserved for continuing or future long-term operations. DOE-SR, EPA-4, and SCDHEC agreed that establishing this buffer zone and appropriately sequencing environmental restoration and decommissioning activities can lead to greater efficiency and accelerate completion of entire site areas. This vision is embodied in the concept of Area Completion--which integrated operations, deactivation and decommissioning (D&D), and soils and groundwater cleanup into a time-phased approach to completing all the work necessary to address the Cold War legacy. D&D addresses the ''footprint'' of the building or structure, while the soils and groundwater project addresses any environmental remediation that may be required in the underlying and surrounding soils and groundwater. Since then, {approx}250 facilities have been decommissioned at the SRS, ranging from guard stations to nuclear fuel production facilities.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Wed Jan 31 00:00:00 EST 2007},
month = {Wed Jan 31 00:00:00 EST 2007}
}

Conference:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that hold this conference proceeding.

Save / Share:
  • In February 2002, the U.S. Department of Energy initiated actions to expedite Cleanup, focus on significant and early risk reduction, and reduce costs at the Savannah River Site (SRS). In response SRS started on a project focused on completing the decommissioning of inactive facilities in T, D, and M Areas, areas that are on the perimeter of the Site, by the end of 2006. In June 2003, the Department of Energy Savannah River Operations Office (DOE-SR), the South Carolina Department of Health and Environmental Control (SCDHEC), and the Environmental Protection Agency, Region 4 (EPA-4) endorsed a Memorandum of Agreement (MOA)more » concerning cleanup at the Savannah River Site (SRS). The vision of the Agreement is that SRS will reduce its operations footprint to establish a buffer zone at the perimeter of the Site, while the central core area of the Site will be reserved for continuing or future long-term operations. DOE-SR, EPA-4, and SCDHEC agreed that establishing this buffer zone and appropriately sequencing environmental restoration and decommissioning activities can lead to greater efficiency and accelerate completion of entire site areas. This vision is embodied in the concept of Area Completion - which integrated operations, deactivation and decommissioning (D and D), and soils and groundwater cleanup into a time-phased approach to completing all the work necessary to address the Cold War legacy. D and D addresses the 'footprint' of the building or structure, while the soils and groundwater project addresses any environmental remediation that may be required in the underlying and surrounding soils and groundwater. Since then, {approx}250 facilities have been decommissioned at the SRS, ranging from guard stations to nuclear fuel production facilities. The efforts made up front to develop the MOA and maintain open and active involvement with the EPA and SCDHEC was instrumental to the success of the SRS D and D Project. Accelerated D and D requires innovative regulatory approaches so that time and resources are spent commensurate with the hazards of the facilities being decommissioned. The graded approach developed at SRS accomplished a balance between building hazards and the amount of regulatory and public involvement.« less
  • The R- and P-reactor vessels at the Savannah River Site (SRS) are being prepared for deactivation and decommissioning (D&D). D&D activities will consist primarily of physically isolating and stabilizing the reactor vessel by filling it with a grout material. The reactor vessels contain aluminum alloy materials, which pose a concern in that aluminum corrodes rapidly when it comes in contact with the alkaline grout. A product of the corrosion reaction is hydrogen gas and therefore potential flammability issues were assessed. A model was developed to calculate the hydrogen generation rate as the reactor is being filled with the grout material.more » Three options existed for the type of grout material for D&D of the reactor vessels. The grout formulation options included ceramicrete (pH 6-8), a calcium aluminate sulfate (CAS) based cement (pH 10), or Portland cement grout (pH 12.4). Corrosion data for aluminum in concrete were utilized as input for the model. The calculations considered such factors as the surface area of the aluminum components, the open cross-sectional area of the reactor vessel, the rate at which the grout is added to the reactor vessel, and temperature. Given the hydrogen generation rate, the hydrogen concentration in the vapor space of the reactor vessel above the grout was calculated. This concentration was compared to the lower flammability limit for hydrogen. The assessment concluded that either ceramicrete or the CAS grout may be used to safely grout the P-reactor vessel. The risk of accumulation of a flammable mixture of hydrogen between the grout-air interface and the top of the reactor is very low. Portland cement grout, on the other hand, for the same range of process parameters did not provide a margin of safety against the accumulation of flammable gas in the reactor vessel during grouting operations in the P-reactor vessel. Therefore, it was recommended that this grout not be utilized for this task. On the other hand, the R-reactor vessel contained significantly less aluminum surface area that the P-reactor vessel based on current facility process knowledge, surface observations, and drawings. Therefore, a Portland cement grout may be considered for grouting operations as well as the other grout formulations.« less
  • This paper contains a summary of the holdup and material control and accountability (MC&A) assays conducted for the determination of highly enriched uranium (HEU) in the deactivation and decommissioning (D&D) of Building 321-M at the Savannah River Site (SRS). The 321-M facility was the Reactor Fuel Fabrication Facility at SRS and was used to fabricate HEU fuel assemblies, lithium-aluminum target tubes, neptunium assemblies, and miscellaneous components for the SRS production reactors. The facility operated for more than 35 years. During this time thousands of uranium-aluminum-alloy (U-Al) production reactor fuel tubes were produced. After the facility ceased operations in 1995, allmore » of the easily accessible U-Al was removed from the building, and only residual amounts remained. The bulk of this residue was located in the equipment that generated and handled small U-Al particles and in the exhaust systems for this equipment (e.g., Chip compactor, casting furnaces, log saw, lathes A & B, cyclone separator, Freon{trademark} cart, riser crusher, ...etc). The D&D project is likely to represent an important example for D&D activities across SRS and across the Department of Energy weapons complex. The Savannah River National Laboratory was tasked to conduct holdup assays to quantify the amount of HEU on all components removed from the facility prior to placing in solid waste containers. The U-235 holdup in any single component of process equipment must not exceed 50 g in order to meet the container limit. This limit was imposed to meet criticality requirements of the low level solid waste storage vaults. Thus the holdup measurements were used as guidance to determine if further decontamination of equipment was needed to ensure that the quantity of U-235 did not exceed the 50 g limit and to ensure that the waste met the Waste Acceptance Criteria (WAC) of the solid waste storage vaults. Since HEU is an accountable nuclear material, the holdup assays and assays of recovered residue were also important for material control and accountability purposes. In summary, the results of the holdup assays were essential for determining compliance with the Waste Acceptance Criteria, Material Control & Accountability, and to ensure that administrative criticality safety controls were not exceeded. This paper discusses the {gamma}-ray assay measurements conducted and the modeling of the acquired data to obtain measured holdup in process equipment, exhaust components, and fixed geometry scrap cans. It also presents development work required to model new acquisition configurations and to adapt available instrumentation to perform the assays.« less
  • This paper contains a summary of the holdup and material control and accountability assays conducted for the determination of highly enriched uranium in the deactivation and decommissioning of Building 321 -M at the Savannah River Site. The facility was the Reactor Fuel Fabrication Facility at SRS and assemblies and miscellaneous components for the SRS production reactors. The facility operated for 25 years. During this time thousands of uranium-aluminum-alloy production reactor fuel tubes were produced. After the facility ceased operations in 1995, all of the easily accessible U-Al was removed from the building, and only residual amounts remained. The D andmore » D project is likely to represent an important example for D and D activities across SRS and across the Department of Energy weapons complex.« less
  • Building 247-F at SRS was a roughly 110,000 ft{sup 2} two-story facility designed and constructed during the height of the cold war naval buildup to provide additional naval nuclear fuel manufacturing capacity in early 1980s. The building layout is shown in Fig. 1. A photograph of the facility is shown in Fig. 2. The manufacturing process employed a wide variety of acids, bases, and other hazardous materials. As the cold war wound down, the need for naval fuel declined. Consequently, the facility was shut down and underwent initial deactivation. All process systems were flushed with water and drained using themore » existing process drain valves. However, since these drains were not always installed at the lowest point in piping and equipment systems, a significant volume of liquid remained after initial deactivation was completed in 1990. At that time, a non-destructive assay of the process area identified approximately 17 (+/- 100%) kg of uranium held up in equipment and piping.« less