Title: Basic Data Report for Well Plugging and Abandonment and Reconfiguration Activities for Fiscal Year 2005

Abstract

The FY 2005 program was initiated on March 31, 2005, and concluded on July 16, 2005. The FY 2005 program initially included 25 wells requiring workover (P&A, Magenta reconfiguration, cleaning and keeping). During the process, the U.S. Bureau of Land Management (BLM) requested transfer of two wells (H-7c and H-8c) to their ownership for future livestock watering. These wells were transferred to the BLM through execution of Form wr-03, Declaration of Owner of Underground Water Rights, between the New Mexico Office of the State Engineer (NMOSE), the BLM, and the DOE Carlsbad Field Office (CBFO). One well (H-2b2) was cleaned and retained as a Culebra monitor well for continued use. One well (H-3d) was converted to a shallow well to monitor the formational contact between the Dewey Lake Redbeds Formation and the Santa Rosa Formation in support of the DP-831 discharge permit monitoring program. Nine dual-completion wells were reconfigured as Magenta-only monitor wells, and 12 wells were plugged and abandoned permanently. This report presents the summary in the same order that the wells were worked in the field.

Authors:
Publication Date:
Research Org.:
Waste Isolation Pilot Plant (WIPP), Carlsbad, NM (United States)
Sponsoring Org.:
USDOE - Office of Environmental Management (EM)
OSTI Identifier:
877257
Report Number(s):
DOE/WIPP-05-3326
TRN: US1001763
DOE Contract Number:
AC29-01AL66444
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; CLEANING; DOMESTIC ANIMALS; ENGINEERS; MANAGEMENT; MONITORING; MONITORS; OWNERSHIP; PLUGGING; WATER RIGHTS; plugging; abandonment; reconfiguration; disposal; wells; monitoring

Citation Formats

None, None. Basic Data Report for Well Plugging and Abandonment and Reconfiguration Activities for Fiscal Year 2005. United States: N. p., 2006. Web. doi:10.2172/877257.
None, None. Basic Data Report for Well Plugging and Abandonment and Reconfiguration Activities for Fiscal Year 2005. United States. doi:10.2172/877257.
None, None. Mon . "Basic Data Report for Well Plugging and Abandonment and Reconfiguration Activities for Fiscal Year 2005". United States. doi:10.2172/877257. https://www.osti.gov/servlets/purl/877257.
@article{osti_877257,
title = {Basic Data Report for Well Plugging and Abandonment and Reconfiguration Activities for Fiscal Year 2005},
author = {None, None},
abstractNote = {The FY 2005 program was initiated on March 31, 2005, and concluded on July 16, 2005. The FY 2005 program initially included 25 wells requiring workover (P&A, Magenta reconfiguration, cleaning and keeping). During the process, the U.S. Bureau of Land Management (BLM) requested transfer of two wells (H-7c and H-8c) to their ownership for future livestock watering. These wells were transferred to the BLM through execution of Form wr-03, Declaration of Owner of Underground Water Rights, between the New Mexico Office of the State Engineer (NMOSE), the BLM, and the DOE Carlsbad Field Office (CBFO). One well (H-2b2) was cleaned and retained as a Culebra monitor well for continued use. One well (H-3d) was converted to a shallow well to monitor the formational contact between the Dewey Lake Redbeds Formation and the Santa Rosa Formation in support of the DP-831 discharge permit monitoring program. Nine dual-completion wells were reconfigured as Magenta-only monitor wells, and 12 wells were plugged and abandoned permanently. This report presents the summary in the same order that the wells were worked in the field.},
doi = {10.2172/877257},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Mon Mar 13 00:00:00 EST 2006},
month = {Mon Mar 13 00:00:00 EST 2006}
}

Technical Report:

Save / Share:
  • This report summarizes the well installation, plugging and abandonment and redevelopment activities conducted during the federal fiscal year (FY) 1997 at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. No new groundwater monitoring wells were installed during FY 1997. However, 13 temporary piezometers were installed around the Upper East Fork Poplar Creek (UEFPC) in the Y-12 Plant. An additional 36 temporary piezometers, also reported in this document, were installed in FY 1996 and, subsequently, assigned GW-series identification. A total of 21 monitoring wells at the Y-12 Plant were decommissioned in FY 1997. Three existing monitoring wells underwent redevelopment during FYmore » 1997. All well installation and development (including redevelopment) was conducted following industry-standard methods and approved procedures in the Environmental Surveillance Procedures Quality Control Program (Energy Systems 1988), the {ital Resource Conservation and Recovery Act (RCRA) Groundwater Monitoring Technical Enforcement Guidance Document} (EPA 19?6), and {ital Guidelines for Installation of Monitoring Wells at the Y-12 Plant} (Geraghty & Miller 1985). All wells were plugged and abandoned in accordance with the Monitoring Well Plugging and Abandonment Plan for the U.S. Department of Energy, Y-12 Plant, Oak Ridge, Tennessee (HSW, Inc. 1991). Health and safety monitoring and field screening of drilling returns and development waters were conducted in accordance with approved Lockheed Martin Energy Systems, Inc. (Energy Systems) guidelines.« less
  • This report summarizes the well installation, plugging and abandonment, and redevelopment activities conducted during the federal fiscal year (FY) 1998 at the Y-12 Plant, Oak Ridge, Tennessee. Five new groundwater monitoring wells were installed at the Y-12 Plant under the FY 1998 drilling program. Two of the wells are located in west Bear Creek Valley, one is in the eastern Y-12 Plant area near Lake Reality, and two are located near the Oil Landfarm Waste Management Area, which were installed by Bechtel Jacobs Company LLC (Bechtel Jacobs) as part of a site characterization activity for the Oak Ridge Reservation (ORR)more » Disposal Cell. Also, two existing wells were upgraded and nine temporary piezometers were installed to characterize hydrogeologic conditions at the Disposal Cell site. In addition, 40 temporary piezometers were installed in the Boneyard/Bumyard area of Bear Creek Valley by Bechtel Jacobs as part of the accelerated remedial actions conducted by the Environmental Restoration Program. Ten monitoring wells at the Y-12 Plant were decommissioned in FY 1998. Two existing monitoring wells were redeveloped during FY 1998 (of these, GW-732 was redeveloped tsvice). All well installation and development (including redevelopment) was conducted following industry-standard methods and approved procedures from the Environmental Surveillance Procedures Quality Control Program (Energy Systems 1988); the Resource Conservation and Recovery Act (RCRA) Groundwater Monitoring Technical Enforcement Guidance Document (EPA 1992); and the Monitoring Well Installation Plan for the Department of Energy Y-12 Plant, Oak Ridge, Tennessee (Energy Systems 1997a). Well installation and development of the non-Y-12 Plant GWPP oversight installation projects were conducted using procedures/guidance defined in the following documents: Work Plan for Support to Upper East Fork Poplar Creek East End Volatile Organic Compound Plumes Well Installation Project, Oak Ridge Y-12 Plant, Oak Ridge, Tennessee (SAIC 1998a); Sampling and Analysis Plan for the Oil Landfarm Soils Containment Pad (SAIC 1998b); and Work Plan for Phase III Predesign Site Characterization, Environmental Waste Management Facility, Oak Ridge, Tennessee (Jacobs 1998a). Plugging and abandonment of all wells for which such action was taken were done in accordance with the Monitoring Well Plugging and Abandonment Plan, Y-12 Plant, Oak Ridge, Tennessee (Revised) (Energy Systems 1997b). Health and safety monitoring and field screening of drilling returns and development waters were conducted in accordance with the Health and Safety Plan for Well Installation and Plugging and Abandonment Activities, Y-12 Plant, Oak Ridge, Tennessee (SAIC 1992), Sampling and Anaiysis Plan for the Oil Landfarm Soils Containment Pad (SAIC 1998b), Work Plan for Phase III Predesign Site Characterization, Environmental Waste Management Facility, Oak Ridge, Tennessee (Jacobs 1998a), and other applicable MK Ferguson health and safety documents (Project Hazard Analysis, Site-specific Activity Hazard Analysis).« less
  • This report is a synopsis of the progress of the well plugging and abandonment program at the Y-12 Plant, Oak Ridge, Tennessee, from October 1993 through August 1994. A total of 57 wells and borings were plugged and abandoned during the period of time covered in this report. All wells and borings were plugged and abandoned in accordance with the Monitoring Well Plugging and Abandonment Plan for the U.S. Department of Energy, Y-12 Plant, Oak Ridge, Tennessee.
  • This report is a synopsis of the progress of the well plugging and abandonment program at the Y-12 Plant, Oak Ridge, Tennessee, from September 1994 through August 1995. A total of 67 wells, piezometers, and borings were plugged and abandoned during the period of time covered in this report. All wells and borings were plugged and abandoned if (1) its construction did not meet current standards (substandard construction); (2) it was irreparably damaged or had deteriorated beyond practical repair; (3) its location interfered with or otherwise impeded site operations, construction, or closure activities; or (4) special circumstances existed as definedmore » on a case-by-case basis and approved by the Y-12 Plant Groundwater Protection Program (GWPP) Manager. This summary report contains: general geologic setting of the Y-12 Plant and vicinity; discussion of well plugging and abandonment methods, grouting procedures, and waste management practices (a Waste Management Plan for Drilling Activities is included in Appendix C); summaries of plugging and abandonment activities at each site; and quality assurance/quality control (QA/QC) and health and safety protocols used during the FY 1995 Plugging and Abandonment Program.« less
  • This report is a synopsis of the progress of the well plugging and abandonment program at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee, from August 1995 through August 1996. A total of 27 wells, piezometers, and borings were plugged and abandoned during the period of time covered in this report. All wells and borings were plugged and abandoned in accordance with the Monitoring Well Plugging and Abandonment Plan for the U.S. Department of Energy, Y-12 Plant, Oak Ridge, Tennessee (HSW, Inc. 1991).