Title: Fluid Management Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 1

Abstract

The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) initiated the Offsites Project to characterize the risk posed to human health and the environment as a result of testing at formerly used nuclear sites in Alaska, Colorado, Mississippi, Nevada, and New Mexico. The scope of this Fluid Management Plan (FMP) is to support the subsurface investigation at the Project Shoal Area (PSA) Corrective Action Unit (CAU) 447, Shoal - Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Spring Range, south of Highway 50, about 39 miles southeast of Fallon, Nevada. (Figure 1-1). This FMP will be used at the PSA in lieu of an individual discharge permit for each well or a general water pollution control permit for management of all fluids produced during the drilling, construction, development, testing, experimentation, and/or sampling of wells conducted by the Offsites Project. The FMP provides guidance for the management of fluids generated during investigation activities and provides the standards by which fluids may be discharged on site. Although the Nevada Division of Environmental Protection (NDEP), Bureau of Federal Facilities (BoFF) is not amore » signatory to this FMP, it is involved in the negotiation of the contents of this plan and approves the conditions contained within. The major elements of this FMP include: (1) establishment of a well-site operations strategy; (2) site design/layout; (3) monitoring of contamination indicators (monitoring program); (4) sump characterization (sump sampling program); (5) fluid management decision criteria and fluid disposition; and (6) reporting requirements.« less

Authors:
Publication Date:
Research Org.:
Stoller-Navarro Joint Venture (S-N), Las Vegas, NV
Sponsoring Org.:
USDOE
OSTI Identifier:
876479
Report Number(s):
DOE/NV-1060-Rev. 1
TRN: US200604%%409
DOE Contract Number:
DE-AC52-03NA99205
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
54 ENVIRONMENTAL SCIENCES; CONSTRUCTION; CONTAMINATION; DRILLING; ENVIRONMENTAL PROTECTION; MANAGEMENT; MONITORING; NEGOTIATION; REPORTING REQUIREMENTS; SAMPLING; SAND; SECURITY; TESTING; WATER POLLUTION CONTROL

Citation Formats

Findlay, Rick. Fluid Management Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 1. United States: N. p., 2006. Web. doi:10.2172/876479.
Findlay, Rick. Fluid Management Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 1. United States. doi:10.2172/876479.
Findlay, Rick. Sun . "Fluid Management Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 1". United States. doi:10.2172/876479. https://www.osti.gov/servlets/purl/876479.
@article{osti_876479,
title = {Fluid Management Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 1},
author = {Findlay, Rick},
abstractNote = {The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) initiated the Offsites Project to characterize the risk posed to human health and the environment as a result of testing at formerly used nuclear sites in Alaska, Colorado, Mississippi, Nevada, and New Mexico. The scope of this Fluid Management Plan (FMP) is to support the subsurface investigation at the Project Shoal Area (PSA) Corrective Action Unit (CAU) 447, Shoal - Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Spring Range, south of Highway 50, about 39 miles southeast of Fallon, Nevada. (Figure 1-1). This FMP will be used at the PSA in lieu of an individual discharge permit for each well or a general water pollution control permit for management of all fluids produced during the drilling, construction, development, testing, experimentation, and/or sampling of wells conducted by the Offsites Project. The FMP provides guidance for the management of fluids generated during investigation activities and provides the standards by which fluids may be discharged on site. Although the Nevada Division of Environmental Protection (NDEP), Bureau of Federal Facilities (BoFF) is not a signatory to this FMP, it is involved in the negotiation of the contents of this plan and approves the conditions contained within. The major elements of this FMP include: (1) establishment of a well-site operations strategy; (2) site design/layout; (3) monitoring of contamination indicators (monitoring program); (4) sump characterization (sump sampling program); (5) fluid management decision criteria and fluid disposition; and (6) reporting requirements.},
doi = {10.2172/876479},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Sun Jan 01 00:00:00 EST 2006},
month = {Sun Jan 01 00:00:00 EST 2006}
}

Technical Report:

Save / Share:
  • The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) initiated the Offsites Project to characterize the risk posed to human health and the environment as a result of testing at formerly used nuclear sites in Alaska, Colorado, Mississippi, Nevada, and New Mexico. The scope of this Fluid Management Plan (FMP) is to support the subsurface investigation at the Project Shoal Area (PSA) Corrective Action Unit (CAU) 447, Shoal-Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Spring Range, south of Highwaymore » 50, about 39 miles southeast of Fallon, Nevada. (Figure 1-1). This FMP will be used at the PSA in lieu of an individual discharge permit for each well or a general water pollution control permit for management of all fluids produced during the drilling, construction, development, testing, experimentation, and/or sampling of wells conducted by the Offsites Project. The FMP provides guidance for the management of fluids generated during investigation activities and provides the standards by which fluids may be discharged on site. Although the Nevada Division of Environmental Protection (NDEP), Bureau of Federal Facilities (BoFF) is not a signatory to this FMP, it is involved in the negotiation of the contents of this plan and approves the conditions contained within. The major elements of this FMP include: (1) establishment of a well-site operations strategy; (2) site design/layout; (3) monitoring of contamination indicators (monitoring program); (4) sump characterization (sump sampling program); (5) fluid management decision criteria and fluid disposition; and (6) reporting requirements.« less
  • This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for Corrective Action Unit (CAU) 447, Project Shoal Area (PSA)-Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Springs Mountains in Churchill County, Nevada, approximately 48 kilometers (30 miles) southeast of Fallon, Nevada. The CADD/CAP combines the decision document (CADD) with the Corrective Action Plan (CAP) and provides or references the specific information necessary to recommend corrective actions for CAU 447, as provided in the FFACO. Corrective Action Unit 447 consists of two corrective actionmore » sites (CASs): CAS 57-49-01, Emplacement Shaft, and CAS 57-57-001, Cavity. The emplacement shaft (CAS-57-49-01) was backfilled and plugged in 1996 and will not be evaluated further. The purpose of the CADD portion of the document (Section 1.0 to Section 4.0) is to identify and provide a rationale for the selection of a recommended corrective action alternative for the subsurface at PSA. To achieve this, the following tasks were required: (1) Develop corrective action objectives. (2) Identify corrective action alternative screening criteria. (3) Develop corrective action alternatives. (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria. (5) Recommend a preferred corrective action alternative for the subsurface at PSA. The original Corrective Action Investigation Plan (CAIP) for the PSA was approved in September 1996 and described a plan to drill and test four characterization wells, followed by flow and transport modeling (DOE/NV, 1996). The resultant drilling is described in a data report (DOE/NV, 1998e) and the data analysis and modeling in an interim modeling report (Pohll et al., 1998). After considering the results of the modeling effort, the U.S. Department of Energy (DOE) determined that the degree of uncertainty in transport predictions for PSA remained unacceptably large. As a result, a second CAIP was developed by DOE and approved by the Nevada Division of Environmental Protection (NDEP) in December 1998 (DOE/NV, 1998a). This plan prescribed a rigorous analysis of uncertainty in the Shoal model and quantification of methods of reducing uncertainty through data collection. This analysis is termed a Data Decision Analysis (Pohll et al., 1999a) and formed the basis for a second major characterization effort at PSA (Pohll et al., 1999b). The details for this second field effort are presented in an Addendum to the CAIP, which was approved by NDEP in April 1999 (DOE/NV, 1999a). Four additional characterization wells were drilled at PSA during summer and fall of 1999; details of the drilling and well installation are in IT Corporation (2000), with testing reported in Mihevc et al. (2000). A key component of the second field program was a tracer test between two of the new wells (Carroll et al., 2000; Reimus et al., 2003). Based on the potential exposure pathways, two corrective action objectives were identified for CAU 447: Prevent or mitigate exposure to groundwater contaminants of concern at concentrations exceeding regulatory maximum contaminant levels or risk-based levels; and Reduce the risk to human health and the environment to the extent practicable. Based on the review of existing data, the results of the modeling, future use, and current operations at PSA, the following alternatives have been developed for consideration at CAU 447: Alternative 1--No Further Action; Alternative 2--Proof-of-Concept and Monitoring with Institutional Controls; and Alternative 3--Contaminant Control. The corrective action alternatives were evaluated based on the approach outlined in the ''Focused Evaluation of Selected Remedial Alternatives for the Underground Test Area'' (DOE/NV, 1998b). Each alternative was assessed against nine evaluation criteria. These criteria include overall protection of human health and the environment; compliance with appropriate requirements; long-term effectiveness; reduction of the toxicity, mobility, or volume of contamination; short-term effectiveness; implementability; cost; state acceptance; and community acceptance. Based on the results of this evaluation, the preferred alternative for CAU 447 is Alternative 2, Proof-of-Concept and Monitoring with Institutional Controls. The preferred corrective action alternative was chosen for its technical implementability, focusing on performance, reliability, feasibility, safety, and cost. Alternative 2 was judged to meet all requirements for the technical components evaluated and will control inadvertent exposure to contaminated groundwater at CAU 447.« less
  • The report is an addendum to Chapter 6.0, ''Field Investigation,'' of the Corrective Action Investigation Plan for Corrective Action Unit 447: Project Shoal Area, Nevada Subsurface Site, DOE/NV--513. Sections 6.0 and 6.1 in DOE/NV--513 continue to stand, with the sections below following after them. These new sections represent information that was not available at the time DOE/NV--513 was issued.
  • Chapter 6.0 in the Shoal Subsurface Corrective Action Investigation Plan (CAIP) provided a framework for a data decision analysis (DDA) that would be used to determine investigation methods and data collection methods to minimize uncertainty in groundwater flow and transport predictions. Uncertain parameters were identified and possible field activities that could provide information on those uncertain parameters were briefly described. The DDA has now been completed (Pohll and Forsgren, 1999) and prompts this addendum to describe the outcome of the DDA, how it was used to determine the next phase of data collection for the Shoal Subsurface activities, and tomore » provide details of the planned investigations sufficient to allow understanding of the scope and completion of the tasks involved.« less
  • This Corrective Action Investigation Plan (CAIP) describes the US Department of Energy's (DOE's) continued environmental investigation of the subsurface Project Shoal Area (PSA) Corrective Action Unit (CAU) 447. The PSA is located in the Sand Springs Mountains in Churchill County, Nevada, about 48 kilometers (km) (30 miles [mi]) southeast of Fallon, Nevada. Project Shoal was part of the Vela Uniform Program which was conducted to improve the US' ability to detect, identify, and locate underground nuclear detonations. The test consisted of detonating a 12-kiloton nuclear device deep underground in granitic rock to determine whether seismic waves produced by an undergroundmore » nuclear test could be differentiated from seismic waves produced by a naturally occurring earthquake. The test was a joint effort conducted by the US Atomic Energy Commission (AEC) and the US Department of Defense (DoD) in October 1963 (AEC, 1964).« less