Title: Commissioning of the LHC Beam Transfer Line TI 8

Abstract

The first of the two LHC transfer lines was commissioned in autumn 2004. Beam reached an absorber block located some 2.5 km downstream of the SPS extraction point at the first shot, without the need of any threading. The hardware preparation and commissioning phase will be summarized, followed by a description of the beam tests and their results regarding optics and other line parameters, including the experience gained with beam instrumentation, the control system and the machine protection equipment.

Authors:
; ; ; ; ; ; ; ; ;
Publication Date:
Research Org.:
Thomas Jefferson National Accelerator Facility (TJNAF), Newport News, VA
Sponsoring Org.:
USDOE - Office of Energy Research (ER)
OSTI Identifier:
861086
Report Number(s):
JLAB-ACP-05-426; DOE/ER/40150-3655
TRN: US0600210
DOE Contract Number:  
AC05-84ER40150
Resource Type:
Conference
Resource Relation:
Conference: PAC 2005, 16-20 May 2005, Knoxville, Tennessee
Country of Publication:
United States
Language:
English
Subject:
43 PARTICLE ACCELERATORS; LINEAR COLLIDERS; BEAM TRANSPORT; COMMISSIONING; COMPUTERIZED CONTROL SYSTEMS; BEAM POSITION; EQUIPMENT PROTECTION DEVICES

Citation Formats

J.A. Uythoven, G. Arduini, B. Goddard, D. Jacquet, V. Kain, M. Lamont, V. Mertens, A. Spinks, J. Wenninger, and Y.-C. Chao. Commissioning of the LHC Beam Transfer Line TI 8. United States: N. p., 2005. Web.
J.A. Uythoven, G. Arduini, B. Goddard, D. Jacquet, V. Kain, M. Lamont, V. Mertens, A. Spinks, J. Wenninger, & Y.-C. Chao. Commissioning of the LHC Beam Transfer Line TI 8. United States.
J.A. Uythoven, G. Arduini, B. Goddard, D. Jacquet, V. Kain, M. Lamont, V. Mertens, A. Spinks, J. Wenninger, and Y.-C. Chao. Mon . "Commissioning of the LHC Beam Transfer Line TI 8". United States. https://www.osti.gov/servlets/purl/861086.
@article{osti_861086,
title = {Commissioning of the LHC Beam Transfer Line TI 8},
author = {J.A. Uythoven and G. Arduini and B. Goddard and D. Jacquet and V. Kain and M. Lamont and V. Mertens and A. Spinks and J. Wenninger and Y.-C. Chao},
abstractNote = {The first of the two LHC transfer lines was commissioned in autumn 2004. Beam reached an absorber block located some 2.5 km downstream of the SPS extraction point at the first shot, without the need of any threading. The hardware preparation and commissioning phase will be summarized, followed by a description of the beam tests and their results regarding optics and other line parameters, including the experience gained with beam instrumentation, the control system and the machine protection equipment.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2005},
month = {5}
}

Conference:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that hold this conference proceeding.

Save / Share: