Title: FROM PROPERTY LEASE TO PROPERTY TRANSFER - TAKING THE STEPS TO FACILITATE SITE CLOSURE USING THE DEPARTMENT OF ENERGY'S 10 CFR 770 PROCESS

Abstract

While implementing a successful leasing program for land and facilities at the Department of Energy's Oak Ridge Operations Office in Oak Ridge, TN, the Department is now transitioning from a leasing program to one of title transfer. The program, called ''Reindustrialization'', is the result of a visionary idea to enable the use of excess resources to meet a community's needs in the wake of continued DOE downsizing. An established process included within the Comprehensive Environmental Response Compensation and Liability Act, tailored to meet DOE-ORO's objectives, was used to lease. Title transfer, using DOE's new 10 CFR 770 process, is being undertaken to meet a DOE-HQs directive to close the ORO facility where Reindustrialization is taking place. Title transfer is a key component of the closure effort. However, the process for title transfer is new, it is a DOE process, and it has not yet been completed for any facilities in the DOE complex. Making the transition from a known to an unknown has created opportunities in program design, as well as implementation, coordination and acceptance challenges in a variety of areas, and a host of lessons learned and learning.

Authors:
;
Publication Date:
Research Org.:
Bechtel Jacobs Company LLC; Department of Energy-Oak Ridge Operations, Federal Office Building, 200 Administration Road, Oak Ridge, TN 37831 (US)
Sponsoring Org.:
US Department of Energy (US)
OSTI Identifier:
827287
DOE Contract Number:
AC05-98OR22700
Resource Type:
Conference
Resource Relation:
Conference: Waste Management 2003 Symposium, Tucson, AZ (US), 02/23/2003--02/27/2003; Other Information: PBD: 27 Feb 2003
Country of Publication:
United States
Language:
English
Subject:
29 ENERGY PLANNING, POLICY AND ECONOMY; CLOSURES; DESIGN; IMPLEMENTATION; LEARNING; LEASES; LEASING; WASTE MANAGEMENT

Citation Formats

Cusick, Lesley T., and Hart, Patricia W. FROM PROPERTY LEASE TO PROPERTY TRANSFER - TAKING THE STEPS TO FACILITATE SITE CLOSURE USING THE DEPARTMENT OF ENERGY'S 10 CFR 770 PROCESS. United States: N. p., 2003. Web.
Cusick, Lesley T., & Hart, Patricia W. FROM PROPERTY LEASE TO PROPERTY TRANSFER - TAKING THE STEPS TO FACILITATE SITE CLOSURE USING THE DEPARTMENT OF ENERGY'S 10 CFR 770 PROCESS. United States.
Cusick, Lesley T., and Hart, Patricia W. 2003. "FROM PROPERTY LEASE TO PROPERTY TRANSFER - TAKING THE STEPS TO FACILITATE SITE CLOSURE USING THE DEPARTMENT OF ENERGY'S 10 CFR 770 PROCESS". United States. doi:. https://www.osti.gov/servlets/purl/827287.
@article{osti_827287,
title = {FROM PROPERTY LEASE TO PROPERTY TRANSFER - TAKING THE STEPS TO FACILITATE SITE CLOSURE USING THE DEPARTMENT OF ENERGY'S 10 CFR 770 PROCESS},
author = {Cusick, Lesley T. and Hart, Patricia W.},
abstractNote = {While implementing a successful leasing program for land and facilities at the Department of Energy's Oak Ridge Operations Office in Oak Ridge, TN, the Department is now transitioning from a leasing program to one of title transfer. The program, called ''Reindustrialization'', is the result of a visionary idea to enable the use of excess resources to meet a community's needs in the wake of continued DOE downsizing. An established process included within the Comprehensive Environmental Response Compensation and Liability Act, tailored to meet DOE-ORO's objectives, was used to lease. Title transfer, using DOE's new 10 CFR 770 process, is being undertaken to meet a DOE-HQs directive to close the ORO facility where Reindustrialization is taking place. Title transfer is a key component of the closure effort. However, the process for title transfer is new, it is a DOE process, and it has not yet been completed for any facilities in the DOE complex. Making the transition from a known to an unknown has created opportunities in program design, as well as implementation, coordination and acceptance challenges in a variety of areas, and a host of lessons learned and learning.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = 2003,
month = 2
}

Conference:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that hold this conference proceeding.

Save / Share:
  • Citizen involvement in DOE's decision-making for the environmental cleanup from DOE's management of its nuclear wastes across the DOE complex has had a positive effect on the cleanup of its SRS site, characterized by an acceleration of cleanup not only for the Transuranic wastes at SRS, but also for DOE's first two closures of HLW tanks, both of which occurred at SRS. The Citizens around SRS had pushed successfully for the closures of Tanks 17 and 20 in 1997, becoming the first closures of HLW tanks under regulatory guidance in the USA. However, since then, HLW tank closures ceased duemore » to a lawsuit, the application of new tank clean-up technology, interagency squabbling between DOE and NRC over tank closure criteria, and finally and almost fatally, from budget pressures. Despite an agreement with its regulators for the closure of Tanks 18 and 19 by the end of calendar year 2012, the outlook in Fall 2011 to close these two tanks had dimmed. It was at this point that the citizens around SRS became reengaged with tank closures, helping DOE to reach its agreed upon milestone. (authors)« less
  • With the congressionally mandated January 1, 2013 deadline for the U.S. Department of Energy’s (DOE) Nuclear Material Protection, Control and Accounting (MPC&A) program to complete its transition of MPC&A responsibility to the Russian Federation, National Nuclear Security Administration (NNSA) management directed its MPC&A program managers and team leaders to demonstrate that work in ongoing programs would lead to successful and timely achievement of these milestones. In the spirit of planning for successful project completion, the NNSA review of the Russian regulatory development process confirmed the critical importance of an effective regulatory system to a sustainable nuclear protection regime and calledmore » for an analysis of the existing Russian regulatory structure and the identification of a plan to ensure a complete MPC&A regulatory foundation. This paper describes the systematic process used by DOE’s MPC&A Regulatory Development Project (RDP) to develop an effective and sustainable MPC&A regulatory structure in the Russian Federation. This nuclear regulatory system will address all non-military Category I and II nuclear materials at State Corporation for Atomic Energy “Rosatom,” the Federal Service for Ecological, Technological, and Nuclear Oversight (Rostechnadzor), the Federal Agency for Marine and River Transport (FAMRT, within the Ministry of Transportation), and the Ministry of Industry and Trade (Minpromtorg). The approach to ensuring a complete and comprehensive nuclear regulatory structure includes five sequential steps. The approach was adopted from DOE’s project management guidelines and was adapted to the regulatory development task by the RDP. The five steps in the Regulatory Development Process are: 1) Define MPC&A Structural Elements; 2) Analyze the existing regulatory documents using the identified Structural Elements; 3) Validate the analysis with Russian colleagues and define the list of documents to be developed; 4) Prioritize and schedule the development of documents; 5) Identify and develop processes to measure effectiveness of regulations. Utilizing this process is resulting in an effective regulatory process that is understood and is being adopted by the four RF organizations. It is anticipated that the current regulatory development process will continue after U.S. support ends. Utilization of the systematic methodology will ensure regulatory development is based on required MPC&A structural elements and will support the continued maintenance and development of an effective regulatory base.« less
  • Significant progress has been made at the U.S. Department of Energy (DOE) Idaho National Laboratory (INL) to clean and close emptied radioactive liquid waste storage tanks at the Idaho Nuclear Technology and Engineering Center (INTEC) Tank Farm Facility (TFF). The TFF includes eleven 1,135.6-kL (300,000-gal) underground stainless steel storage tanks and four smaller, 113.5-kL (30,000-gal) stainless steel tanks, along with tank vaults, interconnecting piping, and ancillary equipment. The TFF tanks have historically been used to store a variety of radioactive liquid waste, including wastes associated with past spent nuclear fuel reprocessing. Although four of the large storage tanks remain inmore » use for waste storage, the other seven 1,135.6-kL (300,000-gal) tanks and the four 113.5-kL (30,000-gal) tanks have been emptied of waste and cleaned in preparation of final closure. A water spray cleaning system was developed and deployed to clean internal tank surfaces and remove remaining tank wastes. The cleaning system was effective in removing all but a very small volume of solid residual waste particles. Recent issuance of an Amended Record of Decision (ROD) in accordance with the National Environmental Policy Act, and a Waste Determination complying with Section 3116 of the Ronald W. Reagan National Defense Authorization Act (NDAA) for Fiscal Year 2005, has allowed commencement of grouting activities on the cleaned tanks. In November 2006, three of the 113.5-kL (30,000-gal) tanks were filled with grout to provide long-term stability. It is currently planned that all seven cleaned 1,135.6-kL (300,000-gal) tanks, as well as the four 113.5-kL (30,000-gal) tanks and all associated tank vaults and interconnecting piping, will be stabilized with grout as early as 2008. (authors)« less
  • Significant progress has been made at the U.S. Department of Energy (DOE) Idaho National Laboratory (INL) to empty, clean and close radioactive liquid waste storage tanks at the Idaho Nuclear Technology and Engineering Center (INTEC) Tank Farm Facility (TFF). The TFF includes eleven 1,135.6-kL (300,000-gal) underground stainless steel storage tanks and four smaller, 113.5-kL (30,000-gal) stainless steel tanks, along with tank vaults, interconnecting piping, and ancillary equipment. The TFF tanks have historically been used to store a variety of radioactive liquid waste, including wastes associated with past spent nuclear fuel reprocessing. Although four of the large storage tanks remain inmore » use for waste storage, the other seven 1,135.6-kL (300,000-gal) tanks and the four 113.5-kL (30,000-gal) tanks have been emptied of waste, cleaned and filled with grout. A water spray cleaning system was developed and deployed to clean internal tank surfaces and remove remaining tank wastes. The cleaning system was effective in removing all but a very small volume of solid residual waste particles. Recent issuance of an Amended Record of Decision (ROD) in accordance with the National Environmental Policy Act, and a Waste Determination complying with Section 3116 of the Ronald W. Reagan National Defense Authorization Act (NDAA) for Fiscal Year 2005, has allowed commencement of grouting activities on the cleaned tanks. The first three 113.5-kL (30,000-gal) tanks were grouted in the Fall of 2006 and the fourth tank and the seven 1,135.6-kL (300,000-gal) tanks were filled with grout in 2007 to provide long-term stability. It is currently planned that associated tank valve boxes and interconnecting piping, will be stabilized with grout as early as 2008. (authors)« less
  • The U.S. Department of Energy (DOE) owns, operates, and manages the buildings and land areas on the Oak Ridge Reservation (ORR) in Oak Ridge, Tennessee. As land and buildings are declared excess or underutilized, it is the intent of DOE to either transfer the title of or lease suitable property to the Community Reuse Organization of East Tennessee (CROET) or other entities for public use. It is DOE's responsibility, in coordination with the U.S. Environmental Protection Agency (EPA), Region 4, and the Tennessee Department of Environment and Conservation (TDEC), to ensure that the land, facilities, and personal property that aremore » to have the title transferred or are to be leased are suitable for public use. Release of personal property must also meet site requirements and be approved by the DOE contractor responsible for site radiological control. The terms title transfer and lease in this document have unique meanings. Title transfer will result in release of ownership without any restriction or further control by DOE. Under lease conditions, the government retains ownership of the property along with the responsibility to oversee property utilization. This includes involvement in the lessee's health, safety, and radiological control plans and conduct of site inspections. It may also entail lease restrictions, such as limiting access to certain areas or prohibiting digging, drilling, or disturbing material under surface coatings. Survey and sampling requirements are generally more rigorous for title transfer than for lease. Because of the accelerated clean up process, there is an increasing emphasis on title transfers of facilities and land. The purpose of this document is to describe the radiological survey and sampling protocols that are being used for assessing the radiological conditions and characteristics of building and land areas on the Oak Ridge Reservation that contain space potentially available for title transfer or lease. After necessary surveys and sampling and laboratory analyses are completed, the data are analyzed and included in an Environmental Baseline Summary (EBS) report for title transfer or in a Baseline Environmental Analysis Report (BEAR) for lease. The data from the BEAR is then used in a Screening-Level Human Health Risk Assessment (SHHRA) or a risk calculation (RC) to assess the potential risks to future owners/occupants. If title is to be transferred, release criteria in the form of specific activity concentrations called Derived Concentration Guideline Levels (DCGLs) will be developed for the each property. The DCGLs are based on the risk model and are used with the data in the EBS to determine, with statistical confidence, that the release criteria for the property have been met. The goal of the survey and sampling efforts is to (1) document the baseline conditions of the property (real or personal) prior to title transfer or lease, (2) obtain enough information that an evaluation of radiological risks can be made, and (3) collect sufftcient data so that areas that contain minimal residual levels of radioactivity can be identified and, following radiological control procedures, be released from radiological control. (It should be noted that release from radiological control does not necessarily mean free release because DOE may maintain institutional control of the site after it is released from radiological control). To meet the goals of this document, a Data Quality Objective (DQO) process will be used to enhance data collection efficiency and assist with decision-making. The steps of the DQO process involve stating the problem, identifying the decision, identifying inputs to the decision, developing study boundaries, developing the decision rule, and optimizing the design. This document describes the DQOs chosen for surveys and sampling efforts performed for the purposes listed above. The previous version to this document focused on the requirements for radiological survey and sampling protocols that are be used for leasing. Because the primary focus at this time is on title transfer, this revision applies to both situations.« less