Title: Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-11)

Abstract

BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission line. Also, access road clearing will be conducted. All work will be in accordance with the National Electrical Safety Code and BPA standards. BPA plans to conduct vegetation control with the goal of removing tall growing vegetation that is currently or will soon be a hazard to the transmission line. BPA's overall goal is to have low-growing plant communities along the rights-of-way to control the development of potentially threatening vegetation. This project meets the standards and guidelines for the Transmission System Vegetation Management Program Final Environmental Impact Statement (FEIS) and Record of Decision (ROD).

Authors:
Publication Date:
Research Org.:
U.S. Department of Energy, Bonneville Power Administration (US)
Sponsoring Org.:
USDOE Office of NEPA Policy and Assistance (EH-42) (US)
OSTI Identifier:
823853
Report Number(s):
DOE/EIS-0285/SA-11
TRN: US200430%%1397
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 15 May 2001
Country of Publication:
United States
Language:
English
Subject:
24 POWER TRANSMISSION AND DISTRIBUTION; 29 ENERGY PLANNING, POLICY AND ECONOMY; COMMUNITIES; ENVIRONMENTAL IMPACT STATEMENTS; MAINTENANCE; MANAGEMENT; PLANTS; POWER TRANSMISSION LINES; RECOMMENDATIONS; RIGHTS-OF-WAY; SAFETY; SA; VEGETATION MANAGEMENT; COVINGTON-MAPLE VALLEY NO. 2; TRANSMISSION LINE; ROW. T; KING COUNTY; WA; SNOHOMISH REGION

Citation Formats

N /A. Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-11). United States: N. p., 2001. Web. doi:10.2172/823853.
N /A. Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-11). United States. doi:10.2172/823853.
N /A. Tue . "Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-11)". United States. doi:10.2172/823853. https://www.osti.gov/servlets/purl/823853.
@article{osti_823853,
title = {Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-11)},
author = {N /A},
abstractNote = {BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission line. Also, access road clearing will be conducted. All work will be in accordance with the National Electrical Safety Code and BPA standards. BPA plans to conduct vegetation control with the goal of removing tall growing vegetation that is currently or will soon be a hazard to the transmission line. BPA's overall goal is to have low-growing plant communities along the rights-of-way to control the development of potentially threatening vegetation. This project meets the standards and guidelines for the Transmission System Vegetation Management Program Final Environmental Impact Statement (FEIS) and Record of Decision (ROD).},
doi = {10.2172/823853},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Tue May 15 00:00:00 EDT 2001},
month = {Tue May 15 00:00:00 EDT 2001}
}

Technical Report:

Save / Share:
  • Re-vegetation Plot Study along the Lower Monumental-McNary Transmission Line ROW. The study area sections are located near structures 38/4 and 39/3. The line is a 500kV Single Circuit Transmission Line having an easement width of 165 feet. The proposed work will be accomplished in the indicated sections of the transmission line corridor as indicated on the attached checklist. A summer of 2001 fire burned the subject area leaving the ROW in a bare ground situation. Before, the fire the site was dominated by annual vegetation (cheatgrass) and noxious weeds (yellowstar thistle). As a study of plant succession after the firemore » for a local Boy Scout group, two 100 X 100 foot areas will be identified for study over the next 2-3 years. The two test plots will be identified and permanently marked. One will receive treatment while the other will not be treated and used as a control plot.« less
  • BPA proposes to clear unwanted vegetation from the rights of way and access roads for BPA's Big Eddy-Ostrander Transmission Line, beginning April and ending in May, 2001. A Checklist was completed for this project in accordance to the requirements identified in the Bonneville Power Administrations Transmission System Vegetation Management Program FEIS (DOE/EIS-0285). The Checklist evaluated the following areas: (1) Description of right-of-way and vegetation management needed; (2) Vegetation to be controlled; (3) Surrounding land use and landowner; (4) Natural Resource; (5) Vegetation control methods; (6) Debris disposal; (7) Monitoring; and (8) Appropriate environmental documentation. In preparation of this Supplement Analysis,more » the Checklist was reviewed. Specific information regarding the areas as identified above are described the attached checklist. This Supplement Analysis finds that: (1) the proposed actions are substantially consistent with the Transmission System Vegetation Management Program FEIS (DOE/EIS0285) and ROD; and (2) there are no new circumstances or information relevant to environmental concerns and bearing on the proposed actions or their impacts. Therefore, no further NEPA documentation is required.« less
  • Vegetation Management along selected ROW sections of the Ostrander-Pearl transmission line. The ROWs include sections of the Ostrander-Pearl 500 kV line; the Ostrander-McLoughlin 500 kV line; the Big Eddy-Chemawa 230 kV line and the Big Eddy-McLoughlin 230 kV line. BPA proposes to clear unwanted vegetation in the rights-of-way and around tower structures that may impede the operation and maintenance of the subject transmission lines. The project also includes clearing approximately 3 miles of access road and cutting of some danger trees. All work will be in accordance with the National Electrical Safety Code and BPA Standards. BPA plans to conductmore » vegetation control with the goal of removing tall-growing vegetation that is currently or will soon be a hazard to the transmission lines and to promote low-growing plant communities in the right-of-way and to clear vegetation from new rights-of-way corridors.« less
  • BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission line. BPA plans to conduct vegetation control with the goal of removing tall growing vegetation that is currently or will soon be a hazard to the transmission line. BPA’s overall goal is to have low-growing plant communities along the rights-of-way to control the development of potentially threatening vegetation. All work will be executed in accordance with the National Electrical Safety Code and BPA standards.
  • Vegetation Management along the Port Angeles - Sappo No.1 Transmission Line ROW, from structure 1/1 to structure 42/10. BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission line. BPA plans to conduct vegetation control with the goal of removing tall growing vegetation that is currently or will soon be a hazard to the transmission line. BPA’s overall goal is to have low-growing plant communities along the rights-of-way to control the development of potentially threatening vegetation. All work will be executed in accordance with the Nationalmore » Electrical Safety Code and BPA standards.« less