Title: Advanced Design Mixer Pump Tank 18 Design Modifications Summary Report

Abstract

The Westinghouse Savannah River Company (WSRC) is preparing to retrieve high level waste (HLW) from Tank 18 in early FY03 to provide feed for the Defense Waste Processing Facility (DWPF) and to support tank closure in FY04. As part of the Tank 18 project, WSRC will install a single Advanced Design Mixer Pump (ADMP) in the center riser of Tank 18 to mobilize, suspend, and mix radioactive sludge in preparation for transfer to Tank 7. The use of a single ADMP is a change to the current baseline of four (4) standard slurry pumps used during previous waste retrieval campaigns. The ADMP was originally conceived by Hanford and supported by SRS to provide a more reliable and maintainable mixer pump for use throughout the DOE complex. The ADMP underwent an extensive test program at SRS between 1998 and 2002 to assess reliability and hydraulic performance. The ADMP ran for approximately 4,200 hours over the four-year period. A detailed tear down and inspection of the pump following the 4,2 00-hour run revealed that the gas mechanical seals and anti-friction bearings would need to be refurbished/replaced prior to deployment in Tank 18. Design modifications were also needed to meet current Authorization Basismore » safety requirements. This report documents the modifications made to the ADMP in support of Tank 18 deployment. This report meets the requirements of Tanks Focus Area (TFA) Milestone 3591.4-1, ''Issue Report on Modifications Made to the ADMP,'' contained in Technical Task Plan (TTP) SR16WT51, ''WSRC Retrieval and Closure.''« less

Authors:
Publication Date:
Research Org.:
Savannah River Site (US)
Sponsoring Org.:
US Department of Energy (US)
OSTI Identifier:
805608
Report Number(s):
HLW-STE-2002-00305
TRN: US0300933
DOE Contract Number:  
AC09-96SR18500
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 3 Dec 2002
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; BEARINGS; CLOSURES; DESIGN; HYDRAULICS; MIXERS; MODIFICATIONS; PERFORMANCE; RELIABILITY; SAFETY; SLUDGES; TANKS; WASTE PROCESSING; WASTE RETRIEVAL; WASTES

Citation Formats

Adkins, B.J. Advanced Design Mixer Pump Tank 18 Design Modifications Summary Report. United States: N. p., 2002. Web. doi:10.2172/805608.
Adkins, B.J. Advanced Design Mixer Pump Tank 18 Design Modifications Summary Report. United States. doi:10.2172/805608.
Adkins, B.J. Tue . "Advanced Design Mixer Pump Tank 18 Design Modifications Summary Report". United States. doi:10.2172/805608. https://www.osti.gov/servlets/purl/805608.
@article{osti_805608,
title = {Advanced Design Mixer Pump Tank 18 Design Modifications Summary Report},
author = {Adkins, B.J.},
abstractNote = {The Westinghouse Savannah River Company (WSRC) is preparing to retrieve high level waste (HLW) from Tank 18 in early FY03 to provide feed for the Defense Waste Processing Facility (DWPF) and to support tank closure in FY04. As part of the Tank 18 project, WSRC will install a single Advanced Design Mixer Pump (ADMP) in the center riser of Tank 18 to mobilize, suspend, and mix radioactive sludge in preparation for transfer to Tank 7. The use of a single ADMP is a change to the current baseline of four (4) standard slurry pumps used during previous waste retrieval campaigns. The ADMP was originally conceived by Hanford and supported by SRS to provide a more reliable and maintainable mixer pump for use throughout the DOE complex. The ADMP underwent an extensive test program at SRS between 1998 and 2002 to assess reliability and hydraulic performance. The ADMP ran for approximately 4,200 hours over the four-year period. A detailed tear down and inspection of the pump following the 4,2 00-hour run revealed that the gas mechanical seals and anti-friction bearings would need to be refurbished/replaced prior to deployment in Tank 18. Design modifications were also needed to meet current Authorization Basis safety requirements. This report documents the modifications made to the ADMP in support of Tank 18 deployment. This report meets the requirements of Tanks Focus Area (TFA) Milestone 3591.4-1, ''Issue Report on Modifications Made to the ADMP,'' contained in Technical Task Plan (TTP) SR16WT51, ''WSRC Retrieval and Closure.''},
doi = {10.2172/805608},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2002},
month = {12}
}

Technical Report:

Save / Share: