Title: Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R

Abstract

This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''R''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

Authors:
Publication Date:
Research Org.:
CHG (US)
Sponsoring Org.:
ENVIRONMENTAL MANAGEMENT (US)
OSTI Identifier:
803666
Report Number(s):
RPP-6193, Rev.0
EDT-624913; TRN: US0301605
DOE Contract Number:  
AC27-99RL14047
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 11 May 2000
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; PUMPS; PERFORMANCE TESTING; ON-LINE MEASUREMENT SYSTEMS; STORAGE FACILITIES; RADIOACTIVE WASTE STORAGE; COMPUTERIZED CONTROL SYSTEMS

Citation Formats

KOCH, M.R. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R. United States: N. p., 2000. Web. doi:10.2172/803666.
KOCH, M.R. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R. United States. doi:10.2172/803666.
KOCH, M.R. Thu . "Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R". United States. doi:10.2172/803666. https://www.osti.gov/servlets/purl/803666.
@article{osti_803666,
title = {Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R},
author = {KOCH, M.R.},
abstractNote = {This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''R''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.},
doi = {10.2172/803666},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2000},
month = {5}
}