Title: 244-CR Vault Interim Stabilization Project Plan

Technical Report ·
DOI:https://doi.org/10.2172/803013· OSTI ID:803013

The 244-CR Vault is a two-level, multi-cell structure of reinforced concrete constructed below grade. The lower cell contains four individual compartments, each containing a steel process storage tank and equipped with a concrete sump. The upper cell contains the piping and support equipment, and has two compartments for each of the tanks. The ''pump pit'' is accessed by the removal of concrete cover blocks, while the smaller ''riser pit'' is accessed by steel cover plates. The facility most recently was used as a double-contained receiver tank (DCRT). A DCRT is a type of waste transfer tank that together with its related equipment constitutes a short-term storage area for liquid waste and has a pump pit for waste transfer operations. This vault most recently was used for short-term storage and waste routing for saltwell liquid pumped from the 241-C Tank Farm in the 200 East Area. Waste transfer lines are connected inside the pump pit by a jumper installed between connecting nozzles. An active ventilation system is in operation at the 244-CR vault. Ventilation supply air enters the upper vault section through an inlet header with some leakage through the spaces between the cell cover blocks. The upper and lower vaults are connected by exhauster ports, which allow airflow between the two sections. Normal flow moves air from the upper cell to the lower cell where it is removed and routed into a filter plenum; there the air is treated by a bank of four prefilters and two banks of high-efficiency particulate air (HEPA) filters (each containing four HEPAs). The air is exhausted to the atmosphere through the 296-C-05 Stack. The stack is equipped with a record sampler and continuous air monitor. Two fans (each rated at 4,200 cubic feet per minute) installed downstream of the filtration system provide the motive force for exhausting the vaults and the tanks. As an active system, it is operated continuously with only one of the two fans required to operate at a time. A continuous beta-gamma air monitor is interlocked to the operating fan. Loss of power to the fans will activate an alarm at the 244-AR facility.

Research Organization:
CH2M Hill Hanford Group, Inc., Richland, WA (United States)
Sponsoring Organization:
ENVIRONMENTAL MANAGEMENT (US)
DOE Contract Number:
AC27-99RL14047
OSTI ID:
803013
Report Number(s):
RPP-6029, Rev.0; EDT-628314; TRN: US200301%%270
Resource Relation:
Other Information: PBD: 25 Apr 2000