Title: Installation Instructions (ETN-98-0005) S-farm Overground Transfer (ogt) System Valve Pit 241-S-B to Valve Pit 241-S-D

Abstract

Lockheed Martin Hanford Corporation (LMHC) is providing an overground transfer (OGT) system for use in saltwell pumping of the 241-S-Tank Farm. Fluor Daniel Northwest (FDNW) was requested to support the effort by completing the design of the OGT system and completing the construction of the encasement pipe and encasement pipe support system. FDNW will also install the concrete shielding blocks for the OGT system. The shielding block system will provide a vehicle barrier for protection of the OGT line and will provide a radiation barrier for operations personnel. LMHC is responsible for the regulatory compliance of the entire transfer system. This installation instruction covers the encasement piping, pipe supports, heat tracing, thermal insulation, leak detectors, temperature indicators, and the shielding blocks. Installation of the primary (inner) pipe and associated equipment was completed at a previous time and the integrity of the primary piping will be confirmed by LMHC prior to operation of the system.

Authors:
Publication Date:
Research Org.:
NHC (US)
Sponsoring Org.:
ENVIRONMENTAL MANAGEMENT (US)
OSTI Identifier:
797663
Report Number(s):
HNF-3479, Rev.0
TRN: US0204889
DOE Contract Number:  
AC06-96RL13200
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 25 Aug 1999
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; STORAGE FACILITIES; PIPELINES; INSTALLATION; WASTE RETRIEVAL; DESIGN; LEAK DETECTORS; PUMPING; THERMAL INSULATION; VALVES; SHIELDS; RADIATION PROTECTION

Citation Formats

HICKS, D.F. Installation Instructions (ETN-98-0005) S-farm Overground Transfer (ogt) System Valve Pit 241-S-B to Valve Pit 241-S-D. United States: N. p., 1999. Web. doi:10.2172/797663.
HICKS, D.F. Installation Instructions (ETN-98-0005) S-farm Overground Transfer (ogt) System Valve Pit 241-S-B to Valve Pit 241-S-D. United States. doi:10.2172/797663.
HICKS, D.F. Wed . "Installation Instructions (ETN-98-0005) S-farm Overground Transfer (ogt) System Valve Pit 241-S-B to Valve Pit 241-S-D". United States. doi:10.2172/797663. https://www.osti.gov/servlets/purl/797663.
@article{osti_797663,
title = {Installation Instructions (ETN-98-0005) S-farm Overground Transfer (ogt) System Valve Pit 241-S-B to Valve Pit 241-S-D},
author = {HICKS, D.F.},
abstractNote = {Lockheed Martin Hanford Corporation (LMHC) is providing an overground transfer (OGT) system for use in saltwell pumping of the 241-S-Tank Farm. Fluor Daniel Northwest (FDNW) was requested to support the effort by completing the design of the OGT system and completing the construction of the encasement pipe and encasement pipe support system. FDNW will also install the concrete shielding blocks for the OGT system. The shielding block system will provide a vehicle barrier for protection of the OGT line and will provide a radiation barrier for operations personnel. LMHC is responsible for the regulatory compliance of the entire transfer system. This installation instruction covers the encasement piping, pipe supports, heat tracing, thermal insulation, leak detectors, temperature indicators, and the shielding blocks. Installation of the primary (inner) pipe and associated equipment was completed at a previous time and the integrity of the primary piping will be confirmed by LMHC prior to operation of the system.},
doi = {10.2172/797663},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1999},
month = {8}
}