Title: Project plan remove special nuclear material from PFP project plutonium finishing plant

Abstract

This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process.

Authors:
Publication Date:
Research Org.:
HNF Hanford Site (US)
Sponsoring Org.:
US DOE Office of Environmental Management (US)
OSTI Identifier:
782302
Report Number(s):
HNF-3752-REV0
TRN: US0203119
DOE Contract Number:  
AC06-96RL13200
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 13 May 1999
Country of Publication:
United States
Language:
English
Subject:
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; PLANNING; PLUTONIUM; PROGRAM MANAGEMENT; STABILIZATION; FUEL REPROCESSING PLANTS; MATERIALS RECOVERY; RADIOACTIVE MATERIALS

Citation Formats

BARTLETT, W D. Project plan remove special nuclear material from PFP project plutonium finishing plant. United States: N. p., 1999. Web. doi:10.2172/782302.
BARTLETT, W D. Project plan remove special nuclear material from PFP project plutonium finishing plant. United States. doi:10.2172/782302.
BARTLETT, W D. Thu . "Project plan remove special nuclear material from PFP project plutonium finishing plant". United States. doi:10.2172/782302. https://www.osti.gov/servlets/purl/782302.
@article{osti_782302,
title = {Project plan remove special nuclear material from PFP project plutonium finishing plant},
author = {BARTLETT, W D},
abstractNote = {This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process.},
doi = {10.2172/782302},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1999},
month = {5}
}