Title: Hanford Environmental Management Program implementation plan

Abstract

The Hanford Environmental Management Program (HEMP) was established to facilitate compliance with the applicable environmental statues, regulations, and standards on the Hanford Site. The HEMP provides a structured approach to achieve environmental management objectives. The Hanford Environmental Management Program Plan (HEMP Plan) was prepared as a strategic level planning document to describe the program management, technical implementation, verification, and communications activities that guide the HEMP. Four basic program objectives are identified in the HEMP Plan as follows: establish ongoing monitoring to ensure that Hanford Site operations comply with environmental requirements; attain regulatory compliance through the modification of activities; mitigate any environmental consequences; and minimize the environmental impacts of future operations at the Hanford Site. 2 refs., 24 figs., 27 tabs.

Publication Date:
Research Org.:
Westinghouse Hanford Co., Richland, WA (USA)
OSTI Identifier:
6787942
Report Number(s):
WHC-EP-0180
ON: DE89002163
DOE Contract Number:
AC06-87RL10930
Resource Type:
Technical Report
Resource Relation:
Other Information: Portions of this document are illegible in microfiche products
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; 11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; ENVIRONMENTAL IMPACTS; MITIGATION; RADIOACTIVE WASTE MANAGEMENT; IMPLEMENTATION; COMPLIANCE; HANFORD RESERVATION; MONITORING; PLANNING; REGULATIONS; MANAGEMENT; NATIONAL ORGANIZATIONS; US DOE; US ERDA; US ORGANIZATIONS; WASTE MANAGEMENT 052002* -- Nuclear Fuels-- Waste Disposal & Storage; 053000 -- Nuclear Fuels-- Environmental Aspects

Citation Formats

Not Available. Hanford Environmental Management Program implementation plan. United States: N. p., 1988. Web.
Not Available. Hanford Environmental Management Program implementation plan. United States.
Not Available. 1988. "Hanford Environmental Management Program implementation plan". United States. doi:.
@article{osti_6787942,
title = {Hanford Environmental Management Program implementation plan},
author = {Not Available},
abstractNote = {The Hanford Environmental Management Program (HEMP) was established to facilitate compliance with the applicable environmental statues, regulations, and standards on the Hanford Site. The HEMP provides a structured approach to achieve environmental management objectives. The Hanford Environmental Management Program Plan (HEMP Plan) was prepared as a strategic level planning document to describe the program management, technical implementation, verification, and communications activities that guide the HEMP. Four basic program objectives are identified in the HEMP Plan as follows: establish ongoing monitoring to ensure that Hanford Site operations comply with environmental requirements; attain regulatory compliance through the modification of activities; mitigate any environmental consequences; and minimize the environmental impacts of future operations at the Hanford Site. 2 refs., 24 figs., 27 tabs.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = 1988,
month = 8
}

Technical Report:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that may hold this item. Keep in mind that many technical reports are not cataloged in WorldCat.

Save / Share:
  • This plan documents the Project Hanford Management Contract (PHMC) Pollution Prevention/Waste Minimization (P2/WMin) Program. The subject implementation plan has been updated to reflect the Fiscal Year (FY) 1997 contract structure in which Fluor Daniel Hanford, Inc. (FDH) is the management and integration contractor. The P2/WMin Program scope includes FDH as the principal PHMC contractor, and B&W Hanford Company (BWHC), Duke Engineering & Services Hanford, Inc. (DESH), Lockheed Martin Hanford Corporation, (LMHC), Numatec Hanford Corporation (NHC), Rust Federal Services of Hanford, Inc. (RFSH), and DynCorp Tri-Cities Services, Inc. (DYN) as PHMC contractors, as well as subcontracting enterprise companies, such as Fluormore » Daniel Northwest, Inc. (FDNW), Lockheed Martin Services, Inc. (LMSI), and Rust Federal Services Northwest (RFS), which provide engineering, operation, construction, maintenance, and computer services for the Hanford Site. The P2/WMin Program scope also includes all other subcontractor-affiliated enterprise companies, such as B&W Protec, Inc. (BWP), DE&S Northwest, Inc. (DESNW), and SGN Eurisys Services Corp. (SESC).« less
  • During transition from the Westinghouse Hanford Company (WHC) Management and Operations (M and O) contract to the Fluor Daniel Hanford (FDH) Management and Integration (M and I) contract, existing WHC policies, procedures, and manuals were reviewed to determine which to adopt on an interim basis. Both WHC-SP-1131,Hanford Quality Assurance Program and Implementation Plan, and WHC-CM-4-2, Quality Assurance Manual, were adopted; however, it was recognized that revisions were required to address the functions and responsibilities of the Project Hanford Management Contract (PHMC). This Quality Assurance Program Implementation Plan for Nuclear Facilities (HNF-SP-1228) supersedes the implementation portion of WHC-SP-1 13 1, Rev.more » 1. The revised Quality Assurance (QA) Program is documented in the Project Hanford Quality Assurance Program Description (QAPD), HNF-MP-599. That document replaces the QA Program in WHC-SP-1131, Rev. 1. The scope of this document is limited to documenting the nuclear facilities managed by FDH and its Major Subcontractors (MSCS) and the status of the implementation of 10 CFR 830.120, Quality Assurance Requirements, at those facilities. Since the QA Program for the nuclear facilities is now documented in the QAPD, future updates of the information provided in this plan will be by letter. The layout of this plan is similar to that of WHC-SP-1 13 1, Rev. 1. Sections 2.0 and 3.0 provide an overview of the Project Hanford QA Program. A list of Project Hanford nuclear facilities is provided in Section 4.0. Section 5.0 provides the status of facility compliance to 10 CFR 830.120. Sections 6.0, 7.0, and 8.0 provide requested exemptions, status of open items, and references, respectively. The four appendices correspond to the four projects that comprise Project Hanford.« less
  • The Environmental Support FY 1998 Multi-Year Work Plan (MYWP), consisting of the Hanford Environmental Management Program (HEMP) and the Effluent and Environmental Monitoring (EEM) Program MYWP is prepared to specifically establish the execution year`s work scope, budget targets, and schedule baselines. The work plan contains the work breakdown structure (WBS) and the WBS dictionary, milestone listings and milestone description sheets, and cost targets that the program manager will use to manage program work for the fiscal year. Where activities required to maintain or attain compliance with environmental requirements and agreements are impacted as a result of a reduction of themore » authorized funds, the ``Work Authorization`` identifies the impacted scope and requires the Contracting Officer`s or Assistant Manager-Contracting Officer`s Representative signature. Change requests will be submitted to RL by the contractor for approval, further documenting the impacts of any environmental and agreement noncompliances as a result of funding limitations. This is the first year that the MYWPs are submitted under the new Project Hanford Management Contractor (PHMC). The MYWPs are structured differently than in prior years. The MYWP is divided into two main sections. Section One is titled the ``Project Summary Section`` and Section Two is titled the ``Additional Sections at the Project Baseline Summaries Level``. Section One is where the major project summary-level information is provided. Section Two is designed to detail the information for each Project Baseline Summary (PBS) that falls under the purview of the major project listed in Section One. Considering all of the PHMC MYWPs, the HEMP and EEM programs are the one exception to the above description. HEMP and EEM are two of five separate programs that are organized under one common PBS that is titled Mission Support (PBS {number_sign} RL-OT01). RL has given guidance that HEMP and EEM will be submitted as one common MYWP, exclusive of the other programs under the Mission Support PBS. This MYWP thus has a Section One that speaks to two programs, and two Section Two`s, one each for HEMP and EEM.« less
  • The Hanford Environmental Management Program (HEMP) was established in November 1986 by the US Department of Energy-Richland Operations Office (DOE-RL). Westinghouse Hanford Company (WHC) has been assigned responsibility to manage this program. The program`s goal is to integrate environmental activities such as reporting and planning and to facilitate compliance with environmental regulations. This document describes the scope of work funded by this program for Fiscal Year (FY) 1990, presents the prioritized tasks covered, the management structure in place and the assessment allocation methodology used to determine the FY 1990 assessments. 15 refs., 3 figs., 2 tabs.