The ORR operated at an average power level of 28.7 MW for 73.4 percent of the time during January, February, and March of 1978. Eight new fuel elements were placed in service. The reactor was shut down on sixteen occasions, one of which was unscheduled. Reactor downtime needed for refueling, maintenance and checks was quite low, with the reactor remaining available for operation 88.9 percent of the time. Maintenance activities, both mechanical and instrument were essentially routine in nature. Special tests or measurements completed during the quarter included: (1) reactivity measurement of the Metals and Ceramics Division's (ORR-MFE-1) experiment in CP-C7; (2) flux mapping for core No. 143-B; and (3) calibration of all six shim rods on February 12, 1978 (Appendix A), and calibration of shim rods Nos. 2 through 6 on February 16, 1978.

Research Organization:
Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)
DOE Contract Number:
W-7405-ENG-26
OSTI ID:
6761236
Report Number(s):
ORNL/TM-6447
Country of Publication:
United States
Language:
English