Reactor coolant (RC) pump seal failures have resulted in excessive leakage of primary coolant into reactor containment buildings. In some cases, high levels of airborne activity and surface contamination following these failures have necessitated extensive cleanup efforts and personnel radiation exposure. Unpredictable pump seal performance has also caused forced outages and frequent maintenance. The quality of operating data has been insufficient to allow proper evaluation of theoretical RC pump seal failure mechanisms. The RC pump monitoring and diagnostic system being developed and installed at Toledo Edison's Davis-Besse Nuclear Power Station will examine the relationship between seal failures and three other variables. This report describes system software and hardware development, testing, and installation work performed during the period of December 1981 through May 1982. Also described herein is a parallel effort being conducted by a B and W/Byron Jackson/Utility group to improve pump seal performance.

Research Organization:
Babcock and Wilcox Co., Lynchburg, VA (USA)
DOE Contract Number:
AC02-79ET34019
OSTI ID:
6535293
Report Number(s):
DOE/ET/34019-2; BAW-1746; ON: DE83007923
Resource Relation:
Other Information: Portions are illegible in microfiche products