Title: Oak Ridge Research Reactor quarterly report, July--September 1978

Abstract

The ORR operated at an average power level of 26.6 MW for 86,8% of the time during July, August, and September of 1978. The reactor was shut down on sixteen occasions, two of which were unscheduled. Reactor downtime needed for refueling, maintenance, and checks was normal, with the reactor remaining available for operation 89.0% of the time. Maintenance activities, both mechanical and instrument, were essentially routine in nature. The basic operating data presented; details relative to cycles of operation during the quarter are given.

Authors:
;
Publication Date:
Research Org.:
Oak Ridge National Lab., TN (USA)
OSTI Identifier:
6222311
Report Number(s):
ORNL/TM-6759
DOE Contract Number:  
W-7405-ENG-26
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS; ORR REACTOR; REACTOR OPERATION; REACTOR FUELING; REACTOR MAINTENANCE; ENRICHED URANIUM REACTORS; MAINTENANCE; OPERATION; REACTORS; TANK TYPE REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS; 220600* - Nuclear Reactor Technology- Research, Test & Experimental Reactors

Citation Formats

Hurt, S.S. III, and Lance, E.D. Oak Ridge Research Reactor quarterly report, July--September 1978. United States: N. p., 1979. Web.
Hurt, S.S. III, & Lance, E.D. Oak Ridge Research Reactor quarterly report, July--September 1978. United States.
Hurt, S.S. III, and Lance, E.D. Thu . "Oak Ridge Research Reactor quarterly report, July--September 1978". United States.
@article{osti_6222311,
title = {Oak Ridge Research Reactor quarterly report, July--September 1978},
author = {Hurt, S.S. III and Lance, E.D.},
abstractNote = {The ORR operated at an average power level of 26.6 MW for 86,8% of the time during July, August, and September of 1978. The reactor was shut down on sixteen occasions, two of which were unscheduled. Reactor downtime needed for refueling, maintenance, and checks was normal, with the reactor remaining available for operation 89.0% of the time. Maintenance activities, both mechanical and instrument, were essentially routine in nature. The basic operating data presented; details relative to cycles of operation during the quarter are given.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1979},
month = {2}
}

Technical Report:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that may hold this item. Keep in mind that many technical reports are not cataloged in WorldCat.

Save / Share: