Title: H-Coal Pilot Plant Phase II construction, Catlettsburg, Kentucky. Final construction management report, December 1976-February 1980. [February, 1977 to approximately January, 1980]

Technical Report ·
OSTI ID:5722386

This report covers the H-Coal Pilot Plant facility located in Catlettsburg, Kentucky. The authorization for this project was under DOE contract No. DE-AC05-78ET11052, formally ET-78-C-01-3224. Badger Plants, Inc. carried out the construction management of this facility. The estimated total cost is $147,265,013. A brief process/technical description of the Pilot Plant covers subjects such as objectives, capacity, expected life, etc. A brief technical description of each processing unit, including its purpose in the overall operations of the plant is given. A general description of the organizational history of the project is given. Current overall organization and a description of the responsibilities of each participant are included. Badger Plant's organization at manager level is shown.

Research Organization:
Badger Plants, Inc., Cambridge, MA (USA)
DOE Contract Number:
AC05-78ET11052
OSTI ID:
5722386
Report Number(s):
DOE/ET/11052-41; ON: DE83012413
Resource Relation:
Other Information: Portions are illegible in microfiche products. Original copy available until stock is exhausted
Country of Publication:
United States
Language:
English