Title: Niland development project geothermal loan guaranty: 49-MW (net) power plant and geothermal well field development, Imperial County, California: Environmental assessment

Abstract

The proposed federal action addressed by this environmental assessment is the authorization of disbursements under a loan guaranteed by the US Department of Energy for the Niland Geothermal Energy Program. The disbursements will partially finance the development of a geothermal well field in the Imperial Valley of California to supply a 25-MW(e) (net) power plant. Phase I of the project is the production of 25 MW(e) (net) of power; the full rate of 49 MW (net) would be achieved during Phase II. The project is located on approximately 1600 acres (648 ha) near the city of Niland in Imperial County, California. Well field development includes the initial drilling of 8 production wells for Phase I, 8 production wells for Phase II, and the possible need for as many as 16 replacement wells over the anticipated 30-year life of the facility. Activities associated with the power plant in addition to operation are excavation and construction of the facility and associated systems (such as cooling towers). Significant environmental impacts, as defined in Council on Environmental Quality regulation 40 CFR Part 1508.27, are not expected to occur as a result of this project. Minor impacts could include the following: local degradation of ambientmore » air quality due to particulate and/or hydrogen sulfide emissions, temporarily increased ambient noise levels due to drilling and construction activities, and increased traffic. Impacts could be significant in the event of a major spill of geothermal fluid, which could contaminate groundwater and surface waters and alter or eliminate nearby habitat. Careful land use planning and engineering design, implementation of mitigation measures for pollution control, and design and implementation of an environmental monitoring program that can provide an early indication of potential problems should ensure that impacts, except for certain accidents, will be minimized.« less

Publication Date:
Research Org.:
Oak Ridge National Lab., TN (USA)
OSTI Identifier:
5159626
Report Number(s):
DOE/EA-0247
ON: DE88008878
DOE Contract Number:
AC05-84OR21400
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
15 GEOTHERMAL ENERGY; GEOTHERMAL POWER PLANTS; ENVIRONMENTAL IMPACTS; AIR QUALITY; ECOLOGY; GEOTHERMAL WELLS; GROUND WATER; HYDROLOGY; LAND USE; LOAN GUARANTEES; NOISE; SOCIO-ECONOMIC FACTORS; ENVIRONMENTAL QUALITY; FINANCIAL ASSISTANCE; FINANCIAL INCENTIVES; FINANCING; HYDROGEN COMPOUNDS; INSTITUTIONAL FACTORS; OXYGEN COMPOUNDS; POWER PLANTS; THERMAL POWER PLANTS; WATER; WELLS; Geothermal Legacy

Citation Formats

Not Available. Niland development project geothermal loan guaranty: 49-MW (net) power plant and geothermal well field development, Imperial County, California: Environmental assessment. United States: N. p., 1984. Web. doi:10.2172/5159626.
Not Available. Niland development project geothermal loan guaranty: 49-MW (net) power plant and geothermal well field development, Imperial County, California: Environmental assessment. United States. doi:10.2172/5159626.
Not Available. Mon . "Niland development project geothermal loan guaranty: 49-MW (net) power plant and geothermal well field development, Imperial County, California: Environmental assessment". United States. doi:10.2172/5159626. https://www.osti.gov/servlets/purl/5159626.
@article{osti_5159626,
title = {Niland development project geothermal loan guaranty: 49-MW (net) power plant and geothermal well field development, Imperial County, California: Environmental assessment},
author = {Not Available},
abstractNote = {The proposed federal action addressed by this environmental assessment is the authorization of disbursements under a loan guaranteed by the US Department of Energy for the Niland Geothermal Energy Program. The disbursements will partially finance the development of a geothermal well field in the Imperial Valley of California to supply a 25-MW(e) (net) power plant. Phase I of the project is the production of 25 MW(e) (net) of power; the full rate of 49 MW (net) would be achieved during Phase II. The project is located on approximately 1600 acres (648 ha) near the city of Niland in Imperial County, California. Well field development includes the initial drilling of 8 production wells for Phase I, 8 production wells for Phase II, and the possible need for as many as 16 replacement wells over the anticipated 30-year life of the facility. Activities associated with the power plant in addition to operation are excavation and construction of the facility and associated systems (such as cooling towers). Significant environmental impacts, as defined in Council on Environmental Quality regulation 40 CFR Part 1508.27, are not expected to occur as a result of this project. Minor impacts could include the following: local degradation of ambient air quality due to particulate and/or hydrogen sulfide emissions, temporarily increased ambient noise levels due to drilling and construction activities, and increased traffic. Impacts could be significant in the event of a major spill of geothermal fluid, which could contaminate groundwater and surface waters and alter or eliminate nearby habitat. Careful land use planning and engineering design, implementation of mitigation measures for pollution control, and design and implementation of an environmental monitoring program that can provide an early indication of potential problems should ensure that impacts, except for certain accidents, will be minimized.},
doi = {10.2172/5159626},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Mon Oct 01 00:00:00 EDT 1984},
month = {Mon Oct 01 00:00:00 EDT 1984}
}

Technical Report:

Save / Share:
  • A comprehensive review and analysis is provided of the environmental consequences of (1) guaranteeing a load for the completion of the 64 MW well field and the 48 MW (net) power plant or (2) denying a guaranteed load that is needed to finish the project. Mitigation measures are discussed. Alternatives and their impacts are compared and some discussion is included on unavoidable adverse impacts. (MHR)
  • The action assessed is the guaranty of a loan by DOE to finance geothermal exploration, development, and testing by Mapco Geothermal, Inc. and Republic Geothermal, Inc. in the Westmorland area of Imperial County, California. Initial drilling and flow testing of up to three production wells will occur in the exploratory phase. Exploration is proposed for either or both of two portions of the leasehold area. If exploration confirms the presence of a viable resource in the Sweetwater area, the preferred site based on limited temperature data, then up to 19 new production wells and three new injection wells may bemore » drilled and tested there in preparation for the construction of a 55-MW double-flash electric power plant. If, however, the Sweetwater resource proves infeasible, further exploration and possible full-field development may occur instead at the Dearborn-Kalin-Landers area. At this site, up to 19 new production wells and three new injection wells may be drilled and tested, with six existing wells also used for injection. This environmental assessment chiefly addresses effects of the drilling and testing program. In summary, this paper discusses the proposed action, describes the existing environment and discusses the potential environmental impacts. 75 refs. (LSP)« less
  • The action assessed is the guaranty of a loan by the Geothermal Loan Guaranty Office of the US Department of Energy (DOE) to finance the construction and operation of a mushroom-growing facility that will use geothermal (hot) water for process and space heat. The project consists of two separate facilities: a growing facility located just outside of the eastern limit of the city of Vale, Oregon (Malheur County, Oregon) and a composting facility located about 6.4 km (4 miles) southwest of the city limits (also in Malheur County, Oregon). Five test wells have been drilled into the geothermal resource atmore » the growing site. Either well No. 4 or well No. 5 will serve as a production well. All geothermal fluids will be reinjected into the geothermal aquifer, so either well No. 3 will be used for this purpose, wells Nos. 1 and 2 will be deepened, or a new well will be drilled on the site. A cold-water well will be drilled at the growing site, and another will be drilled at the composting site. The environmental effects of the proposed project are not expected to be significant.« less
  • The guaranty program on electric and hybrid vehicle research, development, and demonstration considers two aspects of loan guaranties: (1) how is the loan guaranty, as an incentive device, best integrated into an overall project strategy, and (2) to what extent can cost-effectiveness measurements be introduced to the loan guaranty review and approval process. The report on the geothermal loan guaranty program is an overview of a large number of existing program elements which, in the opinion of the financial community or the historical record of predecessor loan guaranty programs, can be seen to be (or have potential to become) troublesome.more » Included are relevant administrative, regulatory, and managerial guidelines, commentary, and ideas. (MCW)« less
  • This water assessment report prepared under the provisions of Section 13(b) is an assessment of water requirements and water supply availability for a proposed Geothermal Demonstration Plant near Heber, California. It discusses (1) principal findings, (2) project description, (3) water supply and availability, and (4) effects of the project.