Title: Utility Advanced Turbine System (ATS) technology readiness testing and pre-commercial demonstration -- Phase 3. Quarterly report, April 1--June 30, 1996

Abstract

The overall objective of the Advanced Turbine System (ATS) Phase 3 Cooperative Agreement between GE and the US Department of Energy (DOE) is the development of the GE 7H and 9H combined cycle power systems. The major effort will be expended on detailed design. Validation of critical components and technologies will be performed including: hot gas path component testing, sub-scale compressor testing, steam purity test trials, and rotational heat transfer confirmation testing. Processes will be developed to support the manufacture of the first system, which will be sited and operated in Phase 4. Technology enhancements that are not required for the first machine design but will be critical for future ATS advances in performance, reliability, and costs will be initiated. Long-term tests of materials to confirm design life predictions will continue. This report summarizes work accomplished during the period 2Q96.

Publication Date:
Research Org.:
General Electric Co., Schenectady, NY (United States)
Sponsoring Org.:
USDOE Assistant Secretary for Fossil Energy, Washington, DC (United States)
OSTI Identifier:
486132
Report Number(s):
DOE/MC/31176-5660
ON: DE97052739; TRN: AHC29713%%79
DOE Contract Number:
FC21-95MC31176
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: [1996]
Country of Publication:
United States
Language:
English
Subject:
20 FOSSIL-FUELED POWER PLANTS; COMBINED-CYCLE POWER PLANTS; GAS TURBINES; PROGRESS REPORT; DESIGN; GAS COMPRESSORS; TURBINE BLADES

Citation Formats

NONE. Utility Advanced Turbine System (ATS) technology readiness testing and pre-commercial demonstration -- Phase 3. Quarterly report, April 1--June 30, 1996. United States: N. p., 1996. Web. doi:10.2172/486132.
NONE. Utility Advanced Turbine System (ATS) technology readiness testing and pre-commercial demonstration -- Phase 3. Quarterly report, April 1--June 30, 1996. United States. doi:10.2172/486132.
NONE. Tue . "Utility Advanced Turbine System (ATS) technology readiness testing and pre-commercial demonstration -- Phase 3. Quarterly report, April 1--June 30, 1996". United States. doi:10.2172/486132. https://www.osti.gov/servlets/purl/486132.
@article{osti_486132,
title = {Utility Advanced Turbine System (ATS) technology readiness testing and pre-commercial demonstration -- Phase 3. Quarterly report, April 1--June 30, 1996},
author = {NONE},
abstractNote = {The overall objective of the Advanced Turbine System (ATS) Phase 3 Cooperative Agreement between GE and the US Department of Energy (DOE) is the development of the GE 7H and 9H combined cycle power systems. The major effort will be expended on detailed design. Validation of critical components and technologies will be performed including: hot gas path component testing, sub-scale compressor testing, steam purity test trials, and rotational heat transfer confirmation testing. Processes will be developed to support the manufacture of the first system, which will be sited and operated in Phase 4. Technology enhancements that are not required for the first machine design but will be critical for future ATS advances in performance, reliability, and costs will be initiated. Long-term tests of materials to confirm design life predictions will continue. This report summarizes work accomplished during the period 2Q96.},
doi = {10.2172/486132},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Tue Dec 31 00:00:00 EST 1996},
month = {Tue Dec 31 00:00:00 EST 1996}
}

Technical Report:

Save / Share:
  • The overall objective of the Advanced Turbine System (ATS) Phase 3 Cooperative Agreement between GE and the US Department of Energy (DOE) is the development of the GE 7H and 9H combined cycle power systems. The major effort will be expended on detailed design. Validation of critical components and technologies will be performed including: hot gas path component testing, sub-scale compressor testing, steam purity test trials, and rotational heat transfer confirmation testing. Processes will be developed to support the manufacture of the first system, which will be sited and operated in Phase 4. Technology enhancements that are not required formore » the first machine design but will be critical for future ATS advances in performance, reliability, and costs will be initiated. Long-term tests of materials to confirm design life predictions will continue. This initial report summarizes work accomplished during the third quarter of 1995. The most significant accomplishments reported include the following. Overall design continued, progressing from preliminary and conceptual design activities to detailed design activities. The aerodynamic design of six out of eight 9H turbine airfoils was completed. The 9H compressor design concept was finalized including rotor configuration, aerodynamic design of compressor, and compressor structure. Conceptual on-base and external piping layout was begun. The ATS Phase 3 Cooperative Agreement was negotiated and signed.« less
  • This report covers the period April--June, 1996 for the utility advanced turbine systems (ATS) technical readiness testing and pre-commercial demonstration program. The topics of the report include NEPA information, ATS engine design, integrated program plan, closed loop cooling, thin wall casting development, rotor air sealing development, compressor aerodynamic development, turbine aerodynamic development, phase 3 advanced air sealing development, active tip clearance control, combustion system development, ceramic ring segment, advanced thermal barrier coating development, steam cooling effects, directionally solidified blade development, single crystal blade development program, advanced vane alloy development, blade and vane life prediction, nickel based alloy rotor, and plansmore » for the next reporting period.« less
  • The overall objective of the Advanced Turbine System (ATS) Phase 3 Cooperative Agreement between GE and the US Department of Energy (DOE) is the development of the GE 7H and 9H combined cycle power systems. The major effort will be expended on detail design. Validation of critical components and technologies will be performed including: hot gas path component testing, sub-scale compressor testing, steam purity test trials, and rotational heat transfer confirmation testing. Processes will be developed to support the manufacture of the first system, which will be sited and operated in Phase 4. Technology enhancements that are not required formore » the first machine design but will be critical for future ATS advances in performance, reliability, and costs will be initiated. Long-term tests of materials to confirm design life predictions will continue. A schematic of the GE H machine is shown. This report summarizes work accomplished in 2Q97.« less
  • The overall objective of the Advanced Turbine System (ATS) Phase 3 Cooperative Agreement between GE and the U.S. Department of Energy (DOE) is the development of the GE 7H and 9H combined cycle power systems. The major effort will be expended on detailed design. Validation of critical components and technologies will be performed including: hot gas path component testing, sub-scale compressor testing, steam purity test trials, and rotational heat transfer confirmation testing. Processes will be developed to support the manufacture of the first system, which will be sited and operated in Phase 4. Technology enhancements that are not required formore » the first machine design but will be critical for future ATS advances in performance reliability, and costs will be initiated. Long-term tests of materials to confirm design life predictions will continue.« less
  • Objective of ATS Phase 3 is development of GE 7H and 9H combined cycle power systems. This report summarizes work accomplished during the period 1Q96, including NEPA environmental information.