Title: APPR-1 SIX MONTH OPERATING CONTRACT REPORT

Abstract

The plant was operated principally for crew training and power output. Some limited research and development was also performed during the period. Two cases of loss of primary water to the vapor container sump were experienced. Both of these incidents involve safety relief valves. A total of 24 unscheduled or unexplained scrams were experienced during the six monihs operation. Of these, 13 were chargeable to instrumentation and the remaining to various other causes. A study of the operating performance does not show any indications of inability to operate these small plants with crew sizes originally projected or even smaller. (W. L. H.)

Authors:
;
Publication Date:
Research Org.:
Alco Products, Inc., Schenectady, N.Y.
OSTI Identifier:
4310221
Report Number(s):
APAE-28
NSA Number:
NSA-12-014226
DOE Contract Number:  
AT(11-1)-318
Resource Type:
Technical Report
Resource Relation:
Other Information: Orig. Receipt Date: 31-DEC-58
Country of Publication:
United States
Language:
English
Subject:
PHYSICS; CONTROL SYSTEMS; COOLANT LOOPS; ECONOMICS; EFFICIENCY; FAILURES; INSTRUMENTS; LEAKS; MEASURED VALUES; OPERATION; PACKAGING; PERFORMANCE; PERSONNEL; POWER PLANTS; REACTOR SAFETY; SHUTDOWN; SM-1; SM-1A; STEAM; TRANSPORT; VALVES; WATER COOLANT

Citation Formats

Weinberg, H.L., and Leslie, J.K. eds. APPR-1 SIX MONTH OPERATING CONTRACT REPORT. United States: N. p., 1958. Web. doi:10.2172/4310221.
Weinberg, H.L., & Leslie, J.K. eds. APPR-1 SIX MONTH OPERATING CONTRACT REPORT. United States. doi:10.2172/4310221.
Weinberg, H.L., and Leslie, J.K. eds. Fri . "APPR-1 SIX MONTH OPERATING CONTRACT REPORT". United States. doi:10.2172/4310221. https://www.osti.gov/servlets/purl/4310221.
@article{osti_4310221,
title = {APPR-1 SIX MONTH OPERATING CONTRACT REPORT},
author = {Weinberg, H.L. and Leslie, J.K. eds.},
abstractNote = {The plant was operated principally for crew training and power output. Some limited research and development was also performed during the period. Two cases of loss of primary water to the vapor container sump were experienced. Both of these incidents involve safety relief valves. A total of 24 unscheduled or unexplained scrams were experienced during the six monihs operation. Of these, 13 were chargeable to instrumentation and the remaining to various other causes. A study of the operating performance does not show any indications of inability to operate these small plants with crew sizes originally projected or even smaller. (W. L. H.)},
doi = {10.2172/4310221},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1958},
month = {4}
}