Abstract

Plant operation and maintenance are reviewed and analyzed, and certain recommendations for improvements are made. The in-plant training program is described, and comments deemed appropriate are made. Plant accounting is outlined, and comments are made on plant costs. Unitization and property records and spare parts stocks accounting systems are described. Research and development tasks completed or in progress are reviewed, and conclusions and recommendations are made. The maintenance and instruction manuals for the SM-1 are being revised and rearranged to serve as a guide for other pressurized water plants of this general size. (auth)

Publication Date:
Research Org.:
Alco Products, Inc., Schenectady, N.Y.; Alco Products, Inc., Fort Belvoir, Va.
OSTI Identifier:
4150826
Report Number(s):
APAE-47
NSA Number:
NSA-14-017591
DOE Contract Number:  
AT(30-3)-326
Resource Type:
Technical Report
Resource Relation:
Other Information: Orig. Receipt Date: 31-DEC-60
Country of Publication:
United States
Language:
English
Subject:
REACTOR TECHNOLOGY; ECONOMICS; MAINTENANCE; OPERATION; PERSONNEL; POWER PLANTS; PRESSURE; REACTORS; SM-1; WATER COOLANT; WATER MODERATOR

Citation Formats

None. ANNUAL REPORT, FEBRUARY 1958-FEBRUARY 1959. United States: N. p., 1959. Web. doi:10.2172/4150826.
None. ANNUAL REPORT, FEBRUARY 1958-FEBRUARY 1959. United States. doi:10.2172/4150826.
None. Tue . "ANNUAL REPORT, FEBRUARY 1958-FEBRUARY 1959". United States. doi:10.2172/4150826. https://www.osti.gov/servlets/purl/4150826.
@article{osti_4150826,
title = {ANNUAL REPORT, FEBRUARY 1958-FEBRUARY 1959},
author = {None},
abstractNote = {Plant operation and maintenance are reviewed and analyzed, and certain recommendations for improvements are made. The in-plant training program is described, and comments deemed appropriate are made. Plant accounting is outlined, and comments are made on plant costs. Unitization and property records and spare parts stocks accounting systems are described. Research and development tasks completed or in progress are reviewed, and conclusions and recommendations are made. The maintenance and instruction manuals for the SM-1 are being revised and rearranged to serve as a guide for other pressurized water plants of this general size. (auth)},
doi = {10.2172/4150826},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1959},
month = {6}
}