Title: Acceptance Test Report for 241-U compressed air system

Abstract

This Acceptance Test Report (ATR) documents the results of acceptance testing of a newly upgraded compressed air system at 241-U Farm. The system was installed and the test successfully performed under work package 2W-92-01027.

Authors:
Publication Date:
Research Org.:
Westinghouse Hanford Co., Richland, WA (United States)
Sponsoring Org.:
USDOE, Washington, DC (United States)
OSTI Identifier:
26577
Report Number(s):
WHC-SD-WM-ATR-066
ON: DE95006828; TRN: 95:008256
DOE Contract Number:
AC06-87RL10930
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 20 Oct 1994
Country of Publication:
United States
Language:
English
Subject:
05 NUCLEAR FUELS; HANFORD RESERVATION; RADIOACTIVE WASTE MANAGEMENT; RADIOACTIVE WASTES; UNDERGROUND STORAGE; TANKS; PIPES; MAINTENANCE; INSPECTION; HEAT PUMPS; COMPRESSED AIR

Citation Formats

Freeman, R.D.. Acceptance Test Report for 241-U compressed air system. United States: N. p., 1994. Web. doi:10.2172/26577.
Freeman, R.D.. Acceptance Test Report for 241-U compressed air system. United States. doi:10.2172/26577.
Freeman, R.D.. Thu . "Acceptance Test Report for 241-U compressed air system". United States. doi:10.2172/26577. https://www.osti.gov/servlets/purl/26577.
@article{osti_26577,
title = {Acceptance Test Report for 241-U compressed air system},
author = {Freeman, R.D.},
abstractNote = {This Acceptance Test Report (ATR) documents the results of acceptance testing of a newly upgraded compressed air system at 241-U Farm. The system was installed and the test successfully performed under work package 2W-92-01027.},
doi = {10.2172/26577},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Thu Oct 20 00:00:00 EDT 1994},
month = {Thu Oct 20 00:00:00 EDT 1994}
}

Technical Report:

Save / Share:
  • The 241-U-701 compressed air system supplies instrument quality compressed air to Tank Farm 241-U. The system was upgraded. The operability test showed that the system operates within its intended design parameters. System performance was monitored, recorded, and used to identify areas of concern. Exceptions to the OTP and additional items for safe system performance were minimal and have been resolved; the air system is ready for Operation`s use.
  • The 241-U-701 compressed air system supplies instrument quality compressed air to Tank Farm 241-U. The supply piping to the 241-U Tank Farm is not included in the modification. Modifications to the 241-U-701 compressed air system include installation of a 15 HP Reciprocating Air Compressor, Ingersoll-Rand Model 10T3NLM-E15; an air dryer, Hankinson, Model DH-45; and miscellaneous system equipment and piping (valves, filters, etc.) to meet the design. A newly installed heat pump allows the compressor to operate within an enclosed relatively dust free atmosphere and keeps the compressor room within a standard acceptable temperature range, which makes possible efficient compressor operation,more » reduces maintenance, and maximizes compressor operating life. This document is an Operability Test Procedure (OTP) which will further verify (in addition to the Acceptance Test Procedure) that the 241-U-701 compressed air system and heat pump operate within their intended design parameters. The activities defined in this OTP will be performed to ensure the performance of the new compressed air system will be adequate, reliable and efficient. Completion of this OTP and sign off of the OTP Acceptance of Test Results is necessary for turnover of the compressed air system from Engineering to Operations.« less
  • This Acceptance Test Report (ATR) provides the record of the results of acceptance testing of the instrument air compressor, air dryer, and filtering system located in 241-T-701.
  • The acceptance test procedure (ATP) for the compressed air system at building 241-AW-273 was completed on March 11, 1993. The system was upgraded to provide a reliable source of compressed air to the tank farm. The upgrade included the demolition of the existing air compressor and associated piping, as well as the installation of a new air compressor with a closed loop cooling system. A compressed air cross-tie was added to allow the process air compressor to function as a back-up to the existing instrument air compressor. The purpose of the ATP was to achieve three primary objectives: verify systemmore » upgrade in accordance with the design media; provide functional test of system components and controls; and prepare the system for the Operational Test. The ATP was successfully completed with thirteen exceptions, which were resolved prior to completing the acceptance test. The repaired exceptions had no impact to safety or the environment and are briefly summarized. Testing ensured that the system was installed per design, that its components function as required and that it is ready for operational testing and subsequent turnover to operations.« less
  • This Operability Test Report (OTR) documents the results of functional testing performed on the operating parameters of the 241-T-701 Compressed Air System. The System was successfully installed and tested per work package 2W-92-01172.