Title: Facilitating submetering implementation. Final report

Abstract

Residential submetering is the measurement and billing of electric use in individual apartments in master-metered buildings. In master-metered building situations, residents do not bear electricity costs in proportion to consumption levels. As a result, studies have confirmed that residents in master-metered buildings tend to consume more electricity than residents with individual apartment metering, and have established electrical submetering as an effective energy conservation measure. The New York State Energy Research & Development Authority (NYSERDA) has commissioned a project called Facilitating Submetering Implementation to identify and analyze barriers to the implementation of residential electrical submetering in New York and to formulate recommendations that would facilitate the removal of these barriers, streamlining the process. Experienced professionals in the technical, legal, regulatory, analytical, financial, and other aspects of submetering were retained to interview key interested parties and conduct public forums. This and other data were then analyzed to ascertain the barriers to submetering and develop recommendations designed to reduce or eliminate these barriers. The key barriers to submetering implementation were found to be the Public Service Commission (PSC) requirement for a vote of a majority of shareholders (for coops and condos) and the high initial cost that cannot easily be recouped by ownersmore » of both rental and shareholder-owned buildings. The key recommendations are to repeal the voting requirement, maintain the utility incentives, adopt a uniform dispute resolution mechanism, and increase awareness through an Ad-hoc Submetering Committee and supporting educational materials. Other funding sources not fully available can also be made available with regulatory agency support.« less

Authors:
Publication Date:
Research Org.:
New York State Energy Research and Development Authority, Albany, NY (United States)
Sponsoring Org.:
New York State Energy Research and Development Authority, Albany, NY (United States)
OSTI Identifier:
249286
Report Number(s):
NYSERDA-96-7
ON: TI96011728; TRN: 96:003868
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: May 1996
Country of Publication:
United States
Language:
English
Subject:
32 ENERGY CONSERVATION, CONSUMPTION, AND UTILIZATION; 29 ENERGY PLANNING AND POLICY; APARTMENT BUILDINGS; ENERGY CONSERVATION; ELECTRICITY; METERING; NEW YORK; RECOMMENDATIONS; MASTER METERING; LEGAL ASPECTS; MODIFICATIONS

Citation Formats

Bowers, M.A. Facilitating submetering implementation. Final report. United States: N. p., 1996. Web. doi:10.2172/249286.
Bowers, M.A. Facilitating submetering implementation. Final report. United States. doi:10.2172/249286.
Bowers, M.A. Wed . "Facilitating submetering implementation. Final report". United States. doi:10.2172/249286. https://www.osti.gov/servlets/purl/249286.
@article{osti_249286,
title = {Facilitating submetering implementation. Final report},
author = {Bowers, M.A.},
abstractNote = {Residential submetering is the measurement and billing of electric use in individual apartments in master-metered buildings. In master-metered building situations, residents do not bear electricity costs in proportion to consumption levels. As a result, studies have confirmed that residents in master-metered buildings tend to consume more electricity than residents with individual apartment metering, and have established electrical submetering as an effective energy conservation measure. The New York State Energy Research & Development Authority (NYSERDA) has commissioned a project called Facilitating Submetering Implementation to identify and analyze barriers to the implementation of residential electrical submetering in New York and to formulate recommendations that would facilitate the removal of these barriers, streamlining the process. Experienced professionals in the technical, legal, regulatory, analytical, financial, and other aspects of submetering were retained to interview key interested parties and conduct public forums. This and other data were then analyzed to ascertain the barriers to submetering and develop recommendations designed to reduce or eliminate these barriers. The key barriers to submetering implementation were found to be the Public Service Commission (PSC) requirement for a vote of a majority of shareholders (for coops and condos) and the high initial cost that cannot easily be recouped by owners of both rental and shareholder-owned buildings. The key recommendations are to repeal the voting requirement, maintain the utility incentives, adopt a uniform dispute resolution mechanism, and increase awareness through an Ad-hoc Submetering Committee and supporting educational materials. Other funding sources not fully available can also be made available with regulatory agency support.},
doi = {10.2172/249286},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Wed May 01 00:00:00 EDT 1996},
month = {Wed May 01 00:00:00 EDT 1996}
}

Technical Report:

Save / Share: