Engineering development of advanced coal-fired low-emission boiler systems. Technical progress report No. 12, July--September 1995
The overall objective of the Project is the expedited commercialization of advanced coal-fired low-emission boiler systems. The goals for emissions and plant efficiency are: NO{sub x} emissions not greater than 0.1 lb/million Btu; SO{sub x} emissions not greater than 0.1 lb/million Btu; particulate emissions not greater than 0.01 lb/million Btu; and net plant efficiency (HHV basis) not less than 42%. Other goals include: improved ash disposability and reduced waste generation; and reduced air toxics emissions. The final deliverables are a design data base that will allow future coal-fired power plants to meet the stated objectives, and a preliminary design of a Commercial Generation Unit. The work in Phase I covered a 24- month period and included system analysis, RD&T Plan formulation, component definition, and preliminary Commercial Generating Unit (CGU) design. Phase II will cover a 15-month period and will include preliminary Proof-of-Concept Test Facility (POCTF) design and subsystem testing. Phase III will cover a 9-month period and will produce a revised CGU design and a revised POCTF design, cost estimate and a test plan. Phase IV, the final Phase, will cover a 36- month period and will include POCTF detailed design, construction, testing, and evaluation.
- Research Organization:
- ABB Combustion Engineering, Inc., Windsor, CT (United States). ABB Power Plant Labs.
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC22-92PC92159
- OSTI ID:
- 206852
- Report Number(s):
- DOE/PC/92159-T14; ON: DE96007728
- Resource Relation:
- Other Information: PBD: 27 Nov 1995
- Country of Publication:
- United States
- Language:
- English
Similar Records
Engineering development of advanced coal-fired low-emission boiler systems. Technical progress report No. 9, September 1994--December 1994
Engineering development of advanced coal-fired low-emission boiler systems. Quarterly report, April 1--June 30, 1997