Effects of Local Permitting and Interconnection Requirements on Solar PV Installation Durations

Journal Article · · Energy Policy

Most rooftop solar photovoltaic (PV) systems must be reviewed and approved by local governments and electric service providers prior to operation. These permitting, inspection, and interconnection (PII) requirements help ensure safe PV system installation and operation, but onerous requirements may needlessly delay construction and operation. Here, we analyze PV PII data to understand the effects of local PII requirements on PV process durations. We combine data on local PII requirements with estimates of process durations for 248,741 PV systems installed in the United States. The data show that local variations in PII requirements can partly explain variations in PV process durations. Requirements that would be expected to reduce durations - such as instant online approvals - are generally associated with shorter durations, while requirements that would be expected to increase durations - such as structural reviews - are associated with longer durations. We find only weak evidence that measures to expedite pre-install processes result in post-install delays, and similarly find only weak evidence that increased pre-install PII oversight can save time in post-install stages. Our results provide further rationale for PII authorities to analyze their requirements and identify opportunities to streamline PII processes.

Research Organization:
National Renewable Energy Lab. (NREL), Golden, CO (United States)
Sponsoring Organization:
USDOE Office of Energy Efficiency and Renewable Energy (EERE), Renewable Power Office. Solar Energy Technologies Office
DOE Contract Number:
AC36-08GO28308
OSTI ID:
1837972
Report Number(s):
NREL/JA-6A20-81645; MainId:82418; UUID:88b70b81-f86e-4bf6-bf32-dab70be357c5; MainAdminID:63493
Journal Information:
Energy Policy, Vol. 161
Country of Publication:
United States
Language:
English

References (10)

Duration Models and Proportional Hazards in Political Science October 2001
Exploring the impact of permitting and local regulatory processes on residential solar prices in the United States March 2015
Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry September 2021
Regression Models and Life-Tables January 1972
The impact of city-level permitting processes on residential photovoltaic installation prices and development times: An empirical analysis of solar systems in California cities December 2013
Time-Dependent Covariates in the cox Proportional-Hazards Regression Model May 1999
Predictors for adoption of local solar approval processes and impact on residential solar installations in California cities June 2018
Patience is a virtue: A data-driven analysis of rooftop solar PV permitting timelines in the United States September 2020
Increasing residential solar installations in California: Have local permitting processes historically driven differences between cities? January 2019
DeepSolar: A Machine Learning Framework to Efficiently Construct a Solar Deployment Database in the United States December 2018