National Ignition Facility start-up/operations engineering and special equipment construction health and safety plan
Abstract
This document sets forth the responsibilities, interfaces, guidelines, rules, policy, and regulations for all workers involved in the S/O and SE construction, installation, and acceptance testing. This document is enforced from the first day that S/O and SE workers set foot on the NIF construction site until the end of the Project at Critical Decision 4. This document is applicable only to site activities, which are defined as those that occur within the perimeter of the fenced-off NIF construction zone and the Target Chamber Assembly Area (Helipad). The associated Special Equipment laydown and construction support areas listed in Appendix B are not under this plan; their safety provisions are discussed in the Appendix. Prototype and other support activities, such as the Amplifier Laboratory and Frame Assembly Unit assembly area, are not included in this plan. After completion of the Operational Readiness Review, the Facility Safety Procedure, Operational Safety Requirements, and Operational Safety Procedures are the governing safety documents for the operating facility. The S/O and SE project elements are required to implement measures that create a universal awareness of and promote safe job practices at the site. This includes all Lawrence Livermore National Laboratory (LLNL), Los Alamos National Laboratory, Sandiamore »
- Authors:
- Publication Date:
- Research Org.:
- Lawrence Livermore National Lab., CA (US)
- Sponsoring Org.:
- USDOE Office of Defense Programs (DP) (US)
- OSTI Identifier:
- 14772
- Report Number(s):
- UCRL-ID-127610-Rev-1; 39DP02000
39DP02000; TRN: US0106789
- DOE Contract Number:
- W-7405-ENG-48
- Resource Type:
- Technical Report
- Resource Relation:
- Other Information: PBD: 8 May 1998
- Country of Publication:
- United States
- Language:
- English
- Subject:
- 70 PLASMA PHYSICS AND FUSION TECHNOLOGY; AMPLIFIERS; CONSTRUCTION; REGULATIONS; OCCUPATIONAL SAFETY; TARGET CHAMBERS; TESTING; US NATIONAL IGNITION FACILITY
Citation Formats
Huddleston, P C. National Ignition Facility start-up/operations engineering and special equipment construction health and safety plan. United States: N. p., 1998.
Web. doi:10.2172/14772.
Huddleston, P C. National Ignition Facility start-up/operations engineering and special equipment construction health and safety plan. United States. doi:10.2172/14772.
Huddleston, P C. Fri .
"National Ignition Facility start-up/operations engineering and special equipment construction health and safety plan". United States.
doi:10.2172/14772. https://www.osti.gov/servlets/purl/14772.
@article{osti_14772,
title = {National Ignition Facility start-up/operations engineering and special equipment construction health and safety plan},
author = {Huddleston, P C},
abstractNote = {This document sets forth the responsibilities, interfaces, guidelines, rules, policy, and regulations for all workers involved in the S/O and SE construction, installation, and acceptance testing. This document is enforced from the first day that S/O and SE workers set foot on the NIF construction site until the end of the Project at Critical Decision 4. This document is applicable only to site activities, which are defined as those that occur within the perimeter of the fenced-off NIF construction zone and the Target Chamber Assembly Area (Helipad). The associated Special Equipment laydown and construction support areas listed in Appendix B are not under this plan; their safety provisions are discussed in the Appendix. Prototype and other support activities, such as the Amplifier Laboratory and Frame Assembly Unit assembly area, are not included in this plan. After completion of the Operational Readiness Review, the Facility Safety Procedure, Operational Safety Requirements, and Operational Safety Procedures are the governing safety documents for the operating facility. The S/O and SE project elements are required to implement measures that create a universal awareness of and promote safe job practices at the site. This includes all Lawrence Livermore National Laboratory (LLNL), Los Alamos National Laboratory, Sandia National Laboratories, University of Rochester, supplement labor organization, and subcontractor employees; visitors; and guests serving the S/O and SE effort.},
doi = {10.2172/14772},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Fri May 08 00:00:00 EDT 1998},
month = {Fri May 08 00:00:00 EDT 1998}
}
-
The purpose of this plan is to identify how the construction and deployment activities of the National Ignition Facility (NIF) Special Equipment (SE) will be safely executed. This plan includes an identification of (1) the safety-related responsibilities of the SE people and their interaction with other organizations involved; (2) safety related requirements, policies, and documentation; (3) a list of the potential hazards unique to SE systems and the mechanisms that will be implemented to control them to acceptable levels; (4) a summary of Environmental Safety and Health (ES&H) training requirements; and (5) requirements of contractor safety plans that will bemore »
-
National ignition facility environment, safety, and health management plan
The ES&H Management Plan describes all of the environmental, safety, and health evaluations and reviews that must be carried out in support of the implementation of the National Ignition Facility (NIF) Project. It describes the policy, organizational responsibilities and interfaces, activities, and ES&H documents that will be prepared by the Laboratory Project Office for the DOE. The only activity not described is the preparation of the NIF Project Specific Assessment (PSA), which is to be incorporated into the Programmatic Environmental Impact Statement for Stockpile Stewardship and Management (PEIS). This PSA is being prepared by Argonne National Laboratory (ANL) with inputmore » -
Construction safety program for the National Ignition Facility Appendix A: Safety Requirements
These rules apply to all LLNL employees, non-LLNL employees (including contract labor, supplemental labor, vendors, personnel matrixed/assigned from other National Laboratories, participating guests, visitors and students) and construction contractors/subcontractors. The General Safety and Health rules shall be used by management to promote accident prevention through indoctrination, safety and health training and on-the-job application. As a condition for contracts award, all contractors and subcontractors and their employees must certify on Form S & H A-1 that they have read and understand, or have been briefed and understand, the National Ignition Facility OCIP Project General Safety Rules. -
National Ignition Facility (NIF) operations procedures plan
The purpose of this Operations Procedures Plan is to establish a standard procedure which outlines how NIF Operations procedures will be developed (i.e , written, edited, reviewed, approved, published, revised) and accessed by the NIF Operations staff who must use procedures in order to accomplish their tasks. In addition, this Plan is designed to provide a guide to the NIF Project staff to assist them in planning and writing procedures. Also, resource and scheduling information is provided. -
National Ignition Facility wet weather construction plan
This report presents a wet weather construction plan for the National Ignition Facility (NIF) construction project. Construction of the NIF commenced in mid- 1997, and excavation of the site was completed in the fall. Preparations for placing concrete foundations began in the fall, and above normal rainfall is expected over the tinter. Heavy rainfall in late November impacted foundation construction, and a wet weather construction plan was determined to be needed. This wet weather constiction plan recommends a strategy, techniques and management practices to prepare and protect the site corn wet weather effects and allow construction work to proceed. Itmore »