Title: RELAP-7 Software Verification and Validation Plan: Requirements Traceability Matrix (RTM) Update and Code Verification Strategy

Abstract

This document describes the recent progress of the RELAP-7 Software Verification and Validation Plan (SVVP). The RELAP-7 RTM has been updated by adding the validation requirement items, rearranging the requirement items, and introducing the classifier to better describe the RELAP-7 V&V status at a specified point in time. Also, from the perspective of nuclear system code validation, six items from the list of LWR safety-relevant phenomena were identified as validation data gaps. Lastly, motivated by the needs revealed from the previous RELAP-7 IV&V activities, the independent verification plan for RELAP-7 has been established. The verification method, procedure, and verification test coverage suite discussed in this document will be applied to the future work for the RELAP-7 independent verification.

Authors:
 [1];  [1]
  1. Idaho National Lab. (INL), Idaho Falls, ID (United States)
Publication Date:
Research Org.:
Idaho National Lab. (INL), Idaho Falls, ID (United States)
Sponsoring Org.:
USDOE Office of Nuclear Energy (NE)
OSTI Identifier:
1468537
Report Number(s):
INL/EXT-17-43199-Rev000
DOE Contract Number:  
AC07-05ID14517
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
42 ENGINEERING; RELAP-7; Requrement Traceability Matrix (RTM); Independent code verification

Citation Formats

Yoo, Junsoo, and Choi, Yong -Joon. RELAP-7 Software Verification and Validation Plan: Requirements Traceability Matrix (RTM) Update and Code Verification Strategy. United States: N. p., 2017. Web. doi:10.2172/1468537.
Yoo, Junsoo, & Choi, Yong -Joon. RELAP-7 Software Verification and Validation Plan: Requirements Traceability Matrix (RTM) Update and Code Verification Strategy. United States. doi:10.2172/1468537.
Yoo, Junsoo, and Choi, Yong -Joon. Fri . "RELAP-7 Software Verification and Validation Plan: Requirements Traceability Matrix (RTM) Update and Code Verification Strategy". United States. doi:10.2172/1468537. https://www.osti.gov/servlets/purl/1468537.
@article{osti_1468537,
title = {RELAP-7 Software Verification and Validation Plan: Requirements Traceability Matrix (RTM) Update and Code Verification Strategy},
author = {Yoo, Junsoo and Choi, Yong -Joon},
abstractNote = {This document describes the recent progress of the RELAP-7 Software Verification and Validation Plan (SVVP). The RELAP-7 RTM has been updated by adding the validation requirement items, rearranging the requirement items, and introducing the classifier to better describe the RELAP-7 V&V status at a specified point in time. Also, from the perspective of nuclear system code validation, six items from the list of LWR safety-relevant phenomena were identified as validation data gaps. Lastly, motivated by the needs revealed from the previous RELAP-7 IV&V activities, the independent verification plan for RELAP-7 has been established. The verification method, procedure, and verification test coverage suite discussed in this document will be applied to the future work for the RELAP-7 independent verification.},
doi = {10.2172/1468537},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2017},
month = {9}
}