Title: Final Report for the Contractor Readiness Assessment of the Transient Reactor Test Facility Resumption of Transient Testing Activity at the Idaho National Laboratory

Technical Report ·
DOI:https://doi.org/10.2172/1468428· OSTI ID:1468428
 [1]
  1. AECOM, Los Angeles, CA (United States)

The purpose of this review was to verify readiness for the TREAT restart of transient testing activity at the INL and inform the startup authorization authority decision-making for startup authorization by providing a deliberate and managed determination of the state of readiness preparation and determination of whether operations can be performed safely. Verification of readiness included assuring that equipment operability, procedure viability, and personnel knowledge, skills, and performance are adequate for operations. Because the TREAT (including restart of transient testing activity) is a hazard category-2 nuclear facility and because reactor operation and transient testing activities were suspended for programmatic and funding reasons in excess of a year, DOE O 425.1D required that both a contractor and DOE RA be satisfactorily completed prior to startup of the TREAT and restart of transient testing activity. To this end, DOE directed that a CRA and federal RA be conducted. The CRA IP defined the depth of the CRA through the objectives and CRADs, delineated in Appendix A of the IP; established roles and responsibilities for CRA team activities; and established processes, practices, and protocols for preparation, conduct, documentation, and reporting of the CRA. The approaches and methodologies identified in the IP were used to verify that the BEA management team has established SSCs, developed personnel capabilities and competencies, and implemented safety features, programs, and procedures in a manner that provides reasonable assurance for adequate protection of workers, the public, and the environment in preparation for and execution of the TREAT restart of transient testing activity. This CRA was intended to confirm that (1) the facility is in a state of readiness to safely conduct operations in accordance with the safety basis; and (2) the management control programs are in place to ensure safe operations can be sustained. This equated to mature implementation of the integrated safety management (ISM) in conjunction with implementation of the individual facility authorization basis. This CRA was structured to verify the readiness to conduct restart of transient testing activity safely, and that facility programs were in place to support the restart of transient testing activity.

Research Organization:
Idaho National Lab. (INL), Idaho Falls, ID (United States)
Sponsoring Organization:
USDOE Office of Nuclear Energy (NE)
DOE Contract Number:
AC07-05ID14517
OSTI ID:
1468428
Report Number(s):
INL/EXT-17-42207-Rev000; TRN: US1902782
Country of Publication:
United States
Language:
English