Title: Designing a Successful Transportation Project: Lessons Learned from the Clean Cities American Recovery and Reinvestment Act Projects

Abstract

The largest source of funding for alternative fuel vehicle and infrastructure projects in the U.S. Department of Energy's Clean Cities program's history came from the American Recovery and Reinvestment Act (Recovery Act). In 2009, the 25 cost-share projects totaled nearly $300 million in federal government investment. This effort included the involvement of 50 Clean Cities coalitions and their nearly 700 stakeholder partners who provided an additional $500 million in matching funds to support projects in their local communities. In total, those 25 projects established 1,380 alternative fueling stations and put more than 9,000 alternative fuel and advanced technology vehicles on the road. Together, these projects displaced 154 million gasoline gallon equivalents (GGE) of petroleum and averted 254,000 tons of greenhouse gas (GHG) emissions, while supporting U.S. energy independence and contributing to regional economic development. During post-project interviews, project leaders consistently cited a number of key components - ranging from technical and logistical factors, to administrative capabilities - for accomplishing an effective and impactful project. This report summarizes the high-level project design and administrative considerations for conducting a successful transportation project.

Authors:
;
Publication Date:
Research Org.:
National Renewable Energy Laboratory, Golden, Colorado
Sponsoring Org.:
USDOE Office of Energy Efficiency and Renewable Energy (EERE), Vehicle Technologies Office (EE-3V) (Clean Cities)
OSTI Identifier:
1413018
Report Number(s):
DOE/GO-102017-4955
7782
Resource Type:
Program Document
Country of Publication:
United States
Language:
English
Subject:
arra, doe, recovery act,clean cities, alternative fuel, afv, gge, ghg,

Citation Formats

Kelly, K., and Singer, M. Designing a Successful Transportation Project: Lessons Learned from the Clean Cities American Recovery and Reinvestment Act Projects. United States: N. p., 2017. Web.
Kelly, K., & Singer, M. Designing a Successful Transportation Project: Lessons Learned from the Clean Cities American Recovery and Reinvestment Act Projects. United States.
Kelly, K., and Singer, M. 2017. "Designing a Successful Transportation Project: Lessons Learned from the Clean Cities American Recovery and Reinvestment Act Projects". United States. doi:. https://www.osti.gov/servlets/purl/1413018.
@article{osti_1413018,
title = {Designing a Successful Transportation Project: Lessons Learned from the Clean Cities American Recovery and Reinvestment Act Projects},
author = {Kelly, K. and Singer, M.},
abstractNote = {The largest source of funding for alternative fuel vehicle and infrastructure projects in the U.S. Department of Energy's Clean Cities program's history came from the American Recovery and Reinvestment Act (Recovery Act). In 2009, the 25 cost-share projects totaled nearly $300 million in federal government investment. This effort included the involvement of 50 Clean Cities coalitions and their nearly 700 stakeholder partners who provided an additional $500 million in matching funds to support projects in their local communities. In total, those 25 projects established 1,380 alternative fueling stations and put more than 9,000 alternative fuel and advanced technology vehicles on the road. Together, these projects displaced 154 million gasoline gallon equivalents (GGE) of petroleum and averted 254,000 tons of greenhouse gas (GHG) emissions, while supporting U.S. energy independence and contributing to regional economic development. During post-project interviews, project leaders consistently cited a number of key components - ranging from technical and logistical factors, to administrative capabilities - for accomplishing an effective and impactful project. This report summarizes the high-level project design and administrative considerations for conducting a successful transportation project.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = 2017,
month = 9
}

Program Document:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that may hold this item.

Save / Share:
  • The largest source of funding for alternative fuel vehicle and infrastructure projects in the U.S. Department of Energy's Clean Cities program's history came from the American Recovery and Reinvestment Act (Recovery Act). In 2009, the 25 cost-share projects totaled nearly $300 million in federal government investment. This effort included the involvement of 50 Clean Cities coalitions and their nearly 700 stakeholder partners who provided an additional $500 million in matching funds to support projects in their local communities. In total, those 25 projects established 1,380 alternative fueling stations and put more than 9,000 alternative fuel and advanced technology vehicles onmore » the road. Together, these projects displaced 154 million gasoline gallon equivalents (GGE) of petroleum and averted 254,000 tons of greenhouse gas (GHG) emissions, while supporting U.S. energy independence and contributing to regional economic development. During post-project interviews, project leaders consistently cited a number of key components - ranging from technical and logistical factors, to administrative capabilities - for accomplishing an effective and impactful project. This report summarizes the high-level project design and administrative considerations for conducting a successful transportation project.« less
  • Utilizing funding provided by the American Recovery and Reinvestment Act (ARRA), the Liquid Waste Program at Savannah River site successfully executed forty-one design, procurement, construction, and operating activities in the period from September 2009 through December 2011. Project Management of the program included noteworthy practices involving safety, integrated project teams, communication, and cost, schedule and risk management. Significant upgrades to plant capacity, progress toward waste tank closure and procurement of needed infrastructure were accomplished. Over 1.5 million hours were worked without a single lost work day case. Lessons Learned were continually identified and applied to enhance the program. Investment ofmore » Recovery Act monies into the Liquid Waste Program has ensured continued success in the disposition of radioactive wastes and the closure of high level waste tanks at SRS. The funding of a portion of the Liquid Waste Program at SRS by ARRA was a major success. Significant upgrades to plant capacity, progress toward waste tank closure and procurement of needed infrastructure was accomplished. Integrated Project Teams ensured quality products and services were provided to the Operations customers. Over 1.5 million hours were worked without a single lost work day case. Lessons Learned were continually reviewed and reapplied to enhance the program. Investment of Recovery Act monies into the Liquid Waste Program has ensured continued success in the disposition of radioactive wastes and the closure of high level waste tanks at SRS. (authors)« less
  • Each Clean Cities project award under the American Recovery and Reinvestment Act included a diverse group of stakeholders who worked together to lay the foundation for their communities to adopt alternative fuels and petroleum reduction strategies. This document provides a snapshot of the impact of each project and highlights the partners and Clean Cities coalitions who helped transform local and regional transportation markets through 25 projects impacting 45 states.
  • The Hanford Site presents unique challenges in meeting the U.S. Department of Energy Richland Operations Office (DOE-RL) 2015 Cleanup Vision. CH2M Hill Plateau Remediation Company (CHPRC), its subcontractors, and DOE-RL were challenged to retrieve, transport and remediate a wide range of waste materials. Through a collaborative effort by all Hanford Onsite Central Plateau Cleanup Team Members, disposition pathways for diverse and seemingly impossible to ship wastes were developed under a DOE Order 460.1C-compliant Hanford Onsite Transportation Safety Program. The team determined an effective method for transporting oversized compliant waste payloads to processing and disposition facilities. The use of the onsitemore » TSD packaging authorizations proved to be vital to safely transporting these materials for processing and eventual final disposition. The American Recovery and Reinvestment Act of 2009 (ARRA) provided additional resources to expedite planning and execution of these important cleanup milestones. Through the innovative and creative use of the TSD, the Hanford Onsite Central Plateau Cleanup Team Members have developed and are executing an integrated project plan that enables the safe and compliant transport of a wide variety of difficult-to-transport waste items, accelerating previous cleanup schedules to meet cleanup milestones. (authors)« less
  • In April 2009, the Department of Energy (DOE) Richland Operations Office (RL) was allocated $1.6 billion (B) in ARRA funding to be applied to cleanup projects at the Hanford Site. DOE-RL selected projects to receive ARRA funding based on 3-criteria: creating/saving jobs, reducing the footprint of the Hanford Site, and reducing life-cycle costs for cleanup. They further selected projects that were currently covered under regulatory documents and existing prime contracts, which allowed work to proceed quickly. CH2M HILL Plateau Remediation Company (CHPRC) is a prime contractor to the DOE focused on the environmental cleanup of the DOE Hanford Site Centralmore » Plateau. CHPRC was slated to receive $1.36B in ARRA funding. As of January, 2010, CHPRC has awarded over $200 million (M) in subcontracts (64% to small businesses), created more that 1,100 jobs, and touched more than 2,300 lives - all in support of long-term objectives for remediation of the Central Plateau, on or ahead of schedule. ARRA funding is being used to accelerate and augment cleanup activities already underway under the baseline Plateau Remediation Contract (PRC). This paper details challenges and accomplishments using ARRA funding to meet DOE-RL objectives of creating/saving jobs, expediting cleanup, and reducing lifecycle costs for cleanup during the first months of implementation.« less