Title: Regional Transmission Planning: A review of practices following FERC Order Nos. 890 and 1000

Abstract

Federal Energy Regulatory Commission (FERC) Order Nos. 890 and 10001 established requirements that transmission planning regions must follow in regional transmission planning and allocating the costs of new transmission facilities. Order No. 890, issued in 2007, outlined general requirements for local as well as regional transmission planning practices and procedures. Order No. 1000, issued in 2011, laid out specific requirements for: (1) regional transmission planning; (2) consideration of transmission needs driven by public policy requirements; (3) non-incumbent transmission development; (4) interregional transmission coordination; and (5) cost allocation for transmission facilities that have been selected in a regional transmission plan for purposes of cost allocation. This report reviews how these FERC orders are being implemented by the 12 transmission planning regions recognized by FERC.

Authors:
 [1];  [1]
  1. Lawrence Berkeley National Lab. (LBNL), Berkeley, CA (United States)
Publication Date:
Research Org.:
Lawrence Berkeley National Lab. (LBNL), Berkeley, CA (United States)
Sponsoring Org.:
USDOE Office of Electricity Delivery and Energy Reliability (OE)
OSTI Identifier:
1411666
Report Number(s):
LBNL-2001079
ark:/13030/qt5qc499jd
DOE Contract Number:
AC02-05CH11231
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
24 POWER TRANSMISSION AND DISTRIBUTION; 29 ENERGY PLANNING, POLICY, AND ECONOMY

Citation Formats

Eto, Joseph H., and Gallo, Guilia. Regional Transmission Planning: A review of practices following FERC Order Nos. 890 and 1000. United States: N. p., 2017. Web. doi:10.2172/1411666.
Eto, Joseph H., & Gallo, Guilia. Regional Transmission Planning: A review of practices following FERC Order Nos. 890 and 1000. United States. doi:10.2172/1411666.
Eto, Joseph H., and Gallo, Guilia. Wed . "Regional Transmission Planning: A review of practices following FERC Order Nos. 890 and 1000". United States. doi:10.2172/1411666. https://www.osti.gov/servlets/purl/1411666.
@article{osti_1411666,
title = {Regional Transmission Planning: A review of practices following FERC Order Nos. 890 and 1000},
author = {Eto, Joseph H. and Gallo, Guilia},
abstractNote = {Federal Energy Regulatory Commission (FERC) Order Nos. 890 and 10001 established requirements that transmission planning regions must follow in regional transmission planning and allocating the costs of new transmission facilities. Order No. 890, issued in 2007, outlined general requirements for local as well as regional transmission planning practices and procedures. Order No. 1000, issued in 2011, laid out specific requirements for: (1) regional transmission planning; (2) consideration of transmission needs driven by public policy requirements; (3) non-incumbent transmission development; (4) interregional transmission coordination; and (5) cost allocation for transmission facilities that have been selected in a regional transmission plan for purposes of cost allocation. This report reviews how these FERC orders are being implemented by the 12 transmission planning regions recognized by FERC.},
doi = {10.2172/1411666},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Wed Nov 15 00:00:00 EST 2017},
month = {Wed Nov 15 00:00:00 EST 2017}
}