The EPRI/DOE High-Burnup Confirmatory Data Project (herein called the “Demo”) is a multi-year, multi-entity test with the purpose of providing quantitative and qualitative data to show if high-burnup fuel mechanical properties change in dry storage over a ten-year period. The Demo involves obtaining 32 assemblies of high-burnup PWR fuel of common cladding alloys from the North Anna Nuclear Power Plant, loading them in an NRC-licensed TN-32B cask, drying them according to standard plant procedures, and then storing them on the North Anna dry storage pad for ten years. After the ten-year storage time, the cask will be opened and the mechanical properties of the rods will be tested and analyzed.

Authors:
 [1];  [1];  [2];  [2];  [2];  [2];  [2];  [2];  [3];  [4];  [4];  [4]
  1. Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)
  2. Pacific Northwest National Lab. (PNNL), Richland, WA (United States)
  3. Argonne National Lab. (ANL), Argonne, IL (United States)
  4. Oak Ridge National Lab. (ORNL), Oak Ridge, TN (United States)
Publication Date:
Research Org.:
Sandia National Lab. (SNL-NM), Albuquerque, NM (United States)
Sponsoring Org.:
USDOE Office of Nuclear Energy (NE), Fuel Cycle Technologies (NE-5)
OSTI Identifier:
1395752
Report Number(s):
SAND-2017-10310R
657245
DOE Contract Number:
AC04-94AL85000
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS

Citation Formats

Saltzstein, Sylvia J., Sorenson, Ken B., Hanson, B. D., Shimskey, R. W., Klymyshyn, N. A., Webster, R. A., Jensen, P. J., MacFarlan, P. J., Billone, Mike, Scaglione, John, Montgomery, Rose, and Bevard, Bruce. EPRI/DOE High-Burnup Fuel Sister Rod Test Plan Simplification and Visualization. United States: N. p., 2017. Web. doi:10.2172/1395752.
Saltzstein, Sylvia J., Sorenson, Ken B., Hanson, B. D., Shimskey, R. W., Klymyshyn, N. A., Webster, R. A., Jensen, P. J., MacFarlan, P. J., Billone, Mike, Scaglione, John, Montgomery, Rose, & Bevard, Bruce. EPRI/DOE High-Burnup Fuel Sister Rod Test Plan Simplification and Visualization. United States. doi:10.2172/1395752.
Saltzstein, Sylvia J., Sorenson, Ken B., Hanson, B. D., Shimskey, R. W., Klymyshyn, N. A., Webster, R. A., Jensen, P. J., MacFarlan, P. J., Billone, Mike, Scaglione, John, Montgomery, Rose, and Bevard, Bruce. 2017. "EPRI/DOE High-Burnup Fuel Sister Rod Test Plan Simplification and Visualization". United States. doi:10.2172/1395752. https://www.osti.gov/servlets/purl/1395752.
@article{osti_1395752,
title = {EPRI/DOE High-Burnup Fuel Sister Rod Test Plan Simplification and Visualization},
author = {Saltzstein, Sylvia J. and Sorenson, Ken B. and Hanson, B. D. and Shimskey, R. W. and Klymyshyn, N. A. and Webster, R. A. and Jensen, P. J. and MacFarlan, P. J. and Billone, Mike and Scaglione, John and Montgomery, Rose and Bevard, Bruce},
abstractNote = {The EPRI/DOE High-Burnup Confirmatory Data Project (herein called the “Demo”) is a multi-year, multi-entity test with the purpose of providing quantitative and qualitative data to show if high-burnup fuel mechanical properties change in dry storage over a ten-year period. The Demo involves obtaining 32 assemblies of high-burnup PWR fuel of common cladding alloys from the North Anna Nuclear Power Plant, loading them in an NRC-licensed TN-32B cask, drying them according to standard plant procedures, and then storing them on the North Anna dry storage pad for ten years. After the ten-year storage time, the cask will be opened and the mechanical properties of the rods will be tested and analyzed.},
doi = {10.2172/1395752},
journal = {},
number = ,
volume = ,
place = {United States},
year = 2017,
month = 9
}

Technical Report:

Save / Share:
  • The EPRI/DOE High Burnup Confirmatory Data Project (herein called the "Demo") is a multi-year, multi-entity confirmation demonstration test with the purpose of providing quantitative and qualitative data to show how high-burnup fuel ages in dry storage over a ten-year period. The Demo involves obtaining 32 assemblies of high-burnup PWR fuel of four common cladding alloys from the North Anna Nuclear Power Plant, drying them according to standard plant procedures, and then storing them in an NRC-licensed TN-3 2B cask on the North Anna dry storage pad for ten years. After the ten-year storage time, the cask will be opened andmore » the rods will be examined for signs of aging. Twenty-five rods from assemblies of similar claddings, in-reactor placement, and burnup histories (herein called "sister rods") have been shipped from the North Anna Nuclear Power Plant and are currently being nondestructively tested at Oak Ridge National Laboratory. After the non-destructive testing has been completed for each of the twenty-five rods, destructive analysis will be performed at ORNL, PNNL, and ANL to obtain mechanical data. Opinions gathered from the expert interviews, ORNL and PNNL Sister Rod Test Plans, and numerous meetings has resulted in the Simplified Test Plan described in this document. Some of the opinions and discussions leading to the simplified test plan are included here. Detailed descriptions and background are in the ORNL and PNNL plans in the appendices . After the testing described in this simplified test plan h as been completed , the community will review all the collected data and determine if additional testing is needed.« less
  • This test plan describes the experimental work to be implemented by the U.S. Department of Energy (DOE) Office of Nuclear Energy (NE) to characterize high burnup (HBU) spent nuclear fuel (SNF) in conjunction with the High Burnup Dry Storage Cask Research and Development Project and serves to coordinate and integrate the multi-year experimental program to collect and develop data regarding the continued storage and eventual transport of HBU (i.e., >45 GWd/MTU) SNF. The work scope involves the development, performance, technical integration, and oversight of measurements and collection of relevant data, guided by analyses and demonstration of need.
  • The High Burnup Spent Fuel Data project pulled 25 sister rods (9 from the project assemblies and 16 from similar HBU assemblies) for characterization. The 25 sister rods are all high burnup and cover the range of modern domestic cladding alloys. The 25 sister rods were shipped to Oak Ridge National Laboratory (ORNL) in early 2016 for detailed non-destructive and destructive examination. Examinations are intended to provide baseline data on the initial physical state of the cladding and fuel prior to the loading, drying, and long-term dry storage process. Further examinations are focused on determining the effects of temperatures encounteredmore » during and following drying. Similar tests will be performed on rods taken from the project assemblies at the end of their long-term storage in a TN-32 dry storage cask (the cask rods ) to identify any significant changes in the fuel rods that may have occurred during the dry storage period. Additionally, some of the sister rods will be used for separate effects testing to expand the applicability of the project data to the fleet, and to address some of the data-related gaps associated with extended storage and subsequent transportation of high burnup fuel. A draft test plan is being developed that describes the experimental work to be conducted on the sister rods. This paper summarizes the draft test plan and necessary coordination activities for the multi-year experimental program to supply data relevant to the assessment of the safety of long-term storage followed by transportation of high burnup spent fuel.« less
  • This test plan is a Level-2 document as defined in the Fissile Materials Disposition Program Light-Water Reactor Mixed-Oxide Fuel Irradiation Test Project Plan. The planned post-irradiation examination (PIE) work to be performed on the mixed uranium and plutonium oxide fuel capsules that have received burnups of approximately 30 GWd/MT is described. The major emphasis of this PIE task will be material interactions, particularly indications of gallium transport and interactions. This PIE will include gamma scanning, ceramography, metallography, pellet radial gallium analysis, and clad gallium analysis. A preliminary PIE report will be generated before all the work is completed so thatmore » the progress of the fuel irradiation may be known in a timely manner.« less
  • A batch of high-burnup fuel from the Fast Flux Test Facility (FFTF) was processed in the Solvent Extraction Test Facility (SETF) during Campaign 9. The fuel had a burnup of {similar_to}0 MWd/kg and a cooling time of {similar_to} year. Two runs were made with this fuel; in the first, the solvent contained 30% tri-n-butyl phosphate (TBP) and partitioning of the uranium and plutonium was effected by reducing the plutonium with hydroxylamine nitrate (HAN); in the second, the solvent contained 10% TBP and a low operating temperature was used in an attempt to partition without reducing the plutonium valence. The plutoniummore » reoxidation problem, which was present in previous runs that used HAN, may have been solved by lowering the temperature and acidity in the partition contactor. An automatic control system was used to maintain high loadings of heavy metals in the coextraction-coscrub contactor in order to increase its efficiency while maintaining low losses of uranium and plutonium to the aqueous raffinate. An in-line photometer system was used to measure the plutonium concentration in an intermediate extraction stage; and based on this data, a computer algorithm determined the appropriate adjustments in the addition rate of the extractant. The control system was successfully demonstrated in a preliminary run with purified uranium. However, a variety of equipment and start up problems prevented an extended demonstration from being accomplished during the runs with the FFTF fuel.« less