Title: Release Report for Building Debris for TA-21 Sewage Treatment Facility

Abstract

ENV-ES finds that the materials associated with TA-21 Buildings 227 (superstructure only), and 229 (see Figure 1) meet the criteria for unrestricted release to the public for recycle or as sanitary/commercial waste. The interior and exterior of the metal shed, building 387, passed the release criteria collectively; however, results from the roof of the structure were above reference background measurements. Waste management should be consulted for waste disposition options for the roofing metal. These findings are consistent with the requirements of DOE Order 458.1 “Radiation Protection of the Public and the Environment” and LANL Policy 412 “Environmental Radiation Protection.” Sampling and data analysis, as described in this report, were sufficient to meet measurement objectives under the Multi-Agency Radiation Survey and Assessment of Materials and Equipment (MARSAME) manual (2009).

Authors:
 [1];  [1];  [1]
  1. Los Alamos National Lab. (LANL), Los Alamos, NM (United States)
Publication Date:
Research Org.:
Los Alamos National Lab. (LANL), Los Alamos, NM (United States)
Sponsoring Org.:
USDOE National Nuclear Security Administration (NNSA)
OSTI Identifier:
1356117
Report Number(s):
LA-UR-17-23637
DOE Contract Number:
AC52-06NA25396
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; Demolition/Decontamination/Decommissioning; Environmental Protection

Citation Formats

Whicker, Jeffrey Jay, Gillis, Jessica, and Ruedig, Elizabeth. Release Report for Building Debris for TA-21 Sewage Treatment Facility. United States: N. p., 2017. Web. doi:10.2172/1356117.
Whicker, Jeffrey Jay, Gillis, Jessica, & Ruedig, Elizabeth. Release Report for Building Debris for TA-21 Sewage Treatment Facility. United States. doi:10.2172/1356117.
Whicker, Jeffrey Jay, Gillis, Jessica, and Ruedig, Elizabeth. Wed . "Release Report for Building Debris for TA-21 Sewage Treatment Facility". United States. doi:10.2172/1356117. https://www.osti.gov/servlets/purl/1356117.
@article{osti_1356117,
title = {Release Report for Building Debris for TA-21 Sewage Treatment Facility},
author = {Whicker, Jeffrey Jay and Gillis, Jessica and Ruedig, Elizabeth},
abstractNote = {ENV-ES finds that the materials associated with TA-21 Buildings 227 (superstructure only), and 229 (see Figure 1) meet the criteria for unrestricted release to the public for recycle or as sanitary/commercial waste. The interior and exterior of the metal shed, building 387, passed the release criteria collectively; however, results from the roof of the structure were above reference background measurements. Waste management should be consulted for waste disposition options for the roofing metal. These findings are consistent with the requirements of DOE Order 458.1 “Radiation Protection of the Public and the Environment” and LANL Policy 412 “Environmental Radiation Protection.” Sampling and data analysis, as described in this report, were sufficient to meet measurement objectives under the Multi-Agency Radiation Survey and Assessment of Materials and Equipment (MARSAME) manual (2009).},
doi = {10.2172/1356117},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Wed May 03 00:00:00 EDT 2017},
month = {Wed May 03 00:00:00 EDT 2017}
}

Technical Report:

Save / Share:
  • An exhaust air filter building contaminated with /sup 227/Ac was decommissioned at the Los Alamos National Laboratory, Los Alamos, New Mexico, in 1978. The building was constructed in the late 1940s to clean exhaust air from several buildings at TA-21, DP Site. It was in service until March 1970. The project involved preliminary decontamination, dismantling the building, and burying the debris at an on-site waste disposal/storage area. This report presents the details on the decommissioning procedures, health physics, waste management, environmental surveillance, and costs for the operation.
  • The Idaho Cleanup Project has prepared this interim control strategy for the U.S. Department of Energy Idaho Operations Office pursuant to DOE Order 5400.5, Chapter 11.3e (1) to support continued discharges to the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond. In compliance with DOE Order 5400.5, a 2-year review of the Interim Control Strategy document has been completed. This submittal documents the required review of the April 2005 Interim Control Strategy. The Idaho Cleanup Project's recommendation is unchanged from the original recommendation. The Interim Control Strategy evaluates three alternatives: (1) re-route the discharge outlet to an uncontaminatedmore » area of the TSF-07; (2) construct a new discharge pond; or (3) no action based on justification for continued use. Evaluation of Alternatives 1 and 2 are based on the estimated cost and implementation timeframe weighed against either alternative's minimal increase in protection of workers, the public, and the environment. Evaluation of Alternative 3, continued use of the TSF-07 Disposal Pond under current effluent controls, is based on an analysis of four points: - Record of Decision controls will protect workers and the public - Risk of increased contamination is low - Discharge water will be eliminated in the foreseeable future - Risk of contamination spread is acceptable. The Idaho Cleanup Project recommends Alternative 3, no action other than continued implementation of existing controls and continued deactivation, decontamination, and dismantlement efforts at the Test Area North/Technical Support Facility.« less
  • This phase report summarizes the results of field investigations conducted in 1992 at Technical Area 21 of Los Alamos National Laboratory, as prescribed by the RCRA Facility Investigation work plan for the Technical Area 21 operable unit (also known as OU 1106). This phase report is the last part of a three-part phase report describing the results of field work conducted in 1992 at this operable unit. Phase Report lA, issued on l4 June l993, summarized site geologic characterization activities. Phase report 1B, issued on 28 January 1994, included an assessment of site-wide surface soil background, airborne emissions deposition, andmore » contamination in the locations of two former air filtration buildings. The investigations assessed in Phase Report 1C include field radiation surveys and surface and near-surface sampling to characterize potential contamination at 25 outfalls and septic systems listed as SWMUs in the RFI work plan. Based on the RFI data, it is recommended that no further action is warranted for 8 SWMUs and further action is recommended for 3 SWMUs addressed in this phase report. For 14 SWMUs which represent no immediate threat to human health or environment, deferral of further action/no further action decisions is recommended until outstanding analytical data are received, sampling of adjacent SWMUs is completed, or decisions are made about the baseline risk assessment approach.« less
  • This report summarizes the sampling design used, associated statistical assumptions, as well as general guidelines for conducting post-sampling data analysis. Sampling plan components presented here include how many sampling locations to choose and where within the sampling area to collect those samples. The type of medium to sample (i.e., soil, groundwater, etc.) and how to analyze the samples (in-situ, fixed laboratory, etc.) are addressed in other sections of the sampling plan.